Zoro Developments Pty Ltd v Northern Beaches Council
[2023] NSWLEC 1566
At a glance
Source factsCourt
Land and Environment Court (NSW)
Decision date
2023-09-18
Source
Original judgment source is linked above.
Judgment (16 paragraphs)
Judgment
- COMMISSIONER: A partially constructed building at 67 Seaforth Crescent, Seaforth, has stood largely undisturbed since the issue of a stop work order in early 2020. The applicant and owner of the land, Zoro Developments Pty Ltd (Zoro) seeks to modify a development consent that applies to the site, which will, in turn, allow works to be carried out to the building. Zoro lodged a modification application with Northern Beaches Council (the Council) on 20 April 2022. Following the expiry of the period after which a modification application is deemed to be refused, Zoro lodged these appeal proceedings, pursuant to s 8.9 of the Environmental Planning and Assessment Act 1979 (EPA Act).
- The proceedings were required to be listed for a conciliation conference in accordance with s 34AA of the Land and Environment Court Act 1979 (LEC Act). The conciliation conference commenced on site on 14 March 2023. On that date, I made a determination the proceedings were not to continue to be dealt with under s 34AA(2). The proceedings were then listed by the Registrar for a court hearing on 18 September 2023.
- The proposed modification is to the development consent (DA127/06) granted on 15 October 2007 for the construction of a new detached dwelling with double car hard stand, inclinator and landscaping. The modification application was amended prior to the hearing, and is now confined to changes to the inclinator landing and stair access on the western side of the dwelling, a proposal for a window on the western elevation in lieu of the door approved by the consent, and the introduction of new open timber stairs with open timber balustrade at the rear of the property, where the property fronts Middle Harbour.
- The Council now agrees that the modification application can be granted, and the consent modified as proposed. It accepts that each of the contentions initially raised in its Statement of Facts and Contentions have been dealt with. For the reasons that are set out below, I accept the parties' agreed position that the application can be granted.