[2001] VSC 154
Supreme Court of Victoria
2001-05-18
Byrne J
Original judgment source is linked above.
[2001] VSC 154
CONTRACT - building contract - progress claim - late certificate - obligation to pay amount claimed - subsequent valid certificate - obligation to pay amount certified less previous payments. AS2124-1992, cll. 42.1, 44.9
The November and subsequent payments were not made by the due dates or at all.
"4.1 If: (a) the Principal fails to perform on time and in full any of the obligations referred to in clause 2.2 above; or (b) the balance of moneys in the Account is at any time less than the value of the claims for certified payment submitted by the Contractor under the Construction Agreement which are at that time unpaid by the Principal; then the Principal and the Contractor agree that despite any other provision of the Construction Agreement or this Deed, the Contractor may at any time and without further notice: (c) suspend the whole or any part of the work under the Construction Agreement; and (d) exercise any of the other rights referred to in clause 44.9 of the Construction Agreement; as if the Principal had failed to show reasonable cause why the Contractor should not exercise a right referred to in clause 44.9 by the time specified in a Notice under clause 44.7. 4.2 The parties acknowledge that the rights conferred by clause 4.1 are continuing rights solely for the benefit of the Contractor and any failure or delay by the Contractor in exercising the rights conferred by clause 4.1 will not amount to a waiver, an estoppel or otherwise limit or reduce the rights of the Contractor pursuant to clause 4.1 above."
"44.9 Rights of the Contractor If by the time specified in a notice under Clause 44.7 the Principal fails to show reasonable cause why the Contractor should not exercise a right referred to in Clause 44.9, the Contractor may by notice in writing to the Principal suspend the whole or any part of the work under the Contract. The Contractor shall lift the suspension if the Principal remedies the breach but if within 28 days after the date of suspension under Clause 44.9, the Principal fails to remedy the breach or, if the breach is not capable of remedy, fails to make other arrangements to the reasonable satisfaction of the Contractor, the Contractor may by notice in writing to the Principal terminate the Contract. The Contractor shall be entitled to recover from the Principal any damages incurred by the Contractor by reason of the suspension."
# These are the dates verified by Mr Zauner. The superintendent's letters enclosing the certificates in response assert that the claims were received later and on dates which would have the consequence that only certificates 2, 3, 5, 6, 7, and 15 were issued after the date stipulated in the building contract. There is, however, no evidence that the superintendent is correct in these assertions and I have not had regard to them.
"Where the Contractor has been granted an Extension of Time under Clause 35.5, for an event specified in Appendix A in respect of which payment of extra costs has been granted, the Principal shall pay to the Contractor the daily amount specified for that separable portion as stated in monetary provisions section of the bills of quantities. Nothing in Clause 36 shall - (a) oblige the Principal to pay extra costs for delay or disruption which have already been included in the value of a variation or any other payment under the Contract; or (b) limit the Principal's liability for damages for breach of contract. The Contractor will not be entitled to recover any monetary compensation from the Principal because of or relating to any delay in reaching Practical Completion unless all of the following conditions have been satisfied, namely: (i) the delay was caused by an event of the type described in Annexure Part A; (ii) the Contractor has claimed an extension of time in respect of the delay in strict accordance with the provisions of Clause 35.5; (iii) an extension of time has been granted under Clause 35.5 in respect of delay; (iv) no monetary compensation in respect of the delay has been included in the value of any variation carried out by the Contractor and no such compensation is payable to the Contractor under any other provision of the Contract. The Contractor acknowledges that the amount calculated is a genuine pre-estimate of the Contractor's likely costs, loss and damage resulting from a delay in reaching Practical Completion caused by an event of the type described in Annexure Part A and will be the Contractor's sole remedy against the Principal for monetary compensation for that delay and will be in full satisfaction of all claims, demands, actions, proceedings, or suits (including claims for damages) which the Contractor may have or make against the Principal arising out of or concerning that delay."
"(iv) variations directed under Clause 40; ... (x) any breach of the Contract by the Principal."
Again, this determination of the value of work performed supersedes the contractor's valuation of the work included in its claim 18 and in claims 15, 16 and 17 which preceded it. No argument was presented for any entitlement under the uncertified claim 20.
[2] Daysea Pty Ltd v Watpac Aust Pty Ltd [2001] QCA 49.
[3] Algons Engineering Pty Ltd v Abigroup Contractors Pty Ltd (1997) 14 BCL 215.
[4] [2001] QCA 49 at [31].
Zauner Construction Pty Ltd
No 2 Pitt Street Pty Ltd [2001] VSC 154