[2025] WASC 399
General information, not legal advice.
Supreme Court of WA
2025-09-23
Palmer J
Original judgment source is linked above.
(a) the field of specialised knowledge of the proposed expert;
(b) the specific questions to be posed;
(c) the assumptions that the experts were being asked to make in providing their opinion; and
(d) the facts relevant to each expert opinion.
And so if your Honour [sic] not minded to simply impose a short deadline for the plaintiffs to put on whatever expert evidence they have and then allow them, obviously, the opportunity to address deficiencies in a transparent way, then the realistic option is vacation of the trial dates. Our friends say nothing about it, but that's in reality where the matter is potentially heading.[1]
My current thinking in relation to the expert evidence is that I am disinclined to vacate the trial dates today. I think that there is still the possibility that the matter can be righted and it is possible for there to be a trial, but I acknowledge that increasingly this is looking difficult.[2]
I don't think if it was necessary to adjourn the trial we are talking months or years or anything like that, but that said, this has been set down for trial in October with the consent of the parties, and in my view we should do everything that we can to maintain those trial dates. That's an appropriate use of court resources, and we should endeavour to do that...[3]
Based on the answers to question [7] above:
...
8.2 given all relevant prevailing market conditions and circumstances, would parties in the position of [the first defendant and the plaintiff] have raised the funding (whether debt or equity or both) necessary, and at the times necessary, to proceed with the project?
(emphasis added)
The Kl deposit is sited under a historical pit with backfilled tailings material from the historical Marymia processing plant, comprising approximately 1,000,000 m3 of tailings across Kl, KISE and minor laterite pits. The KISE pit is completely backfilled and the Kl pit is backfilled to a depth of approximately 20 metres above the final pit floor.
(a) immediately following the Commencement Date, it had more than $3 million cash in the bank; and
>
> (b) it held cash in the bank throughout the extended Earn-in Period between $3,283,652 as at the 31 March 2017 to $1,489,763 as at 30 September 2019,376 to enable it to contribute to Expenditure.377
Why the defendants should have leave to amend the defence
7.1 what activities were required to bring any one or more of the deposits on the Tenement (and the K2 Area, if applicable) to the point of being an operational mine?
7.2 for each activity given in answer to question 7.1 above, how long would it have taken to complete the activity?
7.3 based on your answers to questions 7.1 and 7.2 above:
7.3.1 when was the earliest time that any of the deposits on the Tenement (and the K2 Area, if applicable) could have been brought into production as an operating mine?
7.3.2 at what likely cost, overall, could the deposits on the Tenement (and the K2 Area, if applicable) have been brought into production as an operating mine?
7.4 what activities would have had to occur during the production and operational phase for the Tenement (and the K2 Area, if applicable)?
7.5 in relation to the treatment of ore by the JVA:
7.5.1 were any of the following options practical and economically viable, namely:
(a) assuming Billabong Gold Pty Ltd (Billabong) was open to entering into a new ore treatment agreement with Vango, negotiating and entering into a new ore treatment agreement with Billabong and using its processing plant;
(b) assuming Billabong was not open to entering into a new ore treatment agreement:
(i) acquiring and using a substitute second-hand ore processing plant;
(ii) identifying and using an alternative third-party small- scale processing plant; or
(iii) building and using a small-scale processing plant;
7.6 for each of the Options, how long would it have taken to complete each activity given in answer to question 7.4 above?
7.7.2 (if applicable) each contiguous tenement comprising the K2 Area.
In answering question 7.7, please provide the estimated periodic production volume (in ounces) (if any) in the form of an Excel spreadsheet, including the gold price, extraction cost for each of the Options and cut-off grade, and identify which of the following gold production milestones would have been achieved (if any) and the earliest time each of them would have been achieved:
7.8 based on your answers to questions 7.1 to 7.6 above, and taking into account the likely operational and production costs (also the subject of question 7.10 below), as well as all relevant prevailing market conditions and circumstances and the production of gold on an economic basis, what (if any) amount of gold (in ounces) would have been produced during the production and operational phase for:
7.8.2 (if applicable) each contiguous tenement comprising the K2 Area.
In answering question 7.8, please provide the estimated periodic production volume (in ounces) (if any) in the form of an Excel spreadsheet, including the gold price, extraction cost for each of the Options and cut-off grade, and identify which of the following gold production milestones would have been achieved (if any) and the earliest time each of them would have been achieved:
7.9.2 what would have been the overall cost likely incurred during the production and operational phase for the Tenement (and the K2 Area, if applicable)?
7.10.1 what is the estimated cost of each activity?
7.10.2 what would have been the overall cost likely incurred during the production and operational phase for the Tenement (and the K2 Area, if applicable)?
7.11 what activities would have had to occur for mine closure for the Tenement (and the K2 Area, if applicable)?
7.12 for each activity given in answer to question 7.11 above, how long would it have taken to complete the activity?
7.13.1 what is the estimated cost of each activity?
7.13.2 what would have been the cost likely incurred, overall, for mine closure for the Tenement (and the K2 Area, if applicable)?
8.1 what would have been the JVA's likely estimated return on investment?
8.2 given all relevant prevailing market conditions and circumstances, would parties in the position of Vango and Zuleika have raised the funding (whether debt or equity or both) necessary, and at the times necessary, to proceed with the project?
I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.
[5] Plaintiff's outline of submissions dated 9 September 2025 (Plaintiff's submissions), par 8.
[6] Defendants' submissions in opposition to the Plaintiff's disallowance/strike out Application (Defendants' submissions), par 20.