[2026] FCA 263
General information, not legal advice.
Federal Court of Australia
2026-03-17
Abraham J
Original judgment source is linked above.
TRANGIE-NEVERTIRE CO-OPERATIVE LIMITED ABN 87 517 177 968
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
Question 1: Is the start date of the applicant's claims against the second respondent 31 July 2024 or 21 May 2025?
[23] ...The language of r 8.21(1) is clear: an applicant may apply to the Court for leave to amend an originating application for any reason "including" any of the reasons in r 8.21(1)(a)-(g). Subrules (a) to (g) are examples of amendments that may be the subject of application. They are not a code. Thus, the interaction of r 8.21(1)(g) and (2) does not mean that the Court's power to permit an amendment asserted to involve a statute-barred claim is confined to the circumstances in r 8.21(1)(g)(i). We leave to one side for further argument the proper approach to an amendment introducing an unarguably statute-barred claim. Nevertheless, the following considerations undermine any rigid or bright-line approach exclusively based on r 8.21(1)(g) and r 8.21(2).
[24] The Federal Court Rules must also be construed as a whole. Apart from the fact that the power to apply to amend is expressed inclusively in the opening words of r 8.21(1), other rules disclose the true position.
Rules 1.32 to 1.35 are important weapons in the Court's armoury to enable the overarching purpose of the "civil practice and procedure provisions" (defined in s 37M(4) of the Court Act to comprise the Rules and "any other provision made by or under this Act or any other Act with respect to the practice and procedure of the Court") to be achieved as identified in s 37M(1) of the Court Act. The overarching purpose is to facilitate the just resolution of disputes according to law, as quickly, inexpensively and efficiently as possible. Faced with these provisions to construe r 8.21(1)(g) as an exclusive power to permit a statute-barred amendment let alone a merely arguably statute-barred amendment (as in the present case) only in the circumstances permitted by r 8.21(2), is inconsistent with the language of the Rules and inimical to the overarching purpose in s 37M of the Court Act. As the present case demonstrates, given the competing arguments about when the cause of action first accrued and the potential operation of s 55(1)of the Limitation Act, if there is a reasonable argument the claim is not statute-barred, there is no reason in principle that an amendment should not be permitted, particularly if all rights are preserved by the date on which the amendment takes effect being determined as part of the final judgment rather than on an interlocutory basis.
We refer to your letter of 29 November 2023 ... with respect to the membrane materials supplied by Firestone Building Products Europe Inc (now known as Holcim Solutions and Products EMEA BV) ...
We're asking for your recommendations on how to rectify these problems and whether this can be covered by a warranty.
Today, Firestone Building Products is proud to announce that it is adopting the Holcim name and brand identity, becoming the Holcim Building Envelope Division ...
....
Firestone, a premier provider of industry-leading roofing, wall and lining systems, is becoming Elevate. Building on Firestone's iconic brand and legacy, Elevate ....
...
Under the new Elevate brand, the people, products and standards trusted in the industry will remain the same ... Plus, the high-quality solutions, network of licensed applicators and industry-leading warranties will remain unchanged.
At the start of the meeting, Firestone presented their point of view about the ballast.
This is the largest EPDM job we have ever completed, equivalent to covering 213 soccer fields, it fills us with pride to be part of this success story and deliver a tangible, long-lasting solution to the local farming community.
We agree that the repair operations must be defined urgently and operated while the canals are empty to avoid damage escalation.
... with respect to the membrane materials supplied by Firestone Building Products Europe Inc (now known as Holcim Solutions and Products EMEA BV and referred to as "Holcim" below) ...
...if our construction [of the document] is right, at all times from 2018, before my client was involved, it assigned part of its business but not the relevant part, and it was dissolved in 2020 before my client was involved, and therefore there was no one ever to sue, the position doesn't change whether he was told that then or told that later.
Question 2-5: Is the start date of the applicant's claims against the first respondent 31 July 2024 or 21 May 2025?
This agreement is strictly on the basis that the Applicant has now confirmed that the breach of 'Firestone Warranty' cause of action pleaded against Holcim Solutions and Products EMEA in paragraphs 5, 27, 28, 31 and 54 of TNCL's Statement of Claim are in respect of no more than the 'Firestone Warranty' documents which are defined in paragraph 15 of TNCL's Concise Statement...
I certify that the preceding fifty-eight (58) numbered paragraphs are a true copy of the Reasons for Judgment of the Honourable Justice Abraham.
Trangie-Nevertire Co-Operative Limited
Holcim Solutions and Products EMEA [2026] FCA 263
(2021) 287 FCR 388
(2013) 225 FCR 79
(1992) 175 CLR 514