[2025] NSWCATAP 114
General information, not legal advice.
NCAT Appeal Panel
2025-05-23
M Deane, Senior MemberN Kennedy, Senior Member
Original judgment source is linked above.
Allianz Australia Insurance Limited trading as Allianz v Susak [2025] NSWCA 91
Azzopardi v Tasman UEB Industries Ltd (1985) 4 NSWLR 139
Bellgrove v Eldridge [1954] HCA 36; (1954) 90 CLR 613
Chapman v Taylor [2004] NSWCA 456
Collector of Customs v Pressure Tankers Pty Ltd and Commonwealth of Australia v Amann Aviation Pty Limited [1991] HCA 54; (1992) 174 CLR 64
Pozzolanic Enterprises Pty Ltd [1993] FCA 356; (1993) 43 FCR 280
Corcoran v Far [2019] NSWSC 1284
Day v SAS Trustee Corporation [2021] NSWCA 71
Donohoe v Albulario [2025] NSWSC 9
Dranichnikov v Minister for Immigration and Multicultural Affairs (2003) 77 ALJR 1088; [2003] HCA 26
Mann v Paterson Constructions Pty Ltd [2019] HCA 32
Minister for Immigration & Ethnic Affairs v Wu Shan Liang (1996) 185 CLR 259
New South Wales Land and Housing Corporation v Orr [2019] NSWCA 231
Nu-Stone Building Pty Ltd v McInerney [2023] NSWSC 940
Plaintiff M1/2021 v Minister for Home Affairs (2022) 96 ALJR 497; [2022] HCA 17
Prendergast v Western Murray Irrigation Ltd [2014] NSWCATAP 69
Rodger v De Gelder [2015] NSWCA 211
Ryan v BKB Motor Vehicle Repairs Pty Ltd [2017] NSWCATAP 39
The Owners - Strata Plan 87003 v Raysons Constructions Pty Ltd [2025] NSWSC 66
Unique Commercial Group Pty Ltd v Cusumano [2024] NSWCATAP 204
Walker Group Constructions Pty Ltd v Tzaneros Investments Pty Ltd [2017] NSWCA 27; (2017) 94 NSWLR 108
v Civil Project Management Group Pty Ltd (Respondent)
(1) In the Owner's appeal: The Owner has demonstrated that the Tribunal at first instance made an error on a question of law by applying the wrong legal principle in the assessment of damages. Accordingly, Orders 1 and 3 made by the Tribunal have been set aside and the matter has been remitted for reconsideration of the damages to be awarded to the Owner for the removal and replacement of the slab;
(2) In the Builder's cross-appeal: The Builder has not demonstrated an error on a question of law and the Builder's cross-appeal has been dismissed.
Proceedings in the Consumer and Commercial Division
[$22,125 + $384.00 + $4,965.00 + $3,249 (see [140] totalling] $30,723
110 The terms and conditions of the contract are ambiguous; caused by the builder's unsophisticated and scant regard to documenting the terms and conditions of the contract in a comprehensive form of contract regulating the clear obligations, rights and duties of the parties.
111 The accepted quotation dated 23 March 2021 specified provision for a roller door 3.8 metres high and 5.4 metres wide at the entrance of the shed. Such a wide and high entrance must have contemplated access by vehicles.
112 The Tribunal is satisfied that the owner stipulated that the slab height should allow vehicular access through the north elevation of the shed. This was known to the builder, critically when the plans were submitted to the local authority for approval. The owner's evidence is that on 10 May 2021 the owner included in an email to the builders project engineer, Mr Arbabzadeh, his requirements that the shed be capable of storage of a boat and caravan and large objects including sculptures.
113 The email exchange between Mr Arbabzadeh, the builders engineer, and the owner regarding the final approval of the plans in May 2021, demonstrated that it was the intention of the parties to finalise the plans of the shed to be approved and built after the date the owner accepted the quote on 23 March 2021. The approved plans were the plans of the shed to be built by the builder. Further the levels on the plans were to be verified before construction commenced, the owner was not consulted about any variation to the finished level of the slab from the plans, and the owner was charged a variation for the civil works required to compensate for the fall in the land.
114 The Statement of Environmental Effects ("SOEE"), dated May 2021 and revised June 2021, accompanying the development application, prepared by Mr Arbabzadeh, for the builder, stipulated:
Under the heading "Context, Design, and Bulk":
"" The proposed building is designed to serve its purposes as a personal photoshoot/filmmaking studio. The height and size of the building is essential to provide capacity of filming and shooting various personal projects including the followings (sic):
- filming stationary tall and wide objects such as boats, vans or trucks, and also handmade sculptures".
Under the heading "Vehicle and Pedestrian Access":
E_xisting driveway and garage which remain intact meets the council requirements. In case vehicle access to the proposed shed is required, it is to be accessed through the existing driveway"._
115 The expert opinion of Expert Moore is that it is not practically possible to obtain vehicular access to the shed due to the steepness of the transition slope required on the driveway over a distance of 6.2 metres to the street [Counsel for the Owner submitted that this was intended to mean "to the boundary"]
116 Clearly a slab height of between 600mm and 700mm at the roller door does not allow for vehicular access to the shed.
117 The final plans upon which the local authority issued its development approval on 11 October 2021 were:
(1) Drawing 100 dated 13 April 2021 with two additional revisions, finally on 25 June 2021;
(2) Drawing 200 dated 13 April 2021 with one additional revision on 27 April 2021;
(3) Drawing 300 dated 13 April 2021 with two additional revisions, finally on 25 June 2021; and
(4) Drawing 310 dated 14 April 2021 with one additional revision on 27 April 2021.
118 As the approved plans are the plans that the builder agreed to build, they will be the plans that have been created for the Contract. The plans, although each containing a notation "Levels included on the plan are approximate and shall be verified on the site before construction commences" are drawn to scale and Drawings 300 and 310 show the surface level and excavation approved [for] each elevation. Notably, the north elevation shows the level of the slab relative to the ground level. The as built slab is 600mm - 700mm above the adjoining ground level and with the proximity of the road it is not possible to access the shed with vehicles.
119 The Tribunal is satisfied that vehicular access to the shed was a requirement of the owner, the evidence of that requirement is contained in the email from the owner to Mr Arbabzadeh and his inclusion in the SOEE [of] the requirement for vehicle access.
120 The Tribunal is satisfied that the slab height significantly exceeds the slab height adduced from the approved plans. The Tribunal is satisfied the height of [the] slab surface level relative to the natural land surface level [for] the shed does not allow vehicle access to the shed.
121 The builder has breached the statutory warranty under section 18B(1)(a) of the HBA. The slab has not been completed in accordance with the plans and specifications as it does not allow vehicle access.
122 Rectification by reducing the slab height is not possible.
We need to justify the height. Normally it is done by arguing that the shed is to be used for the storage of a boat and a caravan. It is not relevant in your case. I appreciate it if you can advise whether there is any technical consideration that help to justify the height. For instance installing lighting equipment, a green screen, or decoration would be a strong argument.
... The storage of a boat and caravan is entirely relevant for a number of reasons and examples that include:- rear projection including large stationary objects such as boat/caravan/truck/sculpture. - also if the house was to be sold one day the shed with the height planned would be suitable for people off the local area who would intend to buy as many people that choose to live in Erowal Bay do so for reasons of fishing/camping outdoor sports and these types of activities usually require the storage of supporting equipment including and not limited to Ocean Boats, Personal Watercraft, Caravans, Truck or Large Vehicle to tow the recreational equipment. - lighting systems and green screen systems require height to allow for subjects/actors to be filmed/photographed to achieve certain effects.
(1) the opinion of the Owner's expert's (Expert Moore's) that the cost of demolishing the slab and removal of the spoil was $22,739.96 was preferred;
(2) that cost should be borne by the Builder [123] - [124];
(3) the extent of the rectification required the removal of the slab and the appropriate order should be that the Builder pay to the Owner the assessed cost of the demolition and removal of the slab as assessed by Expert Moore in the amount of $22,739.96.
(1) The Builder's building claim was brought within three years of the cause of action arising and was less than $500,000 [17];
(2) it was common ground that the Contract was terminated on or about 13 December 2021 [133];
(3) the Owner repudiated the Contract on 15 December [sic:2021]. The Builder's representative was requested to leave the site. Although the Builder finished up on site on 16 December 2021, they did not return to and were prevented from returning to the site. The Builder then left the site and did not return after removing the shed kit which had been delivered to the site [137];
(4) the Owner had been invoiced up to 16 December 2021 for progress payments for work performed to that date [139];
(5) the Builder accepted the Owner's repudiation and termination of the Contract by not returning to the site to continue work after 16 December 2021 [138];
(6) the Builder was entitled to succeed in its claim for unpaid Contract progress payments for Stage 2 and the variations of $22,125.00 + 384.00 + $4,965.00 + $3,294 totalling $30,723 [140];
(7) the Builder was not entitled to recover the claim for stage 3 for the delivery of the shed. The shed was generic, despite the builder's claim that the shed was manufactured to the design. The Builder had not supported their claim with evidence of any attempts to mitigate their claimed loss and remained in possession of the shed kit [141];
(8) Stage 4 works had not been carried out and the Builder had not adduced evidence of the loss they had suffered as a result of not being able to deliver Stage 4. That claim failed.
(1) In the Owner's claim, the Builder was to pay the Owner the amount of $22,739.96.
(2) In the Builder's claim, the Owner was to pay the Builder $30,723.00
(3) The amount in Order 1 was to be deducted from Order 2 so that the balance payable to the Owner was $7,983.04.
"27. Where, however, there is a question of law in substance, a court (and, it follows, an Appeal Panel) has discretion (to be exercised judicially and in the interests of justice) to direct its formal notification in an amended notice of appeal: Thomas and Naaz Pty Ltd (ACN 101 491 703) v Chief Commissioner of State Revenue [2022] NSWCATAP 220 at [60]. In appropriate circumstances, the Appeal Panel may elect to waive the requirement to formally lodge an amended notice of appeal, given its mandate to act "with as little formality as the circumstances of the case permit ... without regard to technicalities or legal forms": NCAT Act, s 38(4); Wollondilly at [19]. Where the party is not legally represented, a more generous approach is warranted: Kudrynski at [50]-[51]. This is an aspect of ensuring procedural fairness.
28. When dealing with self‑represented parties, the Appeal Panel has in many instances considered for itself whether a question of law is raised, applying [Prendergast] at [12]."
30 In construing the phrase "question of law", statements of principles are less likely to be of assistance than close attention to the nature of the issue identified by the appellant and the statutory context in which the appeal arises. Reformulating the statutory criterion as referring to a "question of law alone", or as excluding "a mixed question of fact and law", may prove a distraction...
1. The Tribunal erred in law in assessing the proper measure of the applicant's [the Owner's] damages in light of its finding that the respondent [the Builder] was in breach of the contract and the statutory warranties.
2. The Tribunal erred in law in finding that the respondent [the Builder] was entitled to be paid the sum of $30,723 for work which was found to be in breach of the contract, in breach of the statutory warranties and/or had not been performed.
1. The Senior Member erred in his findings [listed from a - i]
2. The Senior Member erred in not providing any or any adequate reasons to support his findings.
1. Appeal allowed (and Tribunal orders set aside)
2. Assessment of damages remitted to Tribunal to be reconsidered without further evidence in accordance with the AP's directions
OR
1. the Tribunal's orders be varied as follows:
(a) Builder to pay the Owner $87,400
(b) Builder's claim dismissed
(c) Builder to pay Owner's costs of the appeal and at first instance as agreed or assessed.
1. The Owner pay the sum of $85,945.00 plus interest and costs.
2. The Owner pay the cost of the appeal.
Do the Owner's appeal grounds raise a question of law?
Did the Tribunal apply the correct legal test in assessing damages?
2. The general principle governing the assessment of compensatory damages in both contract and tort is that the plaintiff should receive the monetary sum which, so far as money can, represents fair and adequate compensation for the loss or injury sustained by reason of the defendant's wrongful conduct. The application of that general principle ordinarily involves a comparison, sometimes implicit, between a hypothetical and an actual state of affairs: what relevantly represents the position in which the plaintiff would have been if the wrongful act (i.e. the repudiation or breach of contract or the tort) had not occurred and what relevantly represents the position in which the plaintiff is or will be after the occurrence of the wrongful act ....
In the present case, the respondent was entitled to have a building erected upon her land in accordance with the contract and the plans and specifications which formed part of it, and her damage is the loss which she has sustained by the failure of the appellant to perform his obligation to her. This loss cannot be measured by comparing the value of the building which has been erected with the value it would have borne if erected in accordance with the contract; her loss can, prima facie, be measured only by ascertaining the amount required to rectify the defects complained of and so give to her the equivalent of a building on her land which is substantially in accordance with the contract.
...
But the work necessary to remedy defects in a building and so produce conformity with the plans and specifications may, and frequently will, require the removal or demolition of some part of the structure. And it is obvious that the necessary remedial work may call for the removal or demolition of a more or less substantial part of the building. Indeed-and such was held to be the position in the present case-there may well be cases where the only practicable method of producing conformity with plans and specifications is by demolishing the whole of the building and erecting another in its place. In none of these cases is anything more done than that work which is required to achieve conformity and the cost of the work, whether it be necessary to replace only a small part, or a substantial part, or, indeed, the whole of the building is, subject to the qualification which we have already mentioned and to which we shall refer, together with any appropriate consequential damages, the extent of the building owner's loss.
The qualification, however, to which this rule is subject is that, not only must the work undertaken be necessary to produce conformity, but that also, it must be a reasonable course to adopt.
The general principle on which damages are recoverable by a building owner for breach of a building contract is the cost of making the work or building conform to the contract, subject to the qualification that not only must the work be necessary to produce conformity, but it must also be a reasonable course to adopt: Bellgrove at 617-618; Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009) 236 CLR 272; [2009] HCA 8 at [15].
123 Expert Moore in his Building Costing Report of 19 August 2022 (Exhibit A4) opines that the cost of demolishing the slab and removal of the spoil is $18,949.97 plus margin of 20% totalling $22,739.96 based on Cordell Online Platinum Estimating program. Expert Cauduro in his report dated 4 July 2023 (Exhibit R2) opines that the cost of demolishing the slab and removal of spoil is $13,274.00 based on Rawlinson's Costing Guide. Expert Cauduro does not express an opinion on builder's margin.
124 The Tribunal is satisfied that the cost of removal of the slab should be borne by the builder. The Tribunal prefers Expert Moore's assessment of the cost of demolition and removal, despite Expert Cauduro's assessment. Expert Moore has explained his reliance on Cordell's in arriving at the cost and for completeness includes a builder's margin for carrying out the work.
125 The Tribunal has considered the preferred outcome under s48MA that the builder rectifies the defective slab. In the circumstances, the Tribunal is satisfied that the extent of the rectification requires the removal of the slab and the appropriate order should be the builder pay to the owner the assessed cost of the demolition and removal of the slab as assessed by Expert Moore in the amount of $22,739.96.
(a) the Stage 2 payment of $22,125 for the delivery of a slab which failed to meet the requirements of the plans;
(b) the payment of $384 for a variation which was not delivered as the window could not be installed until Stage 3 or 4;
(c) any amount for variation 2 which related to excavation to meet the required levels (which was not done, on the Tribunal's finding) and for burnishing the slab, which was also not done to the requisite standard;
(d) any amount for variation 3.
Do the Owner's contentions demonstrate any relevant error?
... mere difficulty in estimating damages does not relieve a court from the responsibility of estimating them as best it can. Indeed, in Jones v Schiffman, Menzies J went so far as to say that the "assessment of damages... does sometimes, off necessity involve what is guesswork rather than estimation." Where precise evidence is not available, the court must do the best it can. Any uncertainty as to the profits to be derived from a business by reason of contingencies is not a reason for a court refusing to assess damages.
5.7 Vehicle and Pedestrian Access
The specific objectives are to:
i. Encourage driveway design that minimises visual impact, stormwater runoff and retains established trees and vegetation.
ii. Encourage an approach to access design that considers the site and its elements holistically (e.g. landscaping).
iii. Provide adequate and safe vehicular and pedestrian access from the street to the site, development and parking spaces.
iv. Ensure the safety of pedestrians and bicycle riders in proximity to the driveway area.
...
Comments
Existing driveway and garage which remain intact meets the council requirements. In case vehicular access to the proposed shared is required, it is to be accessed through the existing driveway.
2.1.4 the shed slab height would prevent vehicular access to the interior due to there being inadequate frontage set back to allow acceptable transitions and slope to the driveway.
in answer to item 2.1.4 of Mr Moore's report. The height of the shed is not required to have vehicular access. The architectural drawings provided highlight from the street frontage of Second Avenue, five bottlebrush trees are to be planted, preventing vehicle access from street level.
16 Before my workers were ordered off the site by Mr Trindorfer, we had completed the manufacture of the shed which he requested. The shed was custom made to fit the size of the slab and is not capable of being sold to any other customer. It is being stored in flat packs at our business premises.
Two preliminary issues in the Builder's cross-appeal
(ii) Entire obligations and divisible obligations
172 It follows from what has been said that, where, under a contract for work and labour, a party is entitled to payment upon completion of any part of the work (which is to say that the obligation to complete that work is "infinitely divisible"), where the contract expressly fixes a price for services, and where the contract is terminated by that party's acceptance of the other party's repudiation of it, the party so terminating the contract will have an accrued right to payment under the contract for that part of the work that has been done. There will have been no failure of consideration. Accordingly, that party's remedy in respect of that part of the work that has been done will generally be restricted to a claim for what has accrued due or damages for breach of contract assessed by reference to the contract price less the cost of completing the work**.**
...
174. By further contrast, if the obligation to perform work is divisible into several entire stages, then, upon termination of the contract for repudiation: (i) the contractor so terminating the contract will have accrued rights under the contract for those stages that have been completed; (ii) there will be a total failure of consideration in respect of the stages that have not been completed, because the contractor's right to complete the performance and earn the price will have failed and nothing will be due under the contract in respect of those uncompleted stages; and (iii) restitution will lie as upon a quantum meruit in respect of the work and labour done towards completion of the uncompleted stages as an alternative to damages for breach of contract.
141. The Tribunal is not satisfied that the builder should recover the claim for Stage 3 for the delivery of the shed. The shed was generic, despite the builder's claim that the shed was manufactured to the design. The builder has not supported their claim with evidence of any attempts to mitigate their claimed loss. The builder remains in possession of the shed kit. The Tribunal is not satisfied that the builder is entitled to the amount claimed for Stage 3.
Do the Builder's appeal grounds raise a question of law?
(1) Whether the Tribunal failed to take into account relevant evidence and
(2) Whether the Tribunal failed to give adequate reasons.
Does a purported failure to consider relevant evidence raise a question of law?
95. It has also been said where the relevant facts have been clearly established and the reasons show the decision-maker acted on the wrong basis in important respects, the decision-maker has failed properly to exercise their jurisdiction: Nufarm Australia Ltd v Dow AgroSciences Australia Ltd (No 2) [2011] FCA 757; 282 ALR 24 at [102]- [103]. Jurisdictional error includes a constructive failure to exercise jurisdiction. A constructive failure to exercise jurisdiction arises when a decision-maker misunderstands the nature of its jurisdiction and, in consequence, applies a wrong test, misconceives its duty, fails to apply itself to the real question to be decided, or misunderstands the nature of the opinion it is to form: Minister for Immigration v Yusuf at [41] (Gaudron J).
Does a failure to provide adequate reasons constitute a question of law?
(1) whether the Tribunal has failed to respond to a substantial argument and so failed to exercise jurisdiction by failing to accord procedural fairness; and
(2) whether the Tribunal failed to provide adequate reasons for the findings described in ground 1.
1(a) [The Senior Member erred in his findings that] the terms and conditions of the contract were ambiguous and such ambiguity was caused by the Builder's unsophisticated and scant regard to documenting the terms and conditions of the contract in a comprehensive form of contract regulating the clear obligations, rights and duties of the parties (or at all) (paragraph 110)
1(b) [The Senior Member erred in his findings that] the vehicular access to the shed was not practicably possible [115] and the slab height would prevent such access [116];
1(c) [The Senior Member erred in his findings that] the contract between the parties required vehicular access being included in the design and the construction of the shed and that access to the shed from the road was required [119]. The Tribunal failed to take any proper regard to the unsatisfactory evidence of the owner under cross examination on this issue (and in general)
...
1(e) The Senior Member erred in his findings that the rectification required demolition and removal of the slab with the builder to pay such costs [125]
...
1(f) [The Senior Member erred in his findings that] the owner's expert engineer's evidence should be preferred over the builder's. Specifically the Senior Member erred in stating that the [builder's engineer's] evidence must be given less weight than [the owner's engineer] because [the builder's engineer's] independence was impugned by his confirmation in cross examination that he had worked for the builder between 7 and 8 years in that time of up to 5 large projects. It was unreasonable for the Senior Member to find that a prior association alone discredited the applicants expert evidence (paragraph 128) [and the builder argued that the Tribunal] failed to give proper, or adequate, reasons for this conclusion.
The Senior Member failed to give adequate reasons or proper reasons as to why the overall height of the shed would encroach the' building envelope';
1(g) [The Senior Member erred in his findings that] the Builder was not entitled to an award for costs for the shed on the basis that the shed was generic in design and construction [141]
1(h) [The Senior Member erred in his findings that] the Builder was not entitled to the value of the shed because it had not demonstrated evidence of having mitigated its loss(or for any other reason) [141]. The Tribunal failed to give adequate weight to the Builder's evidence that the shed was custom made and could not be resold;
1(i) [The Senior Member erred in his findings that] the Builder was not entitled to claim under stage 4 because it had not adduced evidence of the loss it had suffered [142].
1(d) [The Senior Member erred in his findings that] the concrete slab had to be removed [124] because the slab and the shed combined would exceed the relevant height restrictions [120];
(1) the accepted quotation dated 23 March 2021 specified provision for a roller door 3.8 metres high and 5.4 metres wide at the entrance of the shed. Such a wide and high entrance must have contemplated access by vehicles and so the Tribunal was satisfied that the Owner had stipulated that the slab height should allow vehicular access through the north elevation of the shed [111] - [112]. A slab height of between 600 and 700mm at the roller door did not allow for vehicular access to the shed [116];
(2) the slab height significantly exceeded the slab height adduced from the approved plans and the height of the slab surface level relative to the natural land surface level did not allow vehicle access to the shed [120];
(3) accordingly the Builder had breached the statutory warranty under s18B(1)(a). The slab had not been completed in accordance with the plans and specifications as it did not allow vehicle access [121];
(4) rectification by reducing the slab height was not possible [122];
(5) the Tribunal preferred the Owner's expert's (Expert Moore's) opinion that the cost of demolishing the slab and removal of the spoil is $22,739.96;
(6) that cost should be borne by the Builder [123] - [124].
20. The limitation of the jurisdiction to the resolution of questions of law imposes a significant constraint upon the role of the Court in reviewing decisions of the Tribunal. The appealable error of law must arise on the facts found by the Tribunal or must vitiate the findings made or must have led the Tribunal to omit to make a finding it was legally required to make. A wrong finding of fact is not sufficient to demonstrate error of law .... Where the decision of the Tribunal involves matters of fact and degree, then provided it applies correct principles of law, no appeal will lie ....
21. The limits within which the jurisdiction is conferred require that it be exercised with restraint. Only in exceptional circumstances should the decision of the Tribunal not be the final decision ...
22. This translates to a practical as well as principled restraint. The Court will not be concerned with looseness in the language of the Tribunal nor with unhappy phrasing of the Tribunal's thoughts ... The reasons for the decision under review are not to be construed minutely and finely with an eye keenly attuned to the perception of error ...
76. What constitutes adequate reasoning on the part of a tribunal is also informed, in my opinion, by statements from well-known administrative law decisions relating to the limits of judicial review and the need for practical as well as principled restraint in that context: Pozzolanic at 287.
77. These principles include the following:
(i) "Decision-makers commonly express their reasons sequentially; but that does not mean that they decide each factual issue in isolation from the others. Ordinarily they review the whole of the evidence, and consider all issues of fact, before they write anything. Expression of conclusions in a certain sequence does not indicate a failure to consider the evidence as a whole": Re Minister for Immigration and Multicultural Affairs, Re; Ex parte Applicant S20/2002; Appellant S106/2002 v Minister for Immigration and Multicultural Affairs [2003] HCA 30; 77 ALJR 1165 per Gleeson CJ at [14] (Ex parte Applicant);
(ii) the court should not read passages from the reasons for decision in isolation from others to which they may be related: Re Maria Politis v Commissioner of Taxation [1988] FCA 739 at [14]; 20 ATR 108 at 111;
(iii) the reasons must be read fairly and as a whole: Ex parte Applicant at [147] per Kirby J; Wu Shan Liang at 291; Bisley at 251;
(iv) the reasons recorded ought not to be inspected with a fine tooth-comb attuned to identifying error: Collector of Customs v Pozzolanic Enterprises Pty Ltd [1993] FCA 356; (1993) 43 FCR 280 at 287; [1993] FCA 456 (Pozzolanic) at 287; Wu Shan Liang at 272, 291;
(v) there should be a degree of tolerance for looseness in the language of the tribunal, unhappy phrasing of the tribunal's thoughts or verbal slips: Pozzolanic at 287, Wu Shan Liang at 272 and 291.
"a constructive failure to exercise jurisdiction (or a purported exercise, in the sense that there is an appearance of an exercise of jurisdiction) as alleged by the appellant is not a mere failure to consider evidence or to address an argument or submission, which may be contingent or otherwise insignificant, but a failure to understand and determine a case or claim. The ultimate question is whether a failure to consider and address certain issues or arguments involved a failure to address central or critical elements of the case or claim: compare, in relation to failures to consider evidence, Minister for Immigration and Citizenship v SZRKT (2013) 212 FCR 99; [2013] FCA 317 at [69], [111]. It will be insufficient for the appellant to show that his 'three key issues' were not stated and determined discretely. What he must show is that they raised 'substantial' (in the sense of clearly material) arguments or questions which the primary judge in substance failed to address in determining the appellant's claim ...
(1) The appeal in 2024/423490 is allowed in part, and the matter is remitted solely for reconsideration of the damages to be awarded to the Owner for removal and replacement of the concrete slab, with leave given to the parties to adduce such further evidence as the Tribunal thinks fit.
(2) The cross-appeal in 2024/423504 is dismissed.
(3) Orders 1 and 3 are set aside.
(4) Order 2 is stayed until further order of the Tribunal or finalisation of the remitted proceedings, whichever is the earlier in time.
(5) The parties are to file any written submissions in relation to costs within 14 days and are to reply to each other's submissions 7 days thereafter. Submissions are to include whether the parties consider that the issue of costs may be determined on the papers in accordance with s 50(2) of the Civil and Administrative Tribunal Act 2013 (NSW).
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
(1985) 4 NSWLR 139
(1954) 90 CLR 613
(1992) 174 CLR 64
(1993) 43 FCR 280
(2003) 77 ALJR 1088
(1996) 185 CLR 259
(2022) 96 ALJR 497
(2017) 94 NSWLR 108
(2009) 236 CLR 272
(2013) 212 FCR 99