[2020] TASSC 27
Supreme Court of Tasmania
2020-06-26
Blow CJ, Mr P
Original judgment source is linked above.
CITATION: Timber World Pty Ltd v Meander Valley Council [2020] TASSC 27
APPEALED FROM: Timber World Pty Ltd v Meander Valley Council
and Teen Challenge Inc [2019] TASRMPAT 12
Environment and Planning - Environmental planning - Planning schemes and instruments - Tasmania - Other matters - Validity of provision in planning scheme - Uncertainty.
King Gee Clothing Co Pty Ltd v Commonwealth [1945] HCA 23; (1945) 71 CLR 184; Richard Bejah Insurance and Financial Services Pty Ltd v Maning [2002] TASSC 36, 123 LGERA 349, distinguished.
Judgment Number: [2020] TASSC 27
Objective: Only in exceptional circumstances should vulnerable uses be located on land which is within a bushfire-prone area. If a vulnerable use is proposed to be located on land which is in a bushfire-prone area, bushfire protection measures must reduce the risk to firefighters, and must reflect the risk arising from the bushfire-prone vegetation and the characteristics, nature and scale of the use taking into consideration the specific circumstances of the occupants including their ability to:
- protect themselves and defend property from bushfire attack
- understand and respond to instructions in the event of a bushfire.
P1 Where a vulnerable use is proposed to be located in a bushfire-prone area it must be demonstrated that:
A2.1 A bushfire hazard management plan that contains appropriate bushfire protection measures that:
"But to resolve ambiguities and uncertainties about the meaning of any writing is a function of interpretation and, unless the power under which a legislative or administrative order is made is read as requiring certainty of expression as a condition of its valid exercise, as the by-law-making powers of certain corporations have been understood to do, the meaning of the order must be ascertained according to the rules of construction and the principles of interpretation as with any other document."
"It needs no imagination to see that in drafting an order for the fixing of prices for an important trade many difficulties must be encountered and it would be impossible to avoid ambiguities and uncertainties which are bound to arise both from forms of expression and from the intricacies of the subject. But it is not to matters of that sort that I refer. They depend upon the meaning of the instrument and they must be resolved by construction and interpretation as in the case of other documents. They do not go to power. But it is another matter when the basis of the price, however clearly described, involves some matter which is not an ascertainable fact or figure but a matter of estimate, assessment, discretionary allocation, or apportionment, resulting in the attribution of an amount or figure as a matter of judgment. When that is done no certain objective standard is prescribed; it is not a calculation and the result is not a price fixed or a fixed price. That, I think, means that the power has not been pursued and is not well exercised."
"[30] ... Such an analysis in the Tribunal's view would require:
(a) An analysis of the zoning and its compatibility with the proposal;
(b) An assessment of whether the development standards applicable to the proposal could be met at the alternative site. If the alternative site was in a bushfire prone area such an assessment would require an assessment of bushfire risk which would need to identify a lower-risk than the risk identified for the proposed location;
(c) It may also be that a lower-risk alternative site identified may require compliance with different development standards in a different planning scheme that could not be met by the proposal and suitability therefore is not able to be established. It may require a Planning Application to be lodged with the relevant planning authority to ascertain whether the alternative site was an appropriate site for the proposal.
(d) It may also be that although an alternate site is deemed by Planning Authority to be suitable for the proposal, it may still not meet the 'lower-risk' requirements in terms of bushfire, contemplated by sub-paragraph (b).
[31] The Tribunal accepts Mr McElwaine's submission that absent an approval, the suitability of the alternative site cannot be known.
[32] It is the uncertainty with respect to the scope of the inquiry that results, in the Tribunal's view, in the provision being incapable of application in an objective sense. It must therefore, be ultra vires as it sits beyond the power to make delegated legislation. To borrow the words of Crawford J (as he then was) in Bejah - the impossibility objectively of understanding what is encompassed by the requirement to demonstrate that there is no suitable alternative lower-risk site, renders the provision ultra vires as it is not a true exercise of the delegated power. As submitted by Mr McElwaine and accepted by the Tribunal, it is not possible to address the requirements of sub-paragraph (b) because that analysis would be infinite in its scope. Objectively the requirements [sic] to demonstrate the absence of any suitable alternative lower-risk site means that the discretion with respect to P1(b) can never be exercised. This is likely to be the case regardless of the geographical scope of the inquiry."
"(3) If the provision itself is clear, the fact that its application, generally or in particular cases, may be difficult or burdensome, is immaterial."
Timber World Pty Ltd
Meander Valley Council [2020] TASSC 27
(1945) 71 CLR 184
(1946) 71 CLR 210
(1993) 43 FCR 280
(1996) 185 CLR 259
(1995) 57 FCR 25