ISSUE #2 - IS THE BUILDER ENTITLED TO BE INDEMNIFIED IN RESPECT OF 'ANY COSTS' THAT IT MAY BE ORDERED TO PAY EUROPEAN WINDOWS WITH RESPECT TO THE 'ABANDONED' CLAIMS PERTAINING TO WINDOW DEFECTS?
ISSUE #3 - IS THE BUILDER ENTITLED TO AN ORDER THAT THE APPLICANTS PAY THE COSTS OF, AND INCIDENTAL TO, THE BUILDER'S STRIKE OUT APPLICATION DATED 10 NOVEMBER 2023, AND IF SO, CALCULATED ON WHAT BASIS?
ISSUE #4 - IS THE BUILDER ENTITLED TO AN ORDER THAT THE APPLICANTS PAY THE BUILDER'S COSTS 'WASTED' BY REASON OF THE FILING OF NEW EXPERT REPORTS, BY THE OWNERS?
West St. Falls Pty Ltd