[2021] QSC 92
Supreme Court of Queensland
2021-05-10
Martin J
Original judgment source is linked above.
(a) for work undertaken on levels 13 and 14 of the building,
(c) for loss or expense incurred because of Aniko's removal of the work from Total pursuant to s 98(3) of the Act.
(a) the adjudicator's determination of the claim with respect to retention money was invalidated by jurisdictional error, namely, the adjudicator's consideration of a reason included in Aniko's adjudication response which was not included in its payment schedule,
(b) the adjudicator's determination of the third claim was invalidated by two jurisdictional errors being:
(i) his consideration of a reason included in Aniko's adjudication response which was not included in its payment schedule, and
(ii) his failure to consider a relevant document properly submitted by Total in support of its claim.
(a) the amount of the progress payment, if any, to be paid by the respondent to the claimant (the adjudicated amount); and
(b) the date on which any amount became or becomes payable; and
(2) In deciding an adjudication application, the adjudicator is to consider the following matters only -
(a) the provisions of this chapter and, to the extent they are relevant, the provisions of the Queensland Building and Construction Commission Act 1991, part 4A;
(b) the provisions of the relevant construction contract;
(c) the payment claim to which the application relates, together with all submissions, including relevant documents, that have been properly made by the claimant in support of the claim;
(d) the payment schedule, if any, to which the application relates, together with all submissions, including relevant documents, that have been properly made by the respondent in support of the schedule;
(e) the results of any inspection carried out by the adjudicator of any matter to which the claim relates.
(3) However, the adjudicator must not consider any of the following -
(a) an adjudication response, to which the adjudication application relates, that was not given to the adjudicator within the time required under section 83;
(b) a reason included in an adjudication response to the adjudication application, if the reason is prohibited from being included in the response under section 82.
(b) must identify the adjudication application to which it relates; and
(c) may include the submissions relevant to the response the respondent chooses to include.
(4) However, the adjudication response must not include any reasons (new reasons) for withholding payment that were not included in the payment schedule when given to the claimant.
(5) The adjudicator may require the respondent to resubmit the adjudication response without the new reasons." (emphasis added)
(a) identifies the payment claim to which it responds; and
(b) states the amount of the payment, if any, that the respondent proposes to make; and
(c) if the amount proposed to be paid is less than the amount stated in the payment claim - states why the amount proposed to be paid is less, including the respondent's reasons for withholding any payment; and
(d) includes the other information prescribed by regulation."
(a) An entity which claims to be entitled to a payment under a construction contract will give a "payment claim" to the respondent.
(b) The respondent will give the claimant a "payment schedule".
(c) The claimant will lodge with the registrar an "adjudication application" and give a copy to the respondent. The claimant is permitted to include the submissions relevant to the application which it chooses to include.
(d) The registrar will refer the application to an adjudicator. If the referral is accepted the adjudicator will be taken to have been appointed to decide the application.
(e) The respondent will give the adjudicator an "adjudication response" to the adjudication application. The respondent is permitted to include the submissions relevant to the response which it chooses to include.
(a) First jurisdictional error: consideration of a new reason concerning the claim for retention money;
(b) Second jurisdictional error: consideration of a new reason concerning the claim for loss or expense for removal of work; and
(c) Third jurisdictional error: failure to consider a relevant document concerning the claim for loss or expense for removal of work.
The power to set aside an adjudicator's decision on the ground of jurisdictional error
"[60] I have reviewed the submissions from both the parties and agree with the respondent's position that Clause 18 of the Contract afforded the right to the respondent to terminate the Contract and not the claimant.
[61] At paragraph 120 of the Adjudication Application states "these breaches by the respondent justified termination by the claimant.
[62] I concur with the Respondent's position that the Contract was terminated by the Claimant and it follows, that the criteria of clause 18 has not been met to avail the Claimant of the relief it seeks.
[63] I also agree that Clause 16 provides that the parties must agree to alter the Defects Liability Period and has no such agreement has been demonstrated, I conclude that the Defects Liability Period is 52 weeks.
[63] Hence, I concur with the respondent's position that the claim for Release of Retention is premature.
[64] Therefore, I value the Release of Retention as NIL"
"[78] Again, according to the respondent it follows that on the proper interpretation of the Act together with the relief sought by the Claimant, the Adjudicator must decide what works had been removed from the scope of the Contract by the Respondent prior to 16 May 2019.
[79] In the Adjudication Response, the respondent provides evidence in the forms of Statutory Declarations from the respondent's representatives: Scott McGuren, paragraphs 5-8; Statutory Declaration of Bobbie Walker, paragraphs 4-7; and Statutory Declaration of Nathan Edward McGregor paragraphs 5-1; that state that the respondent did not enter into a Contract with another entity until 20th May 2019.
[80] The respondent in the Adjudication Response states that there was no legal relationship between the respondent and the third party until 20th May 2019, that is capable of satisfying the "removal" of work in the context of section 98(3) of the Act, the word "remove" denotes a positive and successful act of the respondent.
[81] The respondent's position as of 16th May 2019, when the claimant purported to terminate the Contract and thus ending the suspension period, no works had been removed from the Contract by the respondent.
[82] I have reviewed Section 98 of the Act, the respondent and claimant's positions and am satisfied that no work was removed from the claimant's Scope of Works as at 16 May 2019.
[83] the evidence was clear that a Contract was in place from 20 May 2019 with a third party, which was four days after the claimant had terminated the Contract.
[84] I therefore conclude that has no works were taken from the claimant's hands that no right to Statutory Damages under Clause 98 (3) of the Act exists for either the loss of income in the amount of $107,873.48 (excl GST) or the new presented claim for Level 13 works in Adjudication Application as "loss and expense incurred" pursuant to section 98 (3) of the Act in the sum of $53,532.73 (excl GST) and therefore I value this work as NIL."
(a) Total sought to include losses that resulted from an alleged repudiation of the construction contract, rather than a loss or expense incurred as a result of the removal of work from the contract during the suspension;
(b) Total had not identified the alleged works that were removed from the contract by Aniko during the suspension;
(c) Aniko could not respond to the quantum claimed for loss and expense as Total had not provided the project budget documentation;
(d) Total's claims for items procured but not installed before the termination of the contract, demobilisation costs following the suspension of works and costs and preliminaries during the suspension period were misguided for several reasons unrelated to the date on which the third party was engaged; and,
(e) Total could not complete the works as the material required for the work on level 14 was being held in China.
(a) no work had been removed from Total's contract at 16 May 2019, and
(b) four days after Total had terminated the contract, another contract was in place with a third party.
(a) what works, if any, were removed from Total's scope of works during suspension of the contract, and
(b) what loss or expense had been incurred by Total as a consequence.
"On 15 May 2019, I personally contacted the other trade contractor and confirmed that they had already attended site and performed inspections, and provided quotations for completing the entirety of the works at the Project. On 16 May 2019, I received confirmation from Tweed Coast Glass that they had received a Purchase Order to perform the remaining work, and that the quotation they had provided had been accepted by [Aniko] with the instruction to immediately proceed with the remaining works."
"... in circumstances in which adjudicators are required to determine complex legal issues quickly, the detection of flaws in reasoning or poorly expressed reasons in an adjudication decision do not compel the conclusion that the adjudicator did not attempt to understand and apply the contract. Adjudicators provide their determinations in a "somewhat pressure cooker environment". In some instances the adjudicator "cannot possibly, in the time available and in which the determination is to be brought down, give the type of care and attention to the dispute capable of being provided upon a full curial hearing" stop the Court should be slow to conclude that adjudicators who work under the very tight deadlines imposed by the Act, and who, in seeking to do their best, make a mistake, have not acted in good faith." (citations omitted)
[1] Northbuild Construction Pty Ltd v Central Interior Linings Pty Ltd [2011] QCA 22; [2012] 1 Qd R 525, 550-556 [67]-[80] per White JA (McMurdo P and Chesterman JA agreeing).
[2] (2020) 4 QR 410 at 422-428 [32]-[42].
[3] [2009] QSC 205; [2010] 1 Qd R 302 at 323 [66].
Total Lifestyle Windows Pty Ltd
Aniko Constructions Pty Ltd & Anor [2021] QSC 92