[2020] NSWLEC 1353
Land and Environment Court (NSW)
2020-07-21
Original judgment source is linked above.
The applicant's written request to contravene the height of buildings development standard
Whether the proposal is in the public interest because it is consistent with the objectives of the contravened development standard and the zone
Orders
Amendments 25 August 2020 - Pursuant to UCPR Rule 36.17 of the Uniform Civil Procedure Rules 2005, by the request of the parties and the Court's own motion, include the following orders made on 21 August 2020: "(4) The Applicant is granted leave to rely on the updated clause 4.6 written request prepared by BBF Planners dated 21 July 2020. (5) In relation to the amendment for which leave is granted by Order (1) and (4) above, the Applicant shall pay the Respondent's costs as agreed or assessed pursuant to section 8.15 of the Environmental Planning and Assessment Act 1979 (NSW)." DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 25 August 2020
TWT Development Pty Ltd
North Sydney Council
Contravention of the height of buildings development standard
(2018) 236 LGERA 256
(2007) 156 LGERA 446