"7. Security will only ordinarily be ordered against a party who is in substance a plaintiff, and an order ought not to be made against parties who are defending themselves and thus forced to litigate: see Interwest Ltd v Tricontinental Corporation Ltd (1991) 5 ACSR 621 at 626; Heller Factors Pty Ltd v John Arnold's Surf Shop Pty Ltd (in liq) (1979) 4 ACLC 492; Sydmar Pty Ltd v Statewise Developments Pty Ltd (1987) 5 ACLC 480; Weily's Quarries v Devine Shipping Pty Ltd (1994) 14 ACSR 186 where Zeeman J stated at 189:
'(t)he general proposition that security ought not to be ordered where the proceedings are defensive in the sense of directly resisting proceedings already brought or seeking to halt self-help procedures is no more than that, a general proposition. It ought not to be elevated to being a rule of law. In many cases of that nature it could be considered oppressive to require security and that in itself may be sufficient to refuse to make an order...(see) Sydmar Pty Ltd v Statewise Developments (supra) and Interwest Ltd v Tricontinental (supra)." (at para 39)"
Other considerations
45 There are a number of very curious parameters of the instant litigation which it is important to take into account in the exercise of the court's discretion.
46 The first is this. There appears to be a very real question, and it may be, as it seems to me, possibly a threshold question which would be determinative, or likely determinative, of the proceedings. The threshold question is whether or not the final decision by Justice Windeyer, to which I have referred, binds both parties in terms of a res judicata such that issues 3 to 14 in the points of claim in the arbitration [and, arguably, the issues sought to be raised thereafter in paragraphs 15 to 20] would be accordingly determined [if the res judicata question was determined in favour of the council].
47 At the court's instance, some time today was taken in a careful discussion of the position of both parties in terms of the possibility that the arbitrator might be approached by the parties consensually to direct that a separate question order ought to be made so that the arbitration would first and foremost deal with this question of res judicata. I should not have imagined that that sort of separate question would take more than possibly a day for hearing. Ultimately, the parties were not able to reach an accommodation in that regard.
48 The second matter which is of real significance, as it seems to me in terms of the instant application, is this. The amount of the cross-claim is for far more than $179,000. In real terms, the amount of the cross-claim is close to a claim for in the order of $1 million. As I have said, the question does arise as to whether or not in a case such as this the council should be regarded, notwithstanding that it is a respondent to the arbitration, as being an effective substantive moving party. It has been put to the court that even absent the terms of the cross-claim, it would always be open to the council, in terms of its defence to the builder's claim, to raise the defective works in every parameter. It has squarely put to the court, by Mr Kerr of counsel for the council, that this cannot be said to be an example of a case where a moving party is itself seeking security.
49 To my mind, that proposition does require to be approached in a very guarded fashion. Standing back from all of the issues, the court is entitled to infer that a principal purpose of this massive cross-claim is effectively to raise the stakes out of sight, as it were, as compared to that which had been the subject of the builder's claim.
50 In any event, the court in exercising its discretion to order security for costs will always stand back from the precise amounts claimed and from the precise assessments of costs to consider every case on its own particular facts and if an order is to be made at all, make such order as is just and reasonable in the circumstances.
51 In the present case, to my mind, the matter should be approached on a stepped basis. A plaintiff is always entitled to return to the court seeking additional security depending upon the circumstances. In my view, the appropriate orders to be made on the instant application will require the defendant within the next four weeks to pay the sum of $60,000. That sum of $60,000 is intended to include $10,000 booked as against the total professional costs and disbursements incurred to date likely to be recovered on a party-party basis, which were identified as $18,350 [that is to say $10,000 against that item]. An additional $50,000 is to cover future costs.
52 That is the only order which I propose presently to make in terms of the application for a security for costs order, and the reason is this. The hearing which has occurred today has thrown up, as I have understood it, at least some real possibility that the parties following this hearing may go back to their drawing boards. There may well be an application to the arbitrator to separate out the res judicata question as a preliminary question. Should such an application be made and should such an application be successful, then the whole of the security for costs application which has been pursued presently will require to be revisited. What one will then have will be nothing remotely like a two-week case and nothing remotely like a case in which the current claim for security for costs, which it should be recalled is for $316,400, will be even the subject of consideration.
53 Should it be that no such application is made in the next four weeks, then the plaintiff has liberty to return this application for security for costs to the court and to apply for such further or other security for costs order as may be appropriate in the then circumstances. Although the question of the court's discretion will remain unfettered and the application will be determined upon its then merits, that if the evidence remains as it was today, the council may well succeed in an entirely different order of security for costs to that which has been the subject of the orders made today.
54 Finally, in terms of the overriding-purpose rule, which, of course, binds parties to proceedings before this court, it does seem to me that where there is the ethical and general obligation of parties and of counsel and solicitors to carry out their best endeavours in any civil litigation to achieve a just, quick and cheap resolution of the proceedings, the parties, even though they are not strictly bound, or may not be, by that rule where there is an arbitration on foot, should pay very careful attention to the possibilities of cutting down in a sensible way, what seems to be a very huge expense to both parties. As the transcript of argument today will disclose, at least an offer had come forward from the council that if the parties could agree on the preliminary separate question being the subject of the arbitration and on particular parameters which Mr Kerr indicated from the bar table and if the council succeeded on the res judicata issue, Mr Kerr's instructions were that the otherwise claims in the cross-claim would not be pursued.
55 Those instructions, given albeit at short notice and in a circumstance in which close questioning of the parties about the real issues came from the court, strongly suggests to me a rethinking to achieve some approach short of the full-blooded hearing, the subject of the case as presently pleaded.
I certify that paragraphs 1 - 55
are a true copy of the reasons
for judgment herein of
the Hon. Justice Einstein
given on 10 June 2004 ex tempore
and revised 17 June 2004