Zauner Construction Pty Ltd v No 2 Pitt Street Pty Ltd [2001] VSC 154
[2001] VSC 154
At a glance
Source factsCourt
Supreme Court of Victoria
Decision date
2001-05-18
Before
Byrne J
Source
Original judgment source is linked above.
Judgment (37 paragraphs)
[2001] VSC 154
CONTRACT - building contract - progress claim - late certificate - obligation to pay amount claimed - subsequent valid certificate - obligation to pay amount certified less previous payments. AS2124-1992, cll. 42.1, 44.9
- The plaintiff, Zauner Construction Pty Ltd ("the contractor"), by summons filed on 6 April 2001 seeks summary judgment in this proceeding for various sums claimed in the alternative. The application is made after delivery of a defence and counterclaim filed on 5 March 2001. The contractor, therefore, relies on admissions contained in this pleading as well as on the affidavits of Gary Christopher Zauner sworn 5 April 2001 and 6 April 2001 respectively. Affidavits in opposition of Dennis Thomas Bubke and Kylea Robina Anderson were both sworn on 1 May 2001. The sums sought represent uncertified progress claims under a building contract, late certified progress claims and one certified sum. Before I turn to these claims and certificates it is necessary that I set out the facts of this case which contain some very unusual features.