14 The essence of the judgment debtor's submission in support of the application for a suspension order was that the issue of the Final Certificate had fundamentally changed the context in which the Determination is to be enforced. The net result of the Final Certificate was that the judgment creditor became liable to pay the judgment debtor a sum of $23,870.25. The judgment debtor further submitted that the issues in relation to the judgment creditor's Claim No. 9, which became the subject of the Determination, had been considered by the superintendent in preparing the Final Certificate. In effect, the submission was that it would be unjust to require the judgment debtor to pay the judgment creditor a sum of $152,967.16, in effect as an advance payment on the account (see CCA s 40), in circumstances where the final balance under the contract had been determined, not as an amount owing by the judgment debtor to the judgment creditor, but as an amount owing by the judgment creditor to the judgment debtor.