41 It is clear from Latoudis v Casey that the successful defendant in summary proceedings should obtain an order for costs in respect of those issues on which the defendant succeeds; that a successful defendant cannot be deprived of his or her costs because the charge is brought in the public interest or by a public official; or because the charge is serious; or because the informant acted reasonably in instituting the proceedings or might be deterred from laying charges in the future if he or she was ordered to pay costs; and, costs are not awarded by way of punishment of the unsuccessful party but rather the function of a costs order is compensatory.
42 In the present case, whilst the appellant laid five separate charges against the respondent, it seems to me that in prosecuting the charges the appellant took a holistic approach and regarded the events of 28 and 29 November as constituting a series of closely interconnected events such that the events of 28 November could not be separated from the events of 29 November. In opening the case for the prosecution before Peterson J, senior counsel for the prosecutor described the incident on 28 November and alleged the kibble dropped about "four feet", striking the scaffold and narrowly missing workers on the scaffold. Senior counsel submitted:
Unfortunately, that near death experience by the men was wasted because the next day there was a mere (sic - near?) repetition of this incident and it had fatal consequences...
Significantly, no lessons had been learned from the incident of 28 November. That incident, and our case will be, should have sounded the alarm bells...
43 Further, senior counsel for the appellant submitted it was necessary for the prosecution at first instance in the sentencing proceedings to bring evidence in relation to what occurred on both 28 and 29 November; what happened on 29 November had to be adduced for the purpose of a successful prosecution of the 28 November charge. Mr Agius SC for the appellant submitted in this regard:
Now our submission to Schmidt J was that in relation to the 28th and the 29th as against Leightons, it was necessary for the prosecution to call such evidence as there was as to how it came about that the crane fell over and that that evidence would have had to be called in any event and it wasn't simply a matter of proving what the system of work was that Leightons had in place on 28 November. Now our submission was rejected by her Honour and we say that her Honour ought not to have rejected that submission. In relation to 28 November, if we had simply proved the factual circumstance of the moving about of the kibble and the ponder (sic) weight, it coming into contact with the scaffold and the obvious danger to the workers there without calling any evidence at all about the structure and integrity of the crane, given that that crane had fallen over the next day on the 29th, we would have been met with a s53 defence. We would have been not able to negate an inference, or meet a suggestion that what happened on the 28th was no more than a precursor to what was going to happen on the 29th, that there was something else going on with this crane or the way that it was being driven, or what we have in the Markload system, or the improper graduations on the gauge which Leightons had no responsibility for and that this had some cause in the event on 28 November.
So it's our submission, and we had made this submission to Schmidt J and we make it again, that in relation to the incident of the 28th, given what happened to the crane on the 29th, that's when it fell over, we would always be going to be litigating the issue as to how it came about that the crane fell over. Was there any other structural problem with the crane? Was it a matter of driver error on the 28th and/or on the 29th? Was it some matter of some fault with the crane which Lindores was responsible? We could not have avoided calling that evidence in the case against Leightons.
Now her Honour found against us, but she doesn't give any reason for that finding at all. She simply says "I don't accept that", but in doing so, her Honour has failed, in our respectful submission, to take any cognizance of the likelihood of s53 defence, or to take any cognizance of what we, in the likelihood, would be met with if we had simply sought to prove without calling any evidence about structural integrity or otherwise of the crane, simply sought to prove the unsafe system of work on the 28th.
44 The effect of the appellant's approach to prosecuting the charges was that the respondent had no choice but to prepare and present its case to meet that presented by the appellant. The respondent was put to the cost of meeting a case that consisted of five interconnected charges. The appellant failed in making out four of those charges. On the authority of Latoudis v Casey there is a strong case for holding the respondent should have its costs.
45 If it had been the case that the appellant had succeeded on four of the charges and had failed in making out the fifth charge, it is probable costs would have been awarded to the appellant on an apportionment basis with the respondent left to pay its own costs in respect of that charge where the prosecution had failed. Such an outcome would, in my opinion, have been uncontroversial (see, for example, O'Sullivan where the prosecutor was awarded 70 per cent of the costs but the defendant was awarded nothing, notwithstanding that two charges were dismissed). That the respondent successfully defended four of the charges but was found guilty of the fifth charge, provides no compelling basis to favour the appellant by giving it its costs in respect of the fifth charge where, if the situation had been reversed, the respondent would probably not have been awarded costs for its successful defence of one of the five charges.
46 A relevant consideration, however, would be if the charge in respect of which the appellant had been successful constituted the bulk of the trial proceedings and the other four charges were subsidiary or in relation to which the respondent would have needed to spend little time. In other words, if the charge relating to the events of 28 November was the central issue in the proceedings and most of the parties' preparation and presentation was consumed by having to concentrate on that charge, a different outcome in terms of cost might be warranted.
47 Because of the manner in which the appellant prosecuted the case at first instance, that is, in not seeking to differentiate in the presentation of evidence between the events of 28 November and those of 29 November, because there were overlapping charges in relation to 28 and 29 November (see IRC00/234 and IRC00/236) and because it was a joint trial of the two defendants (Leighton and Lindores), it is impossible to determine a satisfactory split between the time taken in respect of the charge relating to 28 November and the charges relating to 29 November. However, I note what Mr Agius conceded, namely, that:
What took time in the case was the essential issue as to how it came about that the crane had actually collapsed on 29 November. A great deal of time was spent on that.
48 The next logical question then might be whether or not what occurred on 29 November had any relevance in respect of the events of 28 November and whether much of the evidence led by the appellant in relation to 29 November needed to have been led in relation to 28 November. If not, it would serve to reinforce a conclusion that, on appeal, there should be no interference with her Honour's costs order. On the other hand, if the evidence about the crane's collapse was necessary to make out the charge on 28 November and to deal with the prospect of a submission by the respondent relying on defences under s 53 of the Act, the apportionment of costs ordered by her Honour may not have been just and reasonable.
49 On one view of it, however, the question need not be answered. Having chosen to conduct its case the way it did by effectively rolling up all of the charges into a series of interdependent or interconnecting occurrences, making it impossible to separate out from the proceedings the time taken up in respect of the charge relating to 28 November, it is arguable there is no proper basis for now awarding costs to the appellant in relation to IRC00/236. In other words, having decided that it needed to bring evidence about the crane's collapse and its causes to make out its case in respect of both the 28 and 29 November charges, and having not been successful on four of the five charges, the appellant cannot now complain about an apportionment approach to costs where the respondent is given 75 per cent of its costs.
50 The appellant submitted, however, it was bound to explore every reasonable avenue for prosecution of those who might have been responsible for a breach of the occupational health and safety laws; that in the present case all of the evidence adduced to support the 28 November charge was necessary. Reference was made to WorkCover Authority of NSW (Inspector Dawson) v Plastachem Pty Ltd (2001) IR 110 IR 351where at [61] the Full Bench observed:
The appellant doubtless had a responsibility to conduct a full investigation of the matter and to institute such charges as might appropriately be brought.
51 Undoubtedly, the observation by the Full Bench in Plastachem was correct, with respect. But it is not an easy matter, for the purpose of determining the costs issue, to place oneself in the position of the prosecution and make judgments about just what evidence the appellant needed to have brought in order to make out a successful prosecution of the 28 November charge. Nevertheless, I have formed the view that it was not essential for the prosecution to have adduced all of the evidence regarding the structural/design defects in the crane to make out the charge relating to 28 November. This evidence took up a large part of the proceedings before Peterson J.
52 There was no indication that a structural/design defect in the crane caused the incident on 28 November. The kibble hitting the scaffolding came about because the jib of the crane (which had been extended by 20 feet) was near horizontal or in the "flatstick" position giving it a working radius of 62 metres. Concrete was to be poured into two columns. The radii of the columns from the crane were 58 and 61 metres. Peterson J at [94] referred to the evidence of Mr McLaren that:
A kibble at the end of the crane loaded up with concrete had a certain amount of movement. It was a natural movement that you expect. You expect it to sway and move around. This kibble at that distance out moved more than you would expect and it did not feel safe.
53 At [95] Peterson J held:
95 I find myself unable to see how it could be said that this state of affairs was not the responsibility of Leightons. That an obvious degree of risk was experienced by workers on Leightons' site as the direct result of the adoption of a system of work that created that risk was a matter which must be attributable to Leightons. I find the offence proven as to system of work in IRC00/236.
54 The evidence relating to the structural/design problems with the crane and its capacity to carry certain loads at different radii was adduced to explain the collapse of the crane on 29 November, not why the kibble bounced on 28 November. And, indeed, it would not have been necessary to adduce that evidence in relation to the bouncing kibble because it should have been reasonably apparent the reason it bounced beyond what was the normal experience was due to the jib being flatstick and the loaded kibble being close to the extremity of the jib. Such a system of work was unsafe.
55 The incident that gave rise to the charge on 28 November was capable of being severed from the incident that occurred on 29 November and treated separately in terms of the evidence that was necessary to make out the charge. That is not a criticism of the appellant for taking a 'belt and braces' approach to the evidence but having taken an approach that was not essential, in my opinion the appellant cannot reasonably expect the respondent to bear the cost of having to deal with all of that evidence.
56 I note that in its written submissions before Peterson J the appellant stated:
This offence [IRC00/236] is made out without any consideration of whether the crane was overloaded at the time and independently of any finding about the strength of the crane or the capacity of the crane to lift the payload that comprised the kibble and its contents . It was clearly unsafe to permit the occurrence of a work practice whereby these workers could be in a place of peril should the kibble drop.
Even on the version of events that has the kibble "bouncing" the offence is made out. If it was the case that kibble bounce was a usual feature of this crane's operation the defendant is not relieved of its responsibility. The bouncing of a kibble which even empty weighs .6 tonnes is of itself a safety and health risk if it occurs in the presence of workers on a scaffold working at height. Indeed the actions in permitting the operation of the crane, or the continuation of a work system where this was a usual occurrence increases rather than diminishes the culpability of the defendant (our emphasis).
57 Later in its written submissions at first instance, the appellant addressed the issue regarding the capacity of the crane to cope with loads at various radii but these submissions were put in the alternative. This approach to the evidence by the appellant at first instance tends to support the view that the incident on 28 November was quite separate from what occurred on 29 November and that the prosecution could have run its case accordingly.
58 Mr Agius for the appellant submitted that it was necessary to adduce evidence regarding the structural/design problems with the crane and its capacity to carry certain loads at different radii in order to anticipate the respondent's reliance on defences under s 53 of the Act. That is to say, in the event the respondent was to contend, for instance, that the bouncing kibble that collided with the scaffold on 28 November was the result of causes associated with structural defects over which the respondent had no control, the appellant needed to be in a position to be able to rebut such submissions.
59 Given the strength of the appellant's primary submission before Peterson J regarding the unsafe system of work employed by the defendant on 28 November (i.e., the charge was made out without any consideration of whether the crane was overloaded at the time and independently of any finding about the strength of the crane or the capacity of the crane to lift the payload that comprised the kibble and its contents), to introduce a very large amount of evidence regarding the structural defects in order to anticipate a defence under s 53 would seem to me to have been excessive and not something in respect of which the appellant should be awarded costs.
60 Schmidt J did not explain how she approached the costs of the sentencing proceedings. The sentencing costs would normally go to the appellant and it is not apparent how those costs fitted into her Honour's apportionment of the costs. It may be that the respondent should have been awarded a lesser figure than 75 per cent or the appellant should have been awarded the sentencing costs. However, I am not persuaded that the exercise of her Honour's discretion in awarding costs to the respondent was ultimately unjust or unreasonable.
61 In summary, therefore, considering the end result, I would not interfere with the exercise of her Honour's discretion for the following reasons:
(1) The respondent was put to the expense of defending five charges relating to a series of closely interconnected events of 28 and 29 November with the prosecutor's case being put in such a way that events of 28 November could not be separated from the events of 29 November.
(2) The appellant was successful in relation to only one charge and that related to the events of 28 November. It was not essential for the prosecution to have adduced all of the evidence regarding the structural/design defects in the crane to make out the successful prosecution of charge relating to 28 November yet the defendant was put to the expense of dealing with all of the evidence regarding the structural/design defects.
(3) The successful defendant in summary proceedings should obtain an order for costs in respect of those issues on which the defendant succeeds; a successful defendant cannot be deprived of his or her costs because the charge is brought in the public interest or by a public official; or because the charge is serious; or because the informant acted reasonably in instituting the proceedings or might be deterred from laying charges in the future if he or she was ordered to pay costs; and, costs are not awarded by way of punishment of the unsuccessful party but rather the function of a costs order is compensatory.
(4) It is just and reasonable that the party who has caused the other party to incur the costs of litigation should reimburse that party for the liability incurred. In the present case the appellant caused the respondent to incur the costs of defending five charges and in respect of four of those charges, the respondent was successful. If one were to regard the five charges as one proceeding, the respondent was overwhelmingly successful.
SECOND APPEAL - LINDORES CRANES AND RIGGING (AUST) PTY LTD