[2022] NSWLEC 118
Land and Environment Court (NSW)
2022-09-07
Moore J, Mr J
Original judgment source is linked above.
TABLE OF CONTENTS Introduction Dr Wirth's application The Respondents' cross-claim Relevant statutory provisions Introduction The Encroachment of Buildings Act. The Court Act Relevant costs provisions The hearing Introduction The first phase The second phase The evidence The witnesses The photograph in Exhibit 7 The photographs in Exhibit 8 Introduction The photographs in Exhibit 9 Representation The two interlocutory decisions Introduction The amendment application The Respondents' application to reopen and tender a new document Introduction Submissions Consideration A relevant chronology One structure or two? Introduction The importance of the answer to this question Contextually relevant images Introduction A relevant survey extract A relevant 2003 photograph The evidence on the number of structures Introduction The burden of proof The submissions on the number of structures Introduction The submissions for Dr Wirth The submissions for the Respondents Matters which might be expected to assist but do not Matters about which there is no available evidence Neutral evidence Evidence relevant as to the number of structures Mr Harriman's evidence The relevant photographic evidence Introduction The stair elements The difference between the step designs The handrail/balustrade The orientation of the handrail/balustrade The lowest steel cable element of the balustrade The photographs in Exhibit 8 Consideration and conclusion Discretion concerning the encroaching structure Is it a "building"? Should its removal be ordered? Costs Conclusions Orders Annexure A Annexure B
Introduction
Dr Wirth's application
The Respondents' cross-claim
Introduction
The Encroachment of Buildings Act.
The Court Act
Relevant costs provisions
Introduction
The first phase
The second phase
The witnesses
The photograph in Exhibit 7
Introduction
The photographs in Exhibit 9
Representation
Introduction
The amendment application
The Respondents' application to reopen and tender a new document
Introduction
Submissions
Consideration
A relevant chronology
Introduction
The importance of the answer to this question
Introduction
A relevant survey extract
A relevant 2003 photograph
Introduction
The burden of proof
Introduction
The submissions for Dr Wirth
The submissions for the Respondents
Matters which might be expected to assist but do not
Matters about which there is no available evidence
Neutral evidence
Mr Harriman's evidence
Introduction
The difference between the step designs
The orientation of the handrail/balustrade
The lowest steel cable element of the balustrade
The photographs in Exhibit 8
Consideration and conclusion
Is it a "building"?
Should its removal be ordered?
Costs
Conclusions
Orders
Annexure B DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 15 September 2022
Wirth
Will
(2009) 239 CLR 175
(2009) 170 LGERA 223
(1990) 170 CLR 534
[2009] HCA 27
[1990] HCA 59