[2026] VCAT 181
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2026-03-23
Original judgment source is linked above.
Childcare centre, built form scale, consistency with existing neighbourhood character
Warragul Properties Pty Ltd v Mitchell SC [2026] VCAT 181
Buildings and works for a use in Section 2
P Nickas, of Nickas Legal. He called evidence from:
Development and use of a 92 place childcare centre.
Application under section 77 of the Planning and Environment Act 1987 (Vic) - to review the refusal to grant a permit.
Clause 32.08-10 - Construct a building or construct or carry out works for a Section 2 use
The site is located on the north-east corner of the intersection of Stanley and Duke Streets, Wallan. Stanley Street informally terminates before its junction with Duke Street. The site has a frontage of 34.2 metres to Stanley Street and 50.3 metres to Duke Street, with an approximate overall site area of 1810 square metres. The site is currently developed with an existing dwelling with its two crossovers accessing the site from Stanley Street.
The site benefits from existing vegetation including a number of mature canopy trees.
More broadly, the Wallan Town Centre, which comprises a mix of retail, commercial and community uses, is located approximately 300 metres to the north-east of the site. Duke Street provides access to the Northern Highway, which is located 200 metres to the east and forms part of the Principal Road Network.
Figure 1: Site Layout Plan Source: Evidence statement of Mr Pagliar
Buildings and works for a use in Section 2
(a) transport of materials, goods or commodities to or from the land;
(b) appearance of any buildings, works or materials;
(c) emission of noise, artificial light, vibration, smell, fumes, smoke, vapour, reflection or glare, steam, soot, ash, dust, wastewater, waste products, grit, or oil; or
(d) presence of vermin;
(a) Parking allocations for staff, visitors and service vehicles.
(b) Traffic flow and safety including signage and line markings to guide vehicles and pedestrians, and safe pedestrian routes and crossings within the car park.
(c) Operational procedures including instructions for parents and staff on parking procedures, and clear communication channels for addressing parking related issues. The instructions for parents must emphasise that access to the site and drop-offs/pickups must be from Duke Street and parents should not drop off/pick up children from Stanley Street.
(d) Monitoring of parking usage and effectiveness of the plan, and maintenance of parking infrastructure including line markings and signage.
Noise Protocol means the Noise limit and assessment protocol for the control of noise from commercial, industrial and trade premises and entertainment venues, published by the Environment Protection Authority on its website, as in force from time to time.
(a) Waste collection to be undertaken by vehicles a maximum 6.4 metre long x 2.08 metre high and must only attend the site between the hours of 10.00am-3.00pm Monday to Friday.
(a) Crossover details.
(b) Turning movements demonstrating forward motion ingress and egress.
(c) Signage and line-marking.
(d) Driveway construction and drainage details including driveway grades and indication of fall.
(e) Underground drainage details, overland flow path and supporting calculations.
(f) Fencing details.
(g) All drainage works must be designed to meet the following current best practice performance objectives for stormwater quality as contained in the Urban Stormwater - Best Practice Environmental Management Guidelines (1999) unless otherwise agreed in writing by the Responsible Authority.
(a) Working hours.
(b) Details of site environmental controls.
(c) Methods to contain sediment, dust, spillages, mud and debris within the subject land, and the method and frequency of clean up procedures.
(d) A traffic management plan for both vehicle and pedestrian movements including working hours and after-hours signage.
(e) A liaison officer to contact by residents and the Responsible Authority in the event of relevant enquiries or problems experienced with construction activity.
(f) Details of stockpile areas, other proposed storage and a site office.
(a) constructed
(b) properly formed to such levels that they can be used in accordance with the plans
(c) surfaced with an all-weather-seal coat
(d) drained
(e) line marked to indicate each car space and all access lanes
(f) clearly marked to show the direction of traffic along access lanes and driveways
At all times car spaces, access lanes and driveways must be kept available for these purposes.
Once constructed, these areas must be maintained to the satisfaction of the responsible authority.
At all times, the signs must be located and maintained to the satisfaction of the responsible authority.
(a) Plant schedule including botanical name, container size, mature height and width and total quantities.
(b) Planting details.
(c) Relevant specifications.
(d) Reference the relevant Australian Standards.
(e) Nominate all surfaces, finishes and edge treatments.
(f) Be accurately scaled to show appropriate detail.
(g) Nominate a scale bar and widths of key features to assist in digital assessment of the plans.
(h) To ensure canopy closure and suppress weeds, garden bed species should be spaced at 75% of the mature width of the plant.
(i) In line with Council's Urban Forest Strategy 2023, have a provision for a minimum of 1 shade tree for every 5 parking bays, in garden beds at least 2m wide.
(j) The locations of any trees to be retained both on site and adjacent to the site, including details of the species, notional root zones, tree protection measures and tree sizes, where required.
(k) Existing nature strip trees are to be identified on the plans and protected during all construction activity. Include a reference to the following Australian Standard: AS4970:2025 - Protection of Trees on Development Sites.
(l) Add a notation to the Landscape Plan that the play space is to meet AS 4685.0:2017, Playground equipment and surfacing - Part 0: Development, installation, inspection, maintenance, and operation.
When approved, the landscape plan will form part of the permit.
(a) Pre-construction site preparation, including:
- Dead wooding of the tree's canopy;
- Trunk, branch and ground protection;
- The location of servicing.
(b) On-going maintenance, including:
- Climbing inspections by a suitably qualified arborist once every two years to identify any faults in the branch structure.
- On-going inspections to be carried out by staff of those external areas to be accessed by children immediately before those areas are accessed in order to locate, remove and dispose of any fallen branches.
- The site occupier accepts the responsibility of and will remain at all times responsible for the on-going inspection and maintenance of the tree and the removal and disposal of branches.
(a) The development is not started within 2 years of the issued date of this permit.
(b) The development is not completed within 4 years of the issued date of this permit.
(c) The use does not start within 2 years of completion of the development.
In accordance with Section 69 of the Planning and Environment Act 1987, an application may be submitted to the Responsible Authority for an extension of the periods referred to in this condition.
[1] The submissions and evidence of the parties, any supporting exhibits provided to the hearing and the statements of grounds filed have all been considered in the determination of the proceeding. In accordance with the practice of the Tribunal, not all of this material will be cited or referred to in these reasons.
Warragul Properties Pty Ltd
Mitchell SC [2026] VCAT 181