[2019] NSWCA 280
Court of Appeal (NSW)
2019-11-11
Bell ACJ, Macfarlan JA, White JA
Original judgment source is linked above.
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
[This headnote is not to be read as part of the judgment] In proceedings brought in the District Court of New South Wales, Mr David Armitstead and Ms Maria-Luisa Patisso, the respondents in the current proceedings, sought damages for breach of a twice varied building contract (the Contract) with Visual Building Construction Pty Ltd (the appellant) for the construction of two duplex buildings on a block of land in Caddens, NSW. The respondents had purported to terminate the contract due to the appellant's failure to complete the works by the date for completion specified in the Contract, its failure to obtain the required Construction Certificate and its failure to rectify defective works. The primary judge held that the respondents had validly terminated the Contract, and entered judgment in their favour in the sum of $651,536. The appellant filed an appeal, contending that the primary judge erred in finding that the Contract had been validly terminated, as the respondents had not provided the required 10 business days' notice prior to termination to allow for the defaults to be remedied. By notice of contention, the respondents argued that there were grounds additional to those relied upon by the primary judge which supported the valid termination of the Contract. The Court held (Bell ACJ, Macfarlan and White JJA agreeing), dismissing the appeal with costs: 1. The primary judge did not err in finding that the Contract was validly terminated. To the extent that the Contract imposed any requirement to give 10 business days' notice prior to termination, such a requirement only applied if the default was capable of being remedied within this period. The primary judge correctly found that, as a matter of fact, at least one of the defaults relied upon to justify termination of the contract was incapable of being remedied within that 10 day period: [31]-[36] (Bell ACJ); [40] (Macfarlan JA); [41] (White JA). 2. Even if the Contract had not been validly terminated, however, the respondents were entitled to damages for breach of contract, as the appellant had failed to obtain a Construction Certificate prior to commencement of the works, or at all, as required under the relevant Development Consent. No challenge was made to the assessment of the award of damages for breach of contract: [5], [37] (Bell ACJ); [40] (Macfarlan JA); [41] (White JA).
Judgment
The Contract
Development consent
Variations to the Contract
Notice of Intention to serve Order 19
Termination of the Contract
Proceedings at first instance
Arguments on appeal and notice of contention
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 21 November 2019
Visual Building Construction Pty Ltd
Armitstead