[1999] NSWSC 1252
Supreme Court of NSW
1999-12-17
Bryson J, Sheller JA
Original judgment source is linked above.
New South Wales Supreme Court CITATION : UPPER HUNTER TIMBERS PTY LTD v FORESTRY COMMISSION OF NSW [1999] NSWSC 1252 CURRENT JURISDICTION : Equity FILE NUMBER(S) : 3609/97 HEARING DATE(S) : 10/12/99 JUDGMENT DATE : 17 December 1999
PARTIES : Upper Hunter Timbers Pty Limited v. Forestry Commission of NSW JUDGMENT OF : Bryson J at 1
COUNSEL : DJ Hammerschlag for Plaintiff JE Griffiths for Defendant SOLICITORS : Deacons Graham & James for Plaintiff Crown Solicitor of NSW for Defendant CATCHWORDS : CONTRACT - Forestry Commission - effect of need for Minister's Approval under s.11(1)(m)ii) of Forestry Act 1916 - no power without Minister's approval - detailed consideration of facts after remitter by Court of Appeal [1999] NSWCA 125 Australian Broadcasting Corporation v Redmore Pty Ltd (1989) 116 CLR 454 TCN Channel 9 Pty Ltd v Hayden Enterprises Pty Ltd (1989) 16 NSWLR 130 CASES CITED : Alghussein Establishment v Eton College [1988] 1 WLR 587: see too Suttor v.Gundowda Pty Ltd (1950) 81 CLR 418 at 441. The Commonwealth v Amann Aviation Pty Ltd (1991) 174 CLR 64, Sellars v. Adelaide Petroleum NL & Ors (1994) 179 CLR 332 DECISION : See para.39
IN THE SUPREME COURT OF NEW SOUTH WALES EQUITY DIVISION
3609/97 UPPER HUNTER TIMBERS PTY LTD v. FORESTRY COMMISSION OF NEW SOUTH WALES
JUDGMENT 1 HIS HONOUR: These reasons deal with the determination of the matter remitted to the Equity Division by order 3 of the orders of the Court of Appeal of 21 May 1999. These reasons should be read with my reasons of 17 August 1998 and the judgment of Sheller JA in the Court of Appeal [1999] NSWCA 125. The matter remitted relates to the Mount Royal claim referred to in paras 4 to 9 of the Further Amended Statement of Claim. The Court of Appeal ordered: "3. remit the matter to the Equity Division for the determination of the extent, if any, to which the [Forestry Commission] was in breach of the agreement made on 14 November 1988 during the period on and from 14 August 1991 to 31 December 1996 and the damages, if any, the result of such breach for which the [Forestry Commission] is liable having regard to the provisions of the Frustrated Contracts Act". 2 In my understanding Order 3 of the Court of Appeal's order refers to breaches on and from 14 August 1991 to 31 December 1996, and does not refer to breaches committed before that period which had continuing effects. 3 When the proceedings came before me for determination of the matter remitted the plaintiff's counsel told me that he proposed to read two further affidavits on the issue of liability; these affidavits, which have been filed are those of Mr Bromley sworn 23 June 1999 and Mr R.J. Sims sworn 22 July 1999. Defendant's counsel opposed this course. I did not allow the affidavits to be read because the trial of the proceedings took place earlier and the parties' evidence on the issue of liability was heard then, the appeal did not involve fresh evidence and the evidence proposed to be read could not have been fresh evidence, no ground was advanced on which leave to re-open the evidence ought to be given, and the order of the Court of Appeal did not order a new trial but ordered only the determination of stated questions, in terms which require determination in relation to the issues and the evidence as they already are. While there is power to re-open a hearing and allow further evidence after judgment has been reserved, that power is only to be exercised where there is some substantial ground for exercising it. I refused the application and embarked on determining the question of liability under the Court of Appeal's order on the evidence at the earlier hearing. I did not embark on hearing or determining any question of quantum, as I earlier decided that quantum would be decided separately. Nothing has happened which limits the evidence which parties may read on quantum. 4 The agreement and the breach alleged appear from paras 4,5 and 8 of the Further Amended Statement of Claim and are to the effect that by the agreement of 14 November 1988 the Forestry Commission agreed
(a) to sell to Upper Hunter a parcel of timber in the Mount Royal State Forest; (b) to make the timber available for harvesting by Upper Hunter. 5 It is alleged that there were implied terms that (a) the Forestry Commission would do all such things as were necessary on its part to enable Upper Hunter to have the benefit of the agreement; (b) the Forestry Commission would refrain from doing anything which would prevent Upper Hunter from having the benefit of the agreement. 6 The breaches alleged are that the Forestry Commission has: (a) refused to permit Upper Hunter to continue to harvest the timber; (b) otherwise failed to take such steps as are necessary on its part to make sure that Upper Hunter has the benefit of the agreement. 7 The pleading does not give particulars of the breaches. 8 To establish what matters of fact or law are required to be decided to determine the matter remitted it is necessary to identify the parts of my earlier decision which were erroneous and were set aside. It is not appropriate to reopen any other matter. 9 Paragraph 53 of the judgment of Sheller JA deals with the effect of the frustration of the agreement of 14 November 1988 which occurred on 1 January 1997 when the Forestry Revocation and National Parks Reservation Act 1996 came into force. Sheller JA observed that the frustration prevented any claim for damages for loss of bargain. By implication this shows his Honour's view that the contract of 14 November 1988 was still in effect and was still at least potentially an advantageous bargain for Upper Hunter. 10 Sheller JA went on to say in paragraph 53: "Since the contract had not been terminated by the Commission's wrongful conduct, the frustration defeated any claim for damages for loss of bargain and left [Upper Hunter] to such claim for damages for breaches of promise before the time of frustration, as it might otherwise have. These in turn would be defeated by s14(1) of the Limitation Act 1969 if the cause of action had accrued before 14 August 1991." 11 In para 54 Sheller JA restated a number of findings in my earlier judgment. (I have given numbers to the findings). " Bryson J found that the cause of UHT's inability to work the Mount Royal State Forest throughout the whole six years before the proceedings began and earlier was the injunction which arose out of the Commission's failure to comply with s 112(1) of the EPA Act in 1988. The injunction applied only to compartments 200 to 204. In addition his Honour made the following findings:
(1) That no evidence dealt with whether UHT sought or was refused licenses to take timber in the Mount Royal State Forest for periods after 31 December 1993. Accordingly, there was no contractually effectual entitlement to take timber from 1 January 1994 due to the effect of General Condition 5 which provided:
'Supply of timber for the successful tenderer/s will be made under, and subject to , the provisions of the Forestry Act 1916, the Forestry Regulation 1983 and subject to the conditions of licenses issued under these statutes.
(2) That the contractual obligation did not extend to oblige the Commission to exercise the discretionary statutory power to issue licenses in any particular way.
(3) That the Commission when it entered into the agreement on 14 November 1988 was obliged to comply with s 112(1) of the EPA Act and was in breach of its implied obligation under the contract to do so.
(4) That the Commission was in breach of its obligation to comply with s 112(1) of the EPA Act on each occasion until 12 March 1992, when it granted another timber license.
(5) That, after the commencement of the TIIP Act, the implied contractual obligation would have obliged the Commission to take reasonable steps, in respect of the eight compartments to which schedule 1 of the TIIP Act applied, to overcome the prohibition found in s6 by obtaining an environmental impact statement and the Minister of Planning's determination under s 9 if there were to be any operations in the eight compartments.
(6) That the timber license which UHT had by then obtained for 1992 did not relate to any of those compartments, so no action in relation to them was contractually required of the Commission.
(7) That with respect to other parts, which included compartments 180,181,182 and 187 to which the 1992 license applied, the Commission needed to comply with s8 by obtaining an environmental impact statement and a determination from the Minister of Planning but, as its environmental impact statement was rejected by the Minister of Planning as inadequate, it failed to do so.
(8) That the Commission, in not submitting an acceptable environmental impact statement and not obtaining a determination from the Minister of Planning under the TIIP Act, was not in breach of the Commission's implied obligation.
(9) That, if it had been a breach, it had not been shown to have had any effect to prevent logging operations on any land which UHT would otherwise have worked and therefore as a cause of damage. The TIIP Act did not forbid logging operations on land in schedule 4, presumably because during the period of operation of the Act the application of Pt 5 of the EPA Act in respect of logging operations being carried out or proposed to be carried out on land specified in schedule 4 was suspended.
(10) That, as the terms of the timber license for 1993, did not identify the relevant land by compartments, UHT had not shown by evidence whether the prohibition in s6 had any operation in respect of the land subject to that license or whether that prohibition was a practical impediment to getting timber in accordance with the license.". 12 Sheller JA said at paragraphs 55 and 56: "55. The result of these findings would be that, although the claim for damages caused by breaches of contract which had occurred before 14 August 1991 was statute barred, UHT was entitled to damages for the Commission's failure to comply with s 112(1) of the EPA Act at the time of granting licenses for the period on and after 14 August 1991 up to the timber license granted for 1992. It is not clear whether any damages in the sense of any loss of timber harvesting was suffered during this period. Thereafter, as I understand it, because of the limited areas covered by the licenses subsequently issued, either there was no breach of contract or, alternatively if there was, no damage suffered. This was particularly so from 1 January 1994.
(2) Give judgment for the defendant with costs, such costs to include the costs of the hearing before Bryson J on 15 May and 1 June 1998.
Last Modified: 06/26/2000 DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
UPPER HUNTER TIMBERS PTY LTD
FORESTRY COMMISSION OF NSW
(1989) 116 CLR 454
(1989) 16 NSWLR 130
(1950) 81 CLR 418
(1991) 174 CLR 64
(1994) 179 CLR 332