The liquidated damages claim
63 In its adjudication application, which ran to some hundreds of pages, the first defendant made claims for extensions of time. It stated:
"On 6 October 2006 the Hotel reached Practical Completion.
On 17 November 2006, the first floor units reach Practical Completion."
64 Under the heading "Units" the application contained the following:
"The Claimant notes the following:
(i) The contracted completion date for the units was 26.05.06
(ii) Taking into consideration the 69.5 extension of time days the Completion date is adjusted to 01.09.06
(iii) Practical completion was reached 17.11.06."
65 The adjudication application went on to state:
"The Claimant calculates that it has a total of 157.5 days proper claim for EOT, 99.5 days of which has been granted and the contract adjusted accordingly."
66 In the schedule the plaintiff dealt with the extension of time claims made by the first defendant. It put, with respect to the units, that the maximum allowable and approved extension of time for the units was 69.5 days. It stated that the contractual completion date for the units was 26 May 2006 and that the adjusted contractual completion date became 16 August 2006.
67 In its adjudication response it repeated the contention that the revised contractual completion date for the units was 16 August 2006.
68 With respect to liquidated damages, in the schedule the plaintiff put its claim in the following terms:
Liquidated Damages
Liquidated damages have been assessed in accordance with the Contract, the requested practical completion dates and the period of time that expired while Club Constructions undertook extensive defect rectification in order to provide a product that was fit for use.
The amount claimed for liquidated damages is 105 x days @ $1,500 totalling $159,000 in accordance with Clause 10.14 of the Contract."
69 In a further section entitled Liquidated Damages, amongst others the following was put:
" UNITS
The Practical Completion date requires by Club Constructions for the units was Friday 17th November 2006. Counting of days for late completion is 80 days.
…
Liquidated Damages costs for the late hand over of "fit for purpose" and habitable units is therefore 106 days x $1,500."
70 In its adjudication response it stated amongst others the following:
" Section I - Liquidated Damages
Liquidated damages has been reviewed following the re-assessment of extension of time costs, dates of practical completion and the arguments supplied within the Doyles Adjudication Application.
Liquidated damages are assessed on the two separable portions of the contract in accordance with contract clauses 10.14 and 10.15 and the related appendix items O."
71 In relation to the units it repeated that the contract completion date was 26 May 2006, that an extension of time of 69.5 days had been approved and that the revised contractual completion date was 16 August 2006. It stated:
"Practical completion for the Hotel was requested by the claimant on 6 October 2007 [sic].
Practical completion for the Hotel was requested by the claimant on 17 November 2007 [sic].
The above dates of practical completion and the above dates of extended contractual completion differ by the amounts as follows:
Hotel - The difference being a completion of the staged works 34 days late.
Units - The difference being a completion of the staged works 81 days late.
The contractor has failed in the opinion of the superintendent to bring both stages of the works to practical completion as the above dates demonstrate.
The costs for liquidated damages are as follows:
Hotel - 34 days x $4,500 = $153,00
Units - 81 days x $1,500 = $121,500
Total Liquidated damages = $274,500"
72 The adjudicator dealt with both the extension of time claims and the plaintiff's liquidated damages claim.
73 With respect to the liquidated damages claim his determination was in the following terms:
"The Respondent submits that the practical completion of the units has been delayed by the Claimant. The Respondent has not advised their determination of the date of practical completion as determined in accordance with the contract, including any adjustment to the dates in the contract as provided in section 9.
I determine that the Respondent has provided insufficient information to assess any liquidated damages to be applied in accordance with the contract.
I make no allowance for this item."
74 The determination of liquidated damages involved three steps. Firstly, determining how many days elapsed between 26 May 2006 (the stipulated date for practical completion of the units) and the date of practical completion; secondly, determining how many of those days were covered by extensions of time to which the first defendant was entitled; and thirdly, multiplying the remaining days by $1,500.
75 Mr Christie readily, and properly, conceded that the adjudicator had been provided with sufficient information for him to have assessed any liquidated damages with respect to the units.
76 Mr Christie further submitted that the adjudicator allowed 125.5 days as extensions of time, so that the date for Practical Completion of the units was extended to 1 October 2006. He accepted that the material before the adjudicator established that the date of Practical Completion was 17 November 2006. Accordingly, there were 47 days which at $1,500 per day yielded liquidated damages of $70,500.
77 He put that, in determining that the respondent had provided insufficient information to assess any liquidated damages to be applied in accordance with the contract, the adjudicator had simply made an "unfortunate mistake" being an erroneous failure to consider a submission, which was insufficient to render the adjudication void.
78 Mr Christie proffered as a possible explanation for the error the fact that that part of the response entitled "Section I - Liquidated Damages" did not in terms state the Practical Completion date for the units, but referred only to the hotel.
79 Ms Culkoff put that the problem with the adjudication was more profound. Not only had the plaintiff (contrary to what the adjudicator determined) advised its "determination of the date of Practical Completion as determined in accordance with the contract, including any adjustment to the dates in the contract as provided in section 9 ", but that on the face of the adjudication itself, the adjudicator must have understood that the plaintiff had so advised and, moreover, the adjudicator had determined a completion date and the extensions of time to which the first defendant was entitled. Hence, she put, the adjudicator had failed to make a bona fide attempt to comply with basic requirements of the Act and had denied the plaintiff the measure of natural justice required.
80 In par 2 of the adjudication, the adjudicator stated "work commenced on or about 5 September 2005 and was completed in November 2006".
81 In par 5.8 he stated "[t]he Claimant submits that practical completion for all work was achieved in November 2006. The Respondent considers that practical completion was attained on 17 November 2006."
82 It is difficult to see how, if the adjudicator was making a bona fide attempt to assess liquidated damages, he could have considered that the respondent had not advised its asserted date of Practical Completion nor adjustments for extensions of time when, in his own adjudication, he made reference to the date so advised by the plaintiff, recorded that the work had been completed in November and determined the extensions of time to which the first defendant was entitled.
83 In my view, the mistake was not one of the quality submitted on behalf of the first defendant. The adjudicator, in the face of his own findings, simply did not proceed to adjudicate the plaintiff's claim for liquidated damages as the Act required him to do. Having regard to his own findings, it is not open to conclude that he made a conscientious, but mistaken, assessment of that claim. What he did was to fail to adjudicate a claim on material which he clearly must have known was before him.
84 That the adjudicator's failure worked substantial practical injustice on the plaintiff is self-evident from the fact that there was no ready answer to the claim.
85 It is open to articulate what the adjudicator did as both a failure, bona fide, to attempt to exercise the relevant power with respect to the liquidated damages claim, and a failure to afford the level of natural justice required by the Act to be given to the plaintiff. Either way, his error rendered the whole determination void.