[2010] NSWDC 331
District Court of NSW
2010-12-09
Original judgment source is linked above.
INTRODUCTION
PERSONS INVOLVED 6. It is convenient to list some of the people and corporations that will be referred to in the course of the judgment. They are as follows: 1 Tilley Air Conditioning Pty Ltd is the plaintiff and cross-defendant 2 Traminer Industries Pty Ltd is the defendant and cross-claimant 3 William Tilley is a director of the plaintiff 4 Darren Beecroft is a director of the defendant 5 Brad Aitken was the plaintiff's initial project manager on the site 6 John Hopkins was the plaintiff's project manager for two weeks when Brad Aitken was away 7 Cameron Howes was the plaintiff's project manager from mid-December 2001 on the site 8 Remy Logel was a design engineer employed by the plaintiff 9 Michael Auld was a principal of SydFab Pty Ltd, manufacturer and supplier of ductwork 10 Ian Summers was the Traminer's foreman onsite from September 2001 to May 2002 11 Glen Willmott was Traminer's foreman onsite from May 200212 Michael Sturgess was a quantity surveyor called to give opinion evidence on behalf of Tilley 13 Joseph Maric is the commercial manager of Equilibrium Air Conditioning and was called to give opinion evidence for Traminer 14 TAB Ltd was the client for the project 15 APP Projects Pty Ltd was the project manager 16 AHW Engineering Planning & Management was the mechanical consultant to the project 17 Prime Constructions was the project builder
GENERAL CONTRACT ISSUES Introduction 7. Both parties assert that they were in a contractual relationship with each other. The fundamental components of that contract are common ground. It was a contract for Traminer to undertake certain work for Tilley at a site in Harris Street, Ultimo. Tilley would pay Traminer an agreed lump sum for that work. The work comprised the supply and installation of air conditioning ductwork and of insulations and the undertaking of demolition work by Traminer. It was also common ground that the terms of the contract were partly written and partly verbal. Beyond those fundamental components many other aspects of the contract are in dispute. There has been disagreement over - · some of the documents comprising the written part of the contract · the date the contract was made · whether there was more than one contract · certain important terms of the contract. · 8. The areas of dispute, so far as general contractual issues are concerned, was put in writing by counsel in the list of issues. There were six areas concerning the contact and they are these - Issue 1. What are the contract documents? Issue 2. What are the terms of the contact? Issue 3. Under the terms of the contract is the plaintiff entitled to recover monies from the defendant with respect to reduction in the scope of its works? Issue 4. Was the executed contract a complete contract, or was the demolition a separate and divisible contract? Issue 5. Whether the AHW specifications formed part of the contract? Issue 6. The date the contract was formed?
ISSUE 1: WHAT ARE THE CONTRACT DOCUMENTS? 10. The documents over which the parties differ as being part of the contract comprise: . Which set of plans? . Tilley's purchase order 15 October 2010 . The specifications.
REMY: 'Here are the plans. Have you priced this job?'
ME: 'Thanks for the plans. No, I have not priced it.'
REMY: 'Tilley is in the final stage of winning the job. Would you like to give us a price?'
ME: 'Yes, no problem. I will get back to you.' " 13. Confronted in cross-examination by the fact that the plans annexed to his affidavit could not have been in existence when he was asked to quote for the project, Darren Beecroft agreed that the plans at tab 1 of DJB 1 were not the plans given to him by Remy Legal at the meeting. Dealing with which drawings he had quoted on Mr Beecroft said in evidence at T 543- "I quoted off the drawings that were given to me and I think I've actually stated there that we agree with Mr Tilley's plans and that's what the take-offs were done on, and we agreed on that. I agreed, and that's what we would have used ." 14. Traminer did not attempt to suggest that the concession was wrong. The conclusion is irresistible and I find, as invited by Mr Bland, that- " The plaintiff's version of the tender plans located at BT8...should be preferred and accepted as the tender plans ." 15. Mr Bland argues that the confusion of Mr Beecroft over the plans, and the many assertions in his affidavit about the version of the plans given to him by Remy Logel, must damage his credibility. Mr Loewenstein argues that Mr Beecroft's credibility is not so affected. The question of Mr Beecroft's credibility I will deal with later in this judgment.
ISSUE 2: WHAT ARE THE TERMS OF THE CONTRACT? 16 As Mr Bland pointed out, at clause 25 of his submissions dated 30 November 2008, there are "two issues that arise between the parties in respect to the terms of the contract. They are firstly, the terms of the contract relating to demolition...and the terms of the contract relating to positive and negative variations."
ISSUE 3: UNDER THE TERMS OF THE CONTRACT IS THE PLAINTIFF ENTITLED TO RECOVER MONEYS FROM THE DEFENDANT WITH RESPECT TO REDUCTION IN THE SCOPE OF ITS WORKS?
Traminer's position is that whilst it was entitled to claim for an increase in the scope of works, there was no evidence - documentary, verbal or course of conduct - to support any entitlement of the plaintiff to obtain from the defendant the value of any reduction in the scope of work.
Traminer went to some effort to avoid what would appear to be the fairly obvious consequence of admitting clauses 7 and 8 of the amended statement of claim. The consequence was that those pleaded terms did not require proof by evidence.
First, Mr Loewenstein argued that his client's admissions of clauses 7 and 8, when read in context, are admissions with respect to removal of old ductwork or demolition only. He points to the references in clauses 5 and 6 of the amended statement of claim to demolition and removal of old ductwork.
I do not accept that argument. Clauses 4 to 8 inclusive of the amended statement of claim plead terms of the contract. Each pleads a distinct term, sometimes in the alternative. The references in clauses 5 to 6 to demolition and removal of old ductwork do not influence, in my opinion, the meaning of the terms pleaded in clauses 7 and 8 of the amended statement of claim. Even if the context argument had some force, the context must include clause 4, which relates to the works generally, and is not limited to demolition or removal.
Mr Loewenstein next argues that clause 12 of the amended statement of claim, which is denied by his client, is of relevance in the limiting of clauses 7 and 8 to demolition. Clause 12 of the amended statement of claim reads as follows- " 12. Further, or alternatively, the contract sum is to be adjusted in favour of the plaintiff in respect to variations in the scope of works which resulted in some works not being carried out by the defendant and/or a reduction in the scope of works and/or temporary works having to be undertaken. " I have not included reference to the particulars given to that paragraph. Mr Loewenstein argued, in clause 14 of his written submissions of 24 November 2008, that if paras 7 and 8 "were intended to refer to all the works and not just demolition works, then that would render para 12 ... of no utility."
I do not accept that argument. Clauses 7 and 8 plead terms of the contract. Clause 12 pleads facts: variations, reductions in scope of works and a legal consequence - the contract sum is to be adjusted. The legal consequence follows from the operation of cl 7. All clauses have their utility.
Mr Loewenstein refers to what was said by him regarding an amendment to the defence. The amendment was foreshadowed but not pressed after Mr Bland foreshadowed an adjournment application if the application was allowed. The consequence of the amendment was made abundantly clear by Mr Loewenstein at T 71 where he said as follows- "Your Honour, I should just add that the broad propositions of law that were stated in relation to lump sum contracts are not resiled from as a matter of principle, but insofar as there have been admissions made, and with the spectre of a possible application from adjournments, we are not proceeding to press the issue about lack of entitlement to deduct moneys back." 27. I accept Mr Bland's submission that the defendant is bound by that conduct.
Mr Loewenstein further argues that his client's admission of clauses 7 and 8 is inconsistent with its denial of clause 12 of the amended statement of claim but in my opinion this argument is convincingly met by Mr Bland at clause 6 of his written submissions dated 26 November 2008 where he said as follows- " Para 12 of the statement of claim is pleaded as a consequence of the terms pleaded, that is, the contract price is varied. Para 12 is denied by the defendant as it did not intend to deny the terms, but rather the amounts said to be adjustable...Any event it was made clear on the transcript and the defendant did not amend their pleadings, they are now bound by their conduct ." As I said, I accept that submission. There is, in my opinion, no inconsistency between the admission of clauses 7 and 8 and the denial of clause 12.
I am not assisted by general submissions about the nature of "rise and fall" clauses. It is the pleadings in this case that I am interpreting. The intention of this pleading is made manifest at T 71. I am not suggesting that Mr Loewenstein was, himself, the pleader of the defence.
Mr Loewenstein goes on to argue that clauses 7 and 8 plead terms which do not impose an obligation on his client. That may arguably be true of clause 7 but clause 8 pleads a term that in the event of a variation "the contract price would be adjusted between the plaintiff and the defendant".
Mr Loewenstein goes on to argue that the breach of contract referred to in clause 11 of the amended statement of claim is not a breach of the terms pleaded in clauses 7 and 8. That is true. It seems to me that it is clause 12 which pleads the relief related to the contractual obligations pleaded in clauses 7 and 8.
Mr Loewenstein's fallback position was to acknowledge that clauses 7 and 8 had been admitted but to argue that they pleaded terms of the contract that provided for omissions or variations by mutual agreement between the parties. Mr Loewenstein said in his submissions dated 21 December 2009 that to suggest that Tilley after commencement of the works or at any stage of the works being undertaken by Traminer "could remove a large portion of the works without agreement is a proposition not only unsupported by any evidence in the interests of the plaintiff but also unsupportable on the premise of any sound commercial efficacy in dealings between two commercial entities. No admissions have been made by Traminer as to any such allegation in any event."
Mr Loewenstein developed the argument about mutual agreement in oral submissions on 18 January 2010. He said at T 14 of the transcript of that day that it would be an "unreasonable interpretation" of the pleaded clauses to construe them as meaning that "two commercial entities reaching an agreement and admitting that an agreement has been reached to the effect there could be a unilateral withdrawal of works without agreement by one party to the contract at any point of time including the conclusion of the works and such withdrawal ...that if I could call it unreasonable interpretation could include provision of contract works to another subcontractor and that a party would agree to that contractual arrangement."
The essential question is what clause 7 "really means" as was said by counsel in the oral submissions but Mr Loewenstein's stated position at T 71 at the commencement of the proceedings must be seen in the context of his proffered interpretation of clause 7. I do not accept his argument. It confuses variations to the contract with a provision in the contract allowing for variation of works.
In Building and Construction Contracts in Australia, Dorter and Sharkey, 2nd ed, the authors at [8.10] say that the word "variation" is "generally employed in the context of building and construction contracts to denote one of two types of change". The first they describe as signifying "a change in the contractual terms upon which the relevant work is to be carried out." The authors continue - " Secondly, and more commonly, the word is used to signify an alteration, whether by addition or omission, to the work which the contractor is required by the contract documents to perform ." A similar distinction is made by Duncan Wallace QC, the author of the 11th ed of Hudsons Building and Engineering Contracts at p 877 [7.0001]. Hudson's makes the distinction even sharper at p 46 at [1.091] where, after discussing variations in the terms of a contract between parties, the author relevantly says- " None of the forgoing discussion, which relates to changes or variations made to the contractual provisions of a contract (including, if necessary, the description of work undertaken) is, however, applicable to variations of the work ordered under the express power conferred on the owner...'variations'...which is found in nearly all standard forms of construction contract ." The emphasis is in the original.
It seems to me to be clear from clauses 7 and 8 that what is being pleaded by Tilley and admitted by Traminer are terms which provide, not for variation of the contract but for variation of the contract works. I accept Mr Bland's submission at T 28 of the transcript of 18 January 2010 where he said that the terms pleaded mean that "there is a unilateral power within the contract to vary the works, the contract works."
Mr Loewenstein argued that even if the plaintiff had a power to reduce the scope of works it was not entitled to recover monies for any such reduction. This was because Tilley purported to exercise such power after the event or at the conclusion of the contract. Mr Loewenstein argued over T 38-39 in his oral submissions on 18 January 2010 that "the normal way is for there to be a claim or notification during the process of the works" and not an adjustment at the end of the project. Mr Loewenstein referred to a letter dated 19 June 2003 from Tilleys to Traminer which appears at tab 35 of exhibit 7, Mr Beecroft's affidavit at p 6. Mr Loewenstein said that this was an "attempt at reconciliation between the variations claimed by Traminer and the amount that it asserts Traminer owes them back because of the reduction in the scope of works" (T40, 18 January 2010).
In his written submission in response which became MFI 26, Mr Bland pointed to the evidence led on behalf of Traminer which acknowledged that the terms of the contract permitted a reconciliation at the end of the project. It referred to evidence in the affidavit of Mr Willmot, exhibit 9, where Mr Willmot said as follows: " 11. When I first became the foreman I would ask for written site instructions as in my previous employment as foreman. I would be given written instructions (these are written notes confirming the work required to be done in addition to any work shown on construction drawings) but was told by Cameron words to the effect:-
Me: 'Darren I am not being given anything in writing, they said that it gets fixed at the end.' Darren: 'Just do the work, we have a good relationship with Tilley's. ' 39. In Mr Beecroft's affidavit of 27 July 2007, which became exhibit 7, over clauses 204-207 he outlines a discussion he had on 18 January with Cameron Howes about "non payment" for work performed by Traminer. It is clear from at least one of the items (number 16 over pp 41-42) that Traminer was prepared to acknowledge deductions from the works in a reconciliation process. There was also a reference to an affidavit produced on behalf of Tilley. It was Cameron Howes' affidavit of 16 January 2007, which became exhibit B1. At clause 18 of that affidavit Mr Howes said as follows: " 18. It was a common occurrence during the works that I would give oral instructions to Mr Beecroft of Traminer to change the scope of works. Sometimes these changes would result in increased work for Traminer and sometimes it would result in less work for Traminer ." Mr Bland points out that this assertion was not challenged by Mr Beecroft in his affidavit dated 24 July 207 where at clause 282 he responded to Cameron Howes' affidavit.
Mr Loewenstein quite properly directed my attention to the Court of Appeal decision in BB Constructions (Aust) Pty Limited v Brian A Cheeseman Pty Limited (1994) 35 NSWLR 227 which is some authority for the proposition that the expression "variations" can include a reference to back charges.
I am satisfied on the balance of probabilities from this evidence that Traminer has acknowledged that there was a common understanding between the parties that variations to the works made during the course of the performance of the contract would be the subject of a process of reconciliation at the end of the project. This common understanding amounts to at least an implied if not an express term of the contract.
Accordingly I find that under the terms of the contract, Tilley was entitled to recover money from Traminer with respect to the reduction in the scope of works. ISSUE 4: WAS THE EXECUTED CONTRACT A COMPLETE CONTRACT OR WAS THE DEMOLITION A SEPARATE AND DIVISIBLE CONTRACT?
Both Traminer and Tilley assert that the contractual arrangements for demolition work were part of the main contract. I agree with them for the reasons put forward by Mr Bland at clause 70 of his written submissions dated 13 November 2008- " The dispute between the parties relates to not the fact the demolition work was included in the contract, but rather, the extent to which demolition was required and to some extent, as raised by the defendant, whether there were representations by the plaintiff that would have the effect of limiting the amount of demolition required ". ISSUE 5: WHETHER THE AHW SPECIFICATIONS FORMED PART OF THE CONTRACT
I turn now to the question whether the contract included specifications. The specifications for the project appear in exhibit A2 at tab BT10. They were prepared by AHW Pty Limited Consulting Engineers and received by the builder Prime Constructions on 24 August 2001.
As Mr Loewenstein said in written submissions of 13 November 2008- "A material difference between what is asserted by the plaintiff as having been provided to Mr Beecroft and what Mr Beecroft says to the best of his ability he received, are the AHW specifications." Mr Tilley acknowledged in evidence at T 188 that the specifications was "one of the documents…left at…reception for collection by Mr Beecroft".
Mr Beecroft says that he "never got the specifications" and it "wasn't given to me". The significance of his client not having the specifications is explained by Mr Loewenstein at clause 1.11 of his written submissions of 13 November 2008 in terms of what it included. He said as follows- " The failure to provide the specifications to Mr Beecroft is material insofar as, amongst other matters, the specifications provide a note of the completed drawings…the requirement for 'demolition and removal of existing central plant systems and risers which become redundant under the refurbishment works'; the demolition and removal of existing systems and installations generally…the demolition and removal of existing systems and installations generally as set out in 1.624 on page 14 of the same exhibit to Mr Tilley's affidavit. Also within the specifications was provision for the nature of insulation to be provided (at S.6)." 47. Mr Bland argues that the specifications are incorporated by reference into the documents forming part of the contract between his client and Traminer. He relies on the document "GENERAL NOTES" in exhibit A2 at tab BT9 which is drawing number 20125MO1E.
Mr Bland argues that Traminer would have noted "three metres for insulation on his quotation." But the insulation quotation really came from SydFab. That is, in my opinion, no answer.
Also it is the case that Darren Beecroft trusted his relationship with Tilley.
Mr Bland argues that there were no variation claims for insulation, but there were such claims as appears in Mr Loewenstein's submissions at clause 39.
Although Mr Tilley can say that the specifications were included in the documents left at reception for Mr Beecroft, he cannot assert that Mr Beecroft himself collected from reception what had been left there. This is clear from the cross-examination of Mr Tilley at T 233. Mr Tilley could not say how long it was between him leaving the documents at reception and noticing they were gone, except that it was the same day.
The person who would be able to throw relevant light on what documents Darren Beecroft was provided by Tilley is Remy Logel. He has not been called by either party as a witness.
It seems to me that I should approach this issue of the absence of Remy Logel's evidence on this issue as follows. Mr Bland argues that Traminer has had contact with Remy Logel since the commencement of proceedings and that Remy Logel is no longer working with his client. Mr Bland also points out that Traminer has the onus to prove what it asserts Mr Logel said. Mr Loewenstein argues that Remy Logel is a former senior employee of Tilley's. At T 157 Mr Tilley described Mr Logel as a design engineer.
I should also add here that at least one of the conversations which Mr Beecroft asserted occurred between him and Mr Logel was in the presence of the then project manager for Tilley's Brad Aitken.
In this case it is Traminer as defendant which asserts the terms of a contract based upon oral representations by a person I regard as a senior employee of Tilley. I regard him as a senior employee because he is a design engineer and because he was obviously involved in the discussions with Mr Beecroft regarding the contract. The same representations are said by Traminer not only to amount to terms of the contract, but also to be misleading and deceptive. Essentially in its defence to the cross claim, Tilley denied that the representations were made.
Mr Beecroft gave his evidence about the representations made by Mr Logel in very clear terms. Part of that evidence was supported by Mr Auld, who said that he was present on one occasion when a relevant representation was made by Mr Logel. There is some support also from Mr Summers, who recounts a conversation with Cameron Howes which is consistent with what Mr Beecroft says Mr Logel was asserting.
Both Mr Bland and Mr Loewenstein assert that I should draw against their respective opponent the unfavourable inferences which are referred to and known to lawyers as the inferences in Jones v Dunkel (1959) 101 CLR 298.
In Brandi v Mingott (1976) 12 ALR 551, in a joint judgment, Gibbs ACJ and Stephen, Mason and Aickin JJ said at 560 the following- "When both sides fail to call available evidence competing inferences arise and it will then be for the tribunal of fact to consider the evidence which is before it, in the present case coming exclusively from the appellant and his witnesses, in the light of such inferences." 66. In AMP Services Limited v Manning [2006] FCA 256, Finkelstein J, in delivering his judgment in the Federal Court, referred to a decision of the Full Court of the Supreme Court of Victoria in Erle v Castlemaine District Community Hospital [1974] VR 722 and then said at [49] by reference to the judgment of Little J the following- " The judge went on to say that it would be erroneous to lay down any single 'general rule' that if a witness was available to both parties no inference could be drawn against either and that it must depend on the facts and circumstances of a particular case. This, I think, is the correct view." 67. In Manly Council v Byrne [2004] NSWCA 123, Beazley JA in the New South Wales Court of Appeal said the following at [71]- " But the fact that a witness who was not called is equally available to plaintiff and defendant is not always sufficient to avoid a Jones v Dunkel inference against either, or both, of those parties." Her Honour went on to say in the following paragraph that in certain circumstances it would be "more natural" for the plaintiff in that case to call certain witnesses which she did not call "because the plaintiff had the onus of proof, the proof she had presented was thin". Beazley JA was hypothesising the circumstance that the proof was thin. Her Honour also pointed out in the same paragraph that, having the onus of proof "is not essential to whether it is 'more natural' for one party to call a witness - sometimes it is enough if an onus of adducing evidence is on that party." Her Honour went on to conclude, however, that in that case the evidence presented on behalf of the plaintiff was not thin, but was "ample" to determine the issue which was the subject of the competing inferences.
ISSUE 6 - THE DATE THE CONTRACT WAS FORMED 72. Whilst initially arguing that the contract documents must have included the plaintiff's purchase order of 15 October 2001, Mr Bland later acknowledged at clause 104 of his written submissions of 13 November 2008, that whilst "it is arguable that the plaintiff's purchase order dated 15 October 2001 constituted a formal acceptance of the offer by the defendant dated 27 August 2001, it is more reasonable to conclude that, in the absence of evidence to the contrary, the contract between the parties was formed prior to the commencement of the works in mid-September 2001 when the plaintiff informed the defendant it would start works on site."
HIS HONOUR: I am going to take the morning tea adjournment and take some papers with me.
MCCROSTIE: Your Honour with your leave might I be excused to be replaced at the bar table by Mr Ratnam from my staff?
HIS HONOUR: Thank you for attending Mr McCrostie and for your assistance on that issue, I appreciated it.
HIS HONOUR: Now Mr Ratnam I note your appearance now for the plaintiff, thank you.
METHODOLOGY OF VALUING CLAIMS ISSUE 7: WHAT IS THE APPROPRIATE METHOD OF VALUING TRAMINER'S RATE FOR DUCTWORK
TEMPORARY SCOPE OF WORKS 82. Traminer says it did not receive the specifications and I have so found. So that to the extent that temporary works are provided for in the specifications, it was not made known to Traminer. The quotation makes no reference to temporary works as part of the tender. Mr Tilley said that a letter from AHW dated 16 July 2001 contained a reference to and was a basis for the temporary works valued at $73,493. There is no evidence that that letter, which was at tab 4 to Mr Tilley's affidavit, was provided to Mr Beecroft. Mr Beecroft denies awareness of the amendments referred to in that letter and says he was never asked to quote for temporary works.
ISSUE 9: PLAINTIFF'S STATEMENT OF ISSUE: WHETHER THOSE TEMPORARY WORKS (THE TEMPORARY WORKS ATTACHED AS ANNEXURE TO THE AMENDED STATEMENT OF CLAIM, AS REFERRED TO IN ISSUE 8) WERE NOT UNDERTAKEN BY TRAMINER INDUSTRIES. DEFENDANT'S STATEMENT OF ISSUE: WHETHER THE DEFENDANT DID UNDERTAKE TEMPORARY WORKS IN THE LEVEL 4 PLANT ROOM (THE DEFENDANT CONCEDES THAT IT DID NOT PERFORM TEMPORARY WORKS IN OTHER PARTS OF THE SITE, ON THE BASIS THAT SUCH WORKS WERE NOT INCLUDED IN THE CONTRACT DOCUMENTS PROVIDED TO IT). 85. As the title of this issue indicates, Traminer concedes that it did not perform temporary works, apart from the level 4 plant room. The only temporary works required was the level 4 plant room, which Traminer claims for in item 18 of the schedule to the cross-claim.
ISSUE 10: THE VALUE OF THOSE TEMPORARY WORKS 86. Mr Loewenstein argues that the temporary works can only be valued on the basis of rates agreed between the parties to the contract. Mr Loewenstein argues that Traminer made no provision for temporary works or their price, so it is an irrelevant exercise. I have found that they were not part of the contract. If I had to value them, I would accept Mr Sturgess's evidence of a value of $80,843, excluding GST, but I note that Traminer claims no more than $73,493, excluding GST, which if it was necessary, I would so find.
DUCTWORK DELETED FROM STAGE 10 ISSUE 11: WHETHER THE CONTRACT DOCUMENTS PROVIDED FOR DUCTWORK AT STAGE 10
ISSUE 12: PLAINTIFF'S STATEMENT OF ISSUES: WHETHER THE DUCTWORK AT STAGE 10 WAS NOT UNDERTAKEN BY TRAMINER INDUSTRIES. DEFENDANT'S STATEMENT OF ISSUE: WHETHER THE DUCTWORK AT STAGE 10 WAS MODIFIED BY INSTRUCTION OF TILLEY AND WHETHER TRAMINER PERFORMED THAT WORK. ISSUE 13: PLAINTIFF'S STATEMENT OF ISSUES THE LIABILITY, QUANTUM AND VALUE OF THE DUCTWORK DELETED OR NOT UNDERTAKEN BY TRAMINER. ISSUE 14: PLAINTIFF'S STATEMENT OF ISSUES WHETHER THE EXPERTS HAVE APPROPRIATELY ALLOWED FOR THIS DUCTWORK IN THEIR RESPECTIVE REPORTS. 89. Mr Bland argues that Traminer has not discharged its burden of proof regarding its variation claims. He argues that the joint conclusion of the experts is that the as built plans show less ductwork at an agreed amount than in the tender plans. The majority of the variation claims, he argues, are accounted for. This is supported, he argues, by SydFab's variation registration. These should, he said, be the only variations accepted.
DEMOLITION ISSUE 15 : IF THE ANSWER TO ISSUE 4 ABOVE IS YES THEN WHAT WERE THE TERMS OF THE DIVISIBLE CONTRACT? 92. Mr Loewenstein argues that this issue does not arise in light of the submissions he made with respect issue 4. This is right, because both parties agree that the demolition work was part of the main contract. There was no divisible contract.
ISSUE 16: PLAINTIFF'S STATEMENT OF ISSUE: WHO IS CONTRACTUALLY LIABLE FOR DEMOLITION? DEFENDANT'S STATEMENT OF ISSUE. THE DEFENDANT DOES NOT AGREE THAT THIS IS AN ARISING ISSUE. 95. Mr Loewenstein relies on his submissions in relation to issues 2 and 4. He says that its "contractual responsibility was to undertake demolition work up to a cost of $65,000 after which any additional work undertaken would be the subject of adjustment or compensation." That appears in his written submissions at clause 16.1.
ISSUE 17: WHETHER THERE WAS A TERM OF THE CONTRACT THAT TRAMINER WOULD PERFORM DEMOLITION WORK UP TO A VALUE OF $65,000
Both parties agreed that a quotation from Traminer to Tilley's dated 27 August 2001, but sent by fax on 2 September 2001, was one of the contract documents. That document which made its appearance amongst the exhibits in a number of places, one of which was exhibit A3 at tab 12, contains the following entry which had been made by Mr Beecroft on behalf of Traminer before sending the quotation: "Note: $65,000 has been allowed for demo".
In addition Traminer asserts that there were various conversations between Mr Beecroft and Mr Remy Logel which supported its asserted terms of the contract.
The contractual significance of Mr Beecroft's note in the agreed contract document and the significance of the conversations between Mr Beecroft and Mr Logel were both controversial and the subject of submissions. I need to make findings in both of those areas.
Mr Loewenstein had submitted in relation to issue 2 at clause 2.12 of his written submissions of 13 November 2008 that it is apparent from the "context" in which Mr Beecroft's note appears that "although there has been an 'allowance' of $65,000 for demolition, the carrying out of demolition beyond that cost chargeable to Tilley by Traminer is not Traminer's obligation." In his submission regarding issue 17 at clause 17.1 Mr Loewenstein refers to his earlier submission, which he says "answers the question by submitting that Traminer had no obligation to carry out demolition work under the terms of the Contract for a fee that it would be entitled to charge amounting to more than $65,000."
Mr Bland responds with a series of arguments to the effect that Traminer cannot rely on Mr Beecroft's note in the way that it does. First he argues that there is no ambiguity about the terms of the note so that resort cannot be taken to any "context" in which the expression appears. Secondly, the terms of the note should be taken to mean what they say. They were not drafted by Mr Beecroft to constitute a contractual term but a statement of fact. Thirdly, in any event Mr Beecroft's intention is not relevant- "Identification of terms of the contract and their meaning involves a process of objective analysis and construction. It is not what the parties intended by the words, but rather what the terms or words mean on their face objectively." That appears in his written submissions at clause 137. Fourthly, he argues it should not be regarded as an isolated item which affects the lump sum contract price. Just because a sub-contractor, he argues, might provide a break up of the work at stages does not affect the overall lump sum price. Finally, he argues that Mr Beecroft's evidence of his conversation with Mr Logel about being compensated for any demolition work over $65,000 is inconsistent with his position that $65,000 was an overall limit.
Mr Loewenstein responds by arguing that Mr Beecroft's note "in the context in which it appears is capable of more than one meaning." He says that Mr Bland is relying on the parole evidence rule which, Mr Loewenstein says, is no longer as narrow as was formulated by the High Court in Codelfa Construction Pty Limited v State Rail Authority (NSW) (1982) 149 CLR 337.
106 I note in this regard from a recent decision of the Court of Appeal, to which both parties referred me - Franklins Pty Limited v Metcash Trading Limited [2009] NSWCA 407 - that it is clear that it is no longer necessary to find an ambiguity in the words of a written contract before the surrounding circumstances can be examined as an aid to construction.
Mr Loewenstein acknowledges that the note could mean that the $65,000 is "an allowance within the lump sum contract", but he also points to the fact that the note appears separately in the document from items listed as included in the price and from items listed not included in the price. It, therefore, does not readily lend itself to meaning an inclusion or allowance within in the lump sum price and is, indeed, somewhat ambiguous.
Mr Loewenstein argues at clause 73 of his submissions in reply that the meaning of the note "is unclear and entitles it to clarification by reference to the context in which that expression was used." As I have said, in my opinion I do not need an ambiguity before resorting to the context. However it does appear to me, if it were necessary so to find, that there is an ambiguity about the note in the document. One would expect to find it, if it was meant to be an inclusion in the lump sum price, under the listed items of inclusions, perhaps as part of item 7. Standing as it does by itself suggests that it might have formed some other meaning. I do not think that it could reasonably mean that the total price is to be increased by the $65,000 allowance of a demolition, but an objective reading of the document throws up a question at that point. It clearly does not intend to increase the lump sum price but nor does it appear under the inclusions so the objective reader in my opinion is left wondering what it means.
I do not accept Mr Bland's argument that the note "is not drafted in the form of the term". The note was not "drafted" by a lawyer but written by a contractor who, I accept, does not normally do demolition work. It would not surprise me, although I do not rely on this, if the quotation was sent off - as the fax form suggests - just before midnight. But this is a document prepared by a contractor not by a lawyer who is used to employing niceties of language and grammar. It is true that, as Mr Bland argues, the inclusion in a lump sum contract of an itemised break-up would not entitle the contractor to argue that there is no lump sum contract price. But in my opinion the lump sum contract price is not compromised as at the date of the document.
I accept Mr Loewenstein's submission that when his evidence is considered in its entirety Mr Beecroft did not suggest that he was taking responsibility for the entire demolition. I also accept that there was good reason for Mr Beecroft to request the demolition plans for the reasons set out in Mr Loewenstein's submissions in reply over clauses 78 - 79.
As Mr Loewenstein makes it clear the contract is only partly in writing. Part of the contract is oral and Traminer relies upon the conversations between Mr Beecroft and Mr Logel. It also argues that those conversations may be used to assist in the interpretation of the written component of the contract, including Mr Beecroft's note. The authorities regarding the interpretation of written contracts need to be read in light of the fact that in this case the contract is partly written and partly oral. Mr Bland reasonably points out "the representations allegedly made by Mr Logel and their timing required to be generally accepted by the court", before weight can be placed on Mr Loewenstein's submissions on that topic. But having considered and accepted that the representations were made by Remy Logel, which Mr Beecroft says were made, I conclude from those representations and the note on the quotation that the answer to this issue is, yes there was a term of the contract that Traminer would perform demolition work up to a value of $65,000.
ISSUE 18:THE PLAINTIFF'S STATEMENT OF ISSUE: WHETHER TRAMINER REPUDIATED AND/OR BREACHED THE CONTRACT BY FAILING OR REFUSING TO UNDERTAKE THE ENTIRE DEMOLITION. THE DEFENDANT'S STATEMENT OF ISSUE: THE EXTENT OF DEMOLITION WORK PERFORMED BY TRAMINER AND THE VALUE OF THAT WORK. 112. As Mr Bland argued this "question necessarily involves determination of the phrase 'note: $65,000 has been allowed for demo', as expressed in the defendant's quotation". Tilley's position is that Traminer knew that it was undertaking the refurbishment of existing occupied premises and gave its quotation which included allowance for the demolition in full knowledge of the risks associated with committing itself to such a task. Mr Beecroft, argues Mr Bland, was given a price to beat and made a commercial decision to better that price. Mr Auld recalled "Mr Beecroft was given a figure to meet." On the other hand, Mr Bland argues, "Mr Beecroft is adamant that nobody at Tilley's told them that the best price they had to meet was $860,000". Mr Bland argues that Traminer repudiated its contract with Tilley's "by indicating it was not prepared to any more demolition work". That appears at Mr Bland's written submissions at clause 18.6. He said this occurred "about September/October 2002", but had also been expressed by Traminer "in writing in its letter to the plaintiff dated 2 January 2002". That letter appears behind tab 37 to Mr Beecroft's affidavit which is exhibit 7. Indeed Mr Beecroft said on behalf of Traminer to Tilley in that letter that "Traminer Industries is not going to keep on paying out for demolition works as we did not 'this work'." Traminer in its submissions argues that quite clearly that letter "supports the contention always maintained by him that the defendant did not contract to carry out demolition works in excess of the amount of $65,000". That appears at clause 59 of Mr Loewenstein's submissions in reply. Mr Beecroft does not accept the terms of the conversation which allegedly occurred in September October 2002 wherein he is said to have repudiated the contract.
Of course if the contract was, as Mr Beecroft alleges, that he would be paid for demolition work in excess of $65,000 and this term of the agreement was not being met by Tilley's then it would be Tilley's who was in breach of the agreement and perhaps repudiating it. The real issue here, as Mr Bland says, is not so much which party repudiated the agreement but what the terms of the agreement were.
Mr Bland argues that in Traminer's letter of 2 January 2002 "Traminer does not take this opportunity during the works to state a central plank of its claim, ie 'that duct workers do not do demolition'." In my opinion that assertion is not correct. In that letter Mr Beecroft said about his company that "we are installers not demolishers." Mr Bland also says that there is "no mention of deals done earlier with Remy Logel yet this is the basis upon which Traminer's claim rests". But in his letter of 2 January 2002 Mr Beecroft said that at " the time of quoting I was advised by Remy that an amount of $64,000 was more than enough to cover this work. At this time I advised Remy that I did not want to do the demolition as we are installers not demolishers."
Mr Bland argues at clause 18.12 that there is a "serious lack of direct evidence and very little anecdotal evidence of the extent of demolition works performed by Traminer, at least to the extent that the value exceeded $65,000". Mr Bland examined clauses 258 - 278 of Mr Beecroft's affidavit which is exhibit 7. Mr Bland argues that in clause 258 Mr Beecroft "admits that he does not have written records to the demolition work carried out by Traminer". In my opinion that is not an accurate description of what Mr Beecroft said. What he said in that paragraph was that he did not have "detailed written records for some of the demolition work carried out by Traminer". Mr Bland also asserts that there are "no contemporaneous invoices, claims or demands for demolition works being undertaken by Traminer". Neither is that an accurate assertion. Behind tab 41 to Mr Beecroft's affidavit there is a copy of a letter dated 19 September 2002 which Traminer sent to Tilley's complaining about the amount of demolition work in excess of $65,000 and providing an estimate for total demolition work of $162,734 and a claim for that work.
Mr Bland argues that "Mr Beecroft's analysis of diary entries between para 259 and 278 offers some assistance to the Court, however there is insufficient evidence to make out the claim for $162,734.00 the demolition works." The assertions made by Mr Beecroft over clauses 258 - 273 of his affidavit about demolition work carried out in excess of $65,000 are supported by documents exhibited to his affidavit and contained in exhibit 7. It is true that the documents do not constitute invoices containing all the details which would be desirable in making out such a claim, but nor do I accept all of Tilley's criticisms of the documents. It is apparent to me that most of the documents contain a reference to the relevant project - TAB site - and to a relevant work -demolition. Mr Bland makes some points about cross-examination of Mr Summers, but I do not think that any of those points impact on the general reliability of the documents relied upon by Mr Beecroft to support his claim for demolition work.
I accept Mr Loewenstein's submissions at clause 24 that Mr Beecroft's affidavit sets out the demolition work carried out to the value of $65,000 and the demolition work carried out in excess of $65,000 and is "supported by the log books to which reference is made in the paragraphs and appearing behind tabs 38, 39 and 40" of Mr Beecroft's affidavit.
I accept on the balance of probabilities that Remy Logel, an authorised representative of Tilley's, said to Mr Beecroft that $65,000 would be allowed for demolition and in effect that Tilley's would compensate Traminer for any demolition work which exceeded that amount. I accept that for the following reasons.
First, and perhaps most importantly, Mr Beecroft has always maintained that position. As early as his letter dated 2 January, 2002 he asserted his position that $65,000 was allowed for demolition and had been reached and he therefore expected to be able to invoice for work in excess of that.
Secondly, the claimed assertion by Remy Logel is supported by Mr Auld. Not only that, but Mr Summers gives an account of hearing Cameron Howes say words which were consistent with the same position.
Thirdly, Tilley's did not call Remy Logel to deny that claimed assertion. Indeed, Tilley's was not in a position to challenge Mr Beecroft's evidence of what Mr Logel said, which therefore stood unchallenged and supported by Mr Auld and indirectly by Mr Summers.
Therefore in my opinion, Traminer is right in asserting that "once an allowance of $65,000 is made, there remains due and owing $97,934.00 plus GST totalling $107,507.40": see Mr Loewenstein's written submissions at clause 30.
As for Mr Bland's criticisms of Mr Beecroft's assessments for demolition work in excess of $65,000 I accept Mr Loewenstein's submissions that "the overwhelming evidence is that the work was carried out as asserted and as detailed in the extensive documentation provided." That appears at clause 62 of Mr Loewenstein's submissions in reply.
Over clauses 33 - 34 of his written submissions Mr Loewenstein challenges a claim made by Tilley's in respect of the demolition work which Tilley's said it had to arrange to be done by another contractor named Moylan because Traminer did not complete its agreement to do all the demolition work. Mr Loewenstein examines each of the Moylan invoices and descends into the same "minutiae" which he criticised Mr Bland for descending into with respect to Traminer's estimate of demolition work. Mr Loewenstein makes some valid points about some of the invoices which contain no description of work at all and, if I was wrong in my primary finding, I would be disinclined to allow those invoices.
In the event that I was wrong about my primary liability for the demolition work, the findings that I would make regarding the Moylan invoices briefly are these and they are based upon Mr Loewenstein's submissions about whether or not there was reference to any demolition work.
In respect of docket 410, I would allow nothing, so I would deduct sixteen by forty-one dollars fifty, $664.00. In respect of docket 430, I would allow half, so I would deduct seventy-two by forty-one dollars fifty and nine by fifty dollars fifty. I would divide that by two and deduct a total of $1,721.00. In respect of docket 434, I would allow nil and deduct thirty-four by forty-one dollars fifty, that is $1,411.00. In respect of docket 437, I would allow nil and so I would deduct thirty-six by forty-one dollars fifty, an amount of $1,494.00. In respect of docket 445, I would now allow nil and would deduct thirty-two by forty-one dollars fifty, namely $1,328.00. In respect of docket 450, I would allow half, so I would deduct forty-eight by forty-one dollars fifty. Four by fifty dollars fifty and ten by fifty-nine dollars fifty. I would divide that by two and deduct $1,395.00. In respect of docket 460, I would allow half and deduct half of thirty-two by forty-one dollars, namely $664.00. In respect of docket 486, I would allow half and so I would deduct half of thirty-two by forty-one dollars fifty, namely $664.00. In respect of docket 487, I would allow nil, so I would deduct forty-eight by forty-one dollars fifty. Four by fifty dollars fifty and twelve by fifty-nine dollars fifty: respectively amounts of $1,992.00, $202.00 and $714.00. In respect of docket 494, I would allow half and therefore deduct half of twenty-four by forty-one dollars fifty, namely $498.00. In respect of docket 495, I would allow half and so I would deduct half of sixty-four by forty-one dollars fifty. Four by fifty dollars fifty. Twelve by fifty-nine dollars fifty, namely $1,786.00. In respect of docket 496, I would allow half and therefore deduct half of thirty-five by forty-one dollars fifty, $726.00. In respect of docket 498, I would allow nil and therefore deduct sixteen by forty-one dollars fifty, namely $664.00. I would, if need be, deduct a total of $15,923.00.
ISSUE 19 : PLAINTIFF'S STATEMENT OF ISSUE: THE QUANTUM OF DAMAGES SUFFERED BY TILLEY OR TRAMINER BY REASON OF HAVING TO COMPLETE OR CONTINUE THE DEMOLITION. DEFENDANT'S STATEMENT OF ISSUE: DEFENDANT MAINTAINS THAT THIS IS ENCOMPASSED IN ITEM 13 ABOVE. 127. Mr Bland refers to his submissions on other issues (see clause 19.1) and Mr Loewenstein addresses this issue in his submissions over clauses 22 - 62.
ISSUE 20: WHETHER TRAMINER INDUSTRIES ARE ABLE TO SUCCEED ON A CLAIM UNDER THE TRADE PRACTICES ACT BASED ON ALLEGED REPRESENTATIONS AS TO THE AMOUNT OF DEMOLITION WORK, INCLUDING: A. WHETHER THERE WERE REPRESENTATIONS B. WERE THE REPRESENTATIONS DELIBERATE OR RECKLESS, (INSERTED AT PLAINTIFF'S REQUEST; THE DEFENDANT DISAGREES THAT THIS IS PROPERLY AN ISSUE) C. WAS TRAMINER ABLE TO SEEK CLARIFICATION OR FURTHER INFORMATION? (INSERTED AT PLAINTIFFS REQUEST; THE DEFENDANT DISAGREES THAT THIS IS PROPERLY AN ISSUE) D. WHETHER THERE WAS RELIANCE UPON THOSE REPRESENTATIONS. E. IF D IS FOUND IN THE AFFIRMATIVE WAS THE RELIANCE REASONABLE IN THE CIRCUMSTANCES? F. WHETHER REMY LOGEL HAD ACTUAL OR OSTENSIBLE AUTHORITY TO MAKE THE REPRESENTATIONS ALLEGED BY TRAMINER G. WHETHER TILLEY KNEW OR OUGHT TO HAVE KNOWN THE REPRESENTATIONS WERE FALSE H. WHETHER THE REPRESENTATIONS WERE NEGLIGENT. I. DOES THE DOCTRINE ERRONEOUS ASSUMPTION APPLY? J. DOES S 52 APPLY TO PRIVATE NEGOTIATIONS? DEFENDANT'S STATEMENT OF ISSUE: WHETHER TRAMINER INDUSTRIES ARE ENTITLED TO SUCCEED ON THE CLAIM UNDER THE TRADE PRACTICES ACT AS PLEADED IN ITS CROSS-CLAIM. 128 In its cross-claim Traminer claims that certain representations were made by Tilley's to Traminer before the commencement of the contract work, as well as after entry into the contract. Traminer alleged that the representations were made by Tilley's, a corporation, in trade or commerce and were misleading and deceptive or likely to mislead and deceive. If these allegations are made out then it would follow that Tilley's had breached s 52 of the Trade Practices Act and thus be exposed to the relief provisions of that Act. Traminer claims that some of the representations were made with respect to a future matter and without reasonable grounds would therefore be "taken to be misleading" by s 51A of the Trade Practices Act.
129 Traminer set out in clause 15 of its cross-claim representations it claims Tilley made before the contract work commenced. They are as follows - "(a) Tilley wished to enter into a contract with Traminer whereby Traminer would agree to perform the contract work; (b) Tilley would submit to Traminer a tender for the contract work and allow in that tender an amount of $65,000 plus GST for the demolition work; (c) The demolition work was capable of being completed by Traminer at a cost of no more than $65,000 plus GST in time and materials; (d) The demolition work would cost Traminer no more than $65,000 plus GST in time and materials to complete; (e) Traminer did not require demolition drawings in order to accurately assess the scope and cost of, or accurately tender for, the contract work or to perform the demolition work; and (f) Traminer would receive instructions from Tilley or its agents in relation to the demolition work required to be performed by Traminer at the TAB site ." It is the representation in (d) which Traminer says was with respect to a future matter.
(b) During the period January 2002 to May 2002 that (1) in the event the value of the demolition work performed by Traminer did exceed $65,000 (plus GST) Tilley: (A) would pay Traminer for the full value of the work performed; and/or (B) would otherwise ensure that Traminer was fully compensated for the Demolition Work by: (1) reducing the scope of the Contract Work comprising the Installation Work; and (2) if, after the offset in (B)(1) above the value of the Demolition Work still exceeded $65,000 (plus GST), Tilley would pay to Traminer such amount as was necessary to compensate Traminer for the full value of the work."
It is representation cl (a)(2) which Traminer says was with respect to a future matter.
(b) the cost to Traminer in time and materials of performing the Demolition Work greatly exceeded $65,000 plus GST; and
(c) without the demolition drawings Traminer could not accurately assess the scope, or cost, of the Demolition Work, or accurately tender for the Contract Work." I have not included particulars.
(b) otherwise ensure that Traminer was fully compensated for the Demolition Work by:
(1) reducing the scope of the Installation Work; and/or (2) otherwise paying to Traminer such amount as was necessary to compensate Traminer for the full value of the Demolition Work ." 134. The question for me must be whether I am satisfied on the balance of probabilities that Traminer has made out these various allegations.
The conduct Traminer relies on comprises assertions which it says were made by Remy Logel on behalf of Tilley's. Those assertions are contained in Mr Beecroft's affidavit, exhibit 7, at clauses 23, 25, 27, 29, 32 and 256. I do not propose to set those out in the judgment. Traminer also relies on an account given by Mr Auld of one of those assertions by Remy Logel. It is contained at clause 9 of Mr Auld's affidavit which is exhibit 10.
Traminer says the assertions of Remy Logel are also supported by Mr Summers who gave an account of a conversation he overheard between Mr Beecroft and Cameron Howes. Mr Summers said Cameron Howes made an assertion which was consistent with what Traminer says Remy Logel had said. That appears in Mr Summers' affidavit which is exhibit 11 at clause 27.
For reasons I have given, I accept Darren Beecroft's account of what he claims Remy Logel said to him on various occasions. So the question now becomes whether I have been satisfied on the balance of probabilities by Traminer that the conduct of Remy Logel comprised by his assertions amounted to conduct which was misleading or deceptive or likely to mislead and deceive and so was in breach of s 52 of the Trade Practices Act.
Prima facie, it seems to me, Traminer has made out misleading or deceptive conduct on the part of Tilley in respect of two topics.
The first is that the demolition work was "capable of being completed by Traminer at a cost of not more than $65,000 plus GST in time and materials" and the associated future representation that this demolition work "would cost Traminer no more than $65,000 plus GST in time and materials to complete."
The second topic is that, in the event that the value of the demolition work did exceed $65,000, then Tilley would either pay Traminer the full value of work performed or would otherwise ensure that Traminer was fully compensated for all demolition work.
I make those prima facie findings based on the fact that I accept Mr Beecroft's account that the demolition work far exceeded $65,000 and his account of his conversations with Remy Logel in which Remy Logel said that "they would sort it out on the job." The meaning of that expression was made clear in my opinion by Remy Logel around 30 January 2002 when he said to Mr Beecroft, after Mr Beecroft had sent his letter of 2 January 2002, that Tilley's would "delete some ductwork throughout the project to cover some of the costs of the extra demolition and then will fix up the difference later in the job."
In the context it was clear, in my opinion, that Remy Logel was asserting, as Traminer claims in clause 18(b) of its cross claim, that Tilley would "ensure that Traminer was fully compensated" for the demolition work.
Tilley meets Traminer's claim of misleading or deceptive conduct by arguing a series of issues which, it says, point to no misleading or deceptive conduct on its part.
Mr Bland first raises a question of whether there were any representations. He points to Mr Tilley's account of conversations and urges me to see the Remy Logel conversations in that context. The difficulty with that is that Mr Beecroft says there were also conversations just with Mr Logel, representing Tilley, at which Mr Tilley was not present. I accept Mr Beecroft's uncontradicted evidence to this effect. I do not regard as significant whether or not Mr Beecroft was told the figure of $860,000.
What I do regard as significant are the terms of his conversations with Remy Logel about the demolition work.
I do not regard as persuasive Mr Bland's submission in clause 20.10 urging me to "exercise caution in invoking the provisions such as s 52 based on oral discussions leading to a formal agreement." Both parties plead a contract that comprises both written and oral components. This is not a case where there were pre-contract discussions culminating in a formal document. Conversations are relied on by both parties as containing terms of the contract.
Mr Bland argues that what Remy Logel is alleged to have said about "$64,000 is more than enough" - the first topic I referred to earlier - is an expression of opinion which had a sound foundation, namely the Insultec quotation. He relies upon what the Full Court of the Federal Court said in Global Sportsman Pty Limited v The Mirror Newspapers Pty Limited (1984) 2 FCR 82 at 88 as follows: " The non-fulfilment of a promise when the time for performance arrives does not of itself establish that the promisor did not intend to perform it when it was made or that the promisor's intention lacked any, or any adequate, foundation. Similarly, that a prediction proves inaccurate does not of itself establish that the maker of the prediction did not believe that it would eventuate or that the belief lacked any, or any adequate foundation. Likewise, the incorrectness of an opinion (assuming that can be established) does not of itself establish that the opinion was not held by the person who expressed it or that it lacked any, or any adequate, foundation.
The applicants argued that, nevertheless, the statement of an incorrect opinion is misleading or deceptive or likely to mislead or deceive merely because it misinforms or is likely to misinform. An expression of opinion which is identifiable as such conveys no more than that the opinion expressed is held and perhaps that there is a basis for the opinion. At least if those conditions are met, an expression of opinion, however erroneous, misrepresents nothing." 148. I think there is force in this argument and I accept it. Mr Remy Logel, on behalf of Tilley, had the quotation from Insultec but not the workings and he was, in my view, expressing an opinion about the cost of that demolition work. The opinion was based on that quotation. I am therefore not satisfied that any of the representations pleaded in clauses 15 or cl 18(a) of the cross claim are misleading or deceptive under s 52, including by virtue of s 51A of the Trade Practices Act.
Mr Bland raises as an issue the question of whether any representations were deliberate or reckless but develops a similar argument about expressions of opinion about $64,000, and I have already determined that issue.
Mr Bland argues that Mr Beecroft was able to seek clarification or further information. He argues that Traminer chose "to accept that $65,000 was sufficient for demolition in circumstances where they could have sought quotes from specialist demolition contractors, and arrived at a commercial decision to either tender or not." Mr Bland said that Traminer "still accepted to do the demolition work at the $65,000." He goes on to argue that Traminer "had two options, those being, simply not to submit a quote for the works, or price in a margin to cover the fact that Traminer could only roughly estimate the cost of the demolition works."
In my opinion Traminer had at least one other option and it took this other option. It accepted the work but specified in its quotation that the demolition work was $65,000. Traminer did not accept that $65,000 was sufficient. It submitted a quotation that acknowledged as much. I do not accept Mr Bland's argument to this effect.
Mr Bland argues that Traminer did not rely on the representations and if it did then that reliance was not reasonable. Mr Bland said that Traminer had reservations about the $65,000. This is clearly admitted by Mr Beecroft and Mr Bland argues that Traminer should have "made reasonable independent enquiries and calculations as to the cost of demolition works by further considering and calculating the cost of demolition in the light of its own doubts as to the truthfulness of the representation."
I think it is clear that Mr Beecroft, on behalf of Traminer, did rely on Mr Logel's representations made on behalf of Tilley's. That is obvious from Mr Beecroft's account of his conversations with Mr Logel. He could not see the demolition drawings or the Insultec quotation but he nevertheless proceeded "because we have always worked with Tilley's in the past."
He said in cross-examination at T 568 that if he had been given the Insultec quotation, he would have "rung the other company and found out what they had allowed for and how they - how they established their quote." Remy Logel reassured him not "to worry about it."
It is clear to me that, although Traminer was an independent contractor striking a bargain with another contractor, it was within the context of a longstanding and good working relationship. Traminer was encouraged not to concern itself with its reservations and entered the contract relying, to a significant extent, on that relationship. That reliance is further demonstrated, as Mr Loewenstein argues clause 51, by the fact that Traminer proceeded with the work. It can also be seen in the correspondence.
In my opinion Traminer has established that Traminer relied on Tilley's representations. That reliance was reasonable in the circumstances which included the history of a good working relationship.
Mr Bland argues that there was no evidence of a credible nature that Remy Logel was in a position of authority. I do not accept that argument. Mr Beecroft gave an uncontradicted account of discussions of Remy Logel who asked him to quote for the job, then negotiated with him over components of the quotation, then informed him that Traminer had won the contract. I regard Mr Beecroft's account of his conversations with Remy Logel as evidence that Remy Logel had authority to speak for Tilley so far as the claims he made to Mr Beecroft on behalf of Traminer. Also, as Mr Loewenstein points out at clause 52, exhibit A3 tab 14 is consistent with the representation of Mr Logel to Mr Beecroft.
Mr Bland relies on his earlier submissions on the question of whether the representations were false or negligent, but that is not in any event relied upon by Mr Loewenstein.
Mr Bland argues that Remy Logel's representations were admitted not to prove what was asserted but only to prove the fact that they were asserted. This was the subject of my interlocutory judgment on 30 April 2008. It is sufficient, of course, for Traminer to prove the fact that they were asserted. Traminer does not rely on the truth of the assertions. In fact, Traminer says they were misleading and deceptive.
Mr Bland argues that if Traminer makes out its claim under the Trade Practices Act it cannot prove a loss, because Tilley would not have offered Traminer the contract for more than $860,000. But that argument depends upon whether Tilley breached s 52 by making the other representations that Traminer relies on.
Mr Bland argues that Traminer asserts in its cross claim that the conversations were that the demolition would cost Traminer no more than $65,000, but in its submissions Traminer says that the representation was that "$65,000 is more than enough." Mr Bland argues that a representation that the works would "cost no more than $65,000" is inconsistent with a representation to the effect "if you do more we will take other work off to reduce your costs." There is some force in that as a matter of logic but the negotiations proceeded as they did. The original assertion was doubted by Mr Beecroft so Remy Logel made the assertion that they would work it out.
As to the second topic of claimed misleading and deceptive conduct - that is compensation for demolition work above $65,000 - none of Mr Bland's arguments which I have just recited meets Traminer's claim in my opinion. In reasonable reliance on Remy Logel's assurances on behalf of Tilley that Traminer's demolition work above $64,000 would be "sorted out on the job", it was not and Traminer found itself entering into correspondence, then litigation with Tilley in order to secure fair compensation for the extra work it undertook. In my opinion Traminer has made out a breach of s 52 of the Trade Practices Act by Tilley.
ISSUES 21 TO 22 "ISSUE 21: THE APPLICABLE RATE FOR DUCTWORK DELETED FROM THE SCOPE OF WORKS, TAKING INTO CONSIDERATION, BUT NOT LIMITED TO:
(A) WHETHER THE DELETED DUCTWORK WAS TO BE INSULATED OR NOT INSULATED;
(B) THE PLAINTIFF'S STATEMENT OF ISSUE: THE LOCATION DIFFICULTY AND COMPLEXITY OF DELETED DUCTWORK. THE DEFENDANT'S POSITION: THIS IS NOT AN ISSUE WITH RESPECT TO THE DELETED DUCTWORK, IT IS AN ISSUE WITH RESPECT TO TRAMINER'S CLAIM FOR ADDITIONAL WORK PERFORMED THAT WAS NOT PART OF THE ORIGINAL SCOPE OF WORKS AND AS CLAIMED IN IT'S CROSS CLAIM." 163. The applicable rate for ductwork deleted from the scope of works is indirectly provided for by the contract. Both Tilley and Traminer agree that it was a term of the contract in terms of clause 7 of the amended statement of claim that "if any works were omitted and/or varied from the contract, then the amount due to the defendant would be adjusted by the value of the works omitted."
ISSUES 23 AND 24 ISSUE 23: PLAINTIFF'S STATEMENT OF ISSUE: THE AMOUNT OF DUCTWORK DELETED FROM THE SCOPE OF WORK. DEFENDANT'S STATEMENT OF ISSUE: THE DEFENDANT UNDERSTANDS THAT THE EXPERTS (MR STURGESS FOR THE PLAINTIFF AND MR MARIC FOR THE DEFENDANT) HAVE AGREED THAT THE AMOUNT OF DELETED DUCTWORK FROM THE SCOPE OF WORK IS $1,153 SQUARE METRES. THE DEFENDANT'S STATEMENT OF ISSUES: WHETHER THE VALUATION OF THE DUCTWORK SHOULD BE AT THE RATE PROVIDED BY TRAMINER IN ITS QUOTATION AND THAT WAS THE SUBJECT OF AGREEMENT BY TILLEY, OR WHETHER THE VALUE OF THE DUCTWORK SHOULD BE THE AMOUNT CHARGED BY TILLEY TO TRAMINER OR SOME OTHER RATE. ISSUE 24 PLAINTIFF'S STATEMENT OF ISSUE: THE VALUE OF THE DUCTWORK DELETED FROM THE SCOPE OF WORK. DEFENDANT'S STATEMENT OF ISSUE: WHETHER THE VALUATION OF THE DUCTWORK SHOULD BE AT THE RATE PROVIDED BY TRAMINER IN ITS QUOTATION AND THAT WAS THE SUBJECT OF AGREEMENT BY TILLEY, OR WHETHER THE VALUE OF THE DUCTWORK SHOULD BE THE AMOUNT CHARGED BY TILLEY TO TRAMINER OR SOME OTHER RATE. 166. As to issue 23, Traminer accepts in its statement of issue that "the experts...have agreed that the amount of deleted duct from the scope of work is 1,153 square metres."
OTHER DUCTWORK DELETED FROM THE SCOPE OF WORKS AND AGREED BETWEEN THE PARTIES ISSUE 25: THE PLAINTIFF'S STATEMENT OF ISSUE: IT APPEARS THAT THE PARTIES AGREE THAT ON 13 SEPTEMBER 2002 THE AMOUNTS OF $7,740 AND $8,600 WERE DELETED FROM THE BASIC SCOPE OF WORKS. DEFENDANT'S STATEMENT OF ISSUE: THE DEFENDANT ASSERTS THAT THE PLAINTIFF MISSTATES THE DEFENDANT'S POSITION WITH RESPECT OF ITEMS 5 AND 6 AS CONTAINED ON THE AMENDED SCHEDULE A TO THE AMENDED STATEMENT OF CLAIM, THE DEFENDANT STATES:- "(I) SEE PARA 68 TO 74 OF THE AFFIDAVIT OF DARREN BEECROFT (AND TAB 10 TO MR BEECROFT'S AFFIDAVIT)
(II) AS TO ITEM 5 ON THE AMENDED SCHEDULE A TO THE AMENDED STATEMENT OF CLAIM:
(A) A VARIATION CLAIM WAS MADE BY TRAMINER INDUSTRIES WITH RESPECT TO TIME LOST DUE TO CLOSURE OF THE SITE FOR ONE DAY AND ATTENDANCE UPON MEDICAL EXAMINATIONS FOR ONE DAY (TOTAL TWO DAYS) AND FOR WHICH A VARIATION CLAIM WAS MADE BY TRAMINER IN THE TOTAL AMOUNT OF $8,514. TILLEY DECLINED TO PAY THE INVOICE. TRAMINER AGREED NOT TO PRESS THE CLAIM AND THEREFORE ISSUED A CREDIT NOTE IN THE SAME AMOUNT OF $8,514 IN ORDER TO ASSIST TILLEY IN "BALANCING ITS BOOKS" (SEE PARA 72 OF MR BEECROFT'S AFFIDAVIT).
(III) THE AMOUNT OF $8,600 DOES NOT ARISE FROM ANY DELETION IN THE BASE SCOPE OF WORKS BUT ARISES FROM A CLAIM MADE BY TRAMINER FOR A VARIATION AS A CONSEQUENCE OF ASBESTOS CONTAMINATION (SEE PARAS 51 TO 58 OF MR BEECROFT'S AFFIDAVIT). UNDER TAB 7 OF MR BEECROFT'S AFFIDAVIT WILL BE FOUND A TAX INVOICE THAT CONSTITUTED A VARIATION CLAIM MADE FOR TIME LOST IN THE AMOUNT OF $23,760 INCLUSIVE OF GST. TILLEY REFUSED TO PAY A CLAIM OF $9,460 OF THAT AMOUNT. CONSEQUENTLY AND THEREFORE A CREDIT NOTE OF THAT AMOUNT WAS ISSUED TO TILLEY. 168. It is agreed that two items were deleted from the base scope of works: that is apparent from the statement of issues I have just referred to. Tilley originally claimed for these items but no longer does so (see items 5 and 6 in the further amended schedule A to the amended statement of claim).
ISSUE 27 - UNJUST ENRICHMENT : WHETHER TRAMINER INDUSTRIES WERE UNJUSTLY ENRICHED BY RECEIPT OF PAYMENTS FOR WORKS OMITTED FROM THE CONTRACT. 169. Tilley says it is difficult to see how the issue can arise in light of Traminer's admissions regarding the variation in terms of contract. Traminer argues regard must be had to the contract where one exists in considering any claim for restitution. It refers to Lumbers v W Cook Builders Pty Ltd (in liq) (2008) 232 CLR 635. Then Mr Loewenstein says at clause 74 of his written submissions that it is "essential to revisit the issue of what constituted the contract between the parties or alternatively in so far as the Plaintiff's claim against the Defendant is concerned, how the Plaintiff has pleaded the nature of its contract with the Defendant." But Mr Loewenstein revisits the question of his admissions at clauses 7 and 8 of the amended statement of claim over clauses 75 - 107. I have rejected those arguments. Mr Loewenstein submits that given the existence of a valid contract "there is no room for operation of any principle of unjust enrichment". I agree.
ISSUE 26 : WHETHER TRAMINER IS LIABLE TO PAY ADDITIONAL LABOUR COSTS IN ACCORDANCE WITH TILLEY INVOICE 020507. DEFENDANT'S POSITION: TRAMINER CONCEDES ITS ENTITLEMENT TO ITEM 7 IN THE AMENDED SCHEDULE A TO THE AMENDED STATEMENT OF CLAIM. 170. Traminer concedes that it is liable to pay the amount the subject of this issue which, is apparent from the statement of issue which I have just set out.
ISSUE 28: DEFENDANT'S STATEMENT OF ISSUE: WHETHER TRAMINER IS ENTITLED TO THE VARIATION SET OUT IN ITS SCHEDULE TO CROSS-CLAIM AT ITEMS 7, 10 TO 22 INCLUSIVE OR TO WHAT EXTENT THEY ARE ENTITLED TO SOME OR ALL OF THE VARIATIONS CLAIMED. 171. Mr Loewenstein dealt with these issues in detail by reference to the evidence primarily of Mr Beecroft. I will also refer to the paragraphs of his written submissions. I will also refer to the paragraphs of Mr Beecroft's affidavit.
Item 10. 172. Clauses 82 - 85 demonstrate a clear document trail. Mr Beecroft makes it plain that the "invoice was not paid". The invoice number was 281. Traminer's records show that it was unpaid. In Mr Howes' affidavit, exhibit B2, clause 9 refers to a letter of 19 June 2003 and in exhibit B1 at CH7 shows that that invoice 281 was paid $800 by cheque dated 5 April 2002. That cannot be right. The cheque pre-dates the order of 4 February 2003 and invoice 281 dated 13 February 2003. I accept Mr Loewenstein's submission.
Item 11 173. Clauses 87 - 90 of Mr Beecroft's affidavit provide for a clear document trail and assertion that the invoice was not paid. The invoice is dated 13 February 2003 and numbered 282. Traminer's records show that it was unpaid. Mr Howes says at clause 9 that the order was sent (at CH7) but not paid. There is no denial of Mr Beecroft's assertion about the work being done but unpaid. I accept Mr Loewenstein's submission regarding this topic.
Item 12 174. Clauses 92 - 95 of Mr Beecroft's affidavit provide a clear document trail. The work was done. Invoice 283 is said to be "not paid". In exhibit B1 there is no reference to invoice 283 or description of its content. There is no denial of Mr Beecroft's assertion regarding the work done and unpaid. I accept Mr Loewenstein's submission.
Item 13 175. There is a clear document trail. In clauses 97 -102 of Mr Beecroft's affidavit the work was done. He asserts that invoices 293 and 320 were "not paid". Exhibit B1 shows two payments each of $40,000 each regarding invoice 293 but each pre-dates the order and the invoices of 6 June 2002 and 28 June 2002. But it also shows $16,445 unpaid regarding order number 3502. There is no denial that the work was done. The record of payment pre-dates the order and is also inconsistent. I accept Mr Loewenstein's submission regarding this.
Item 14 176. This concerns the demolition work above $65,000 and I have dealt with that.
Item 17 179. This is dealt with by Mr Beecroft over clauses 141 -154 of his affidavit. The item concerns what Mr Beecroft describes at item 143 as "a problem attempting to install ductwork in certain areas of level 3 in stage 13. Cable trays and structural beams not shown on the original tender drawings, or the Stage 13 Construction Drawings, meant that the ductwork had to be modified on site to fit around them." After a meeting with Mr Howes which Mr Howes does not deny in exhibit B2, Traminer proceeded with work to fix the problem that is referred to in clause 146 of Mr Beecroft's affidavit. Traminer sent a fax to Tilley dated 11 October 2002 which appears at tab 18 regarding extras including an amount of $6,418 for that work. It was also itemised in a fax from Traminer to Tilley dated 5 May 2003 which appears at tab 19. In a meeting with Mr Howes on 18 June 2003, Mr Beecroft made notes on a copy of that fax and there is a note "Okay" next to this item. The day after the meeting Mr Beecroft sent another fax to Traminer dated 19 June 2003, noting an agreement that this item of $6,418 was amongst those left to pay (tab 35 p 1). Tilley's response was a fax of 19 June 2003 (tab 35 p 2) but then some weeks later, according to Mr Beecroft, Mr Howes handed Mr Beecroft a letter dated 19 June 2003 (tab 35 pp 3 to 6). That letter appeared to acknowledge that this item was unpaid and should be counted as a credit to Traminer although denying that, after an overall reckoning, Tilley owed anything to Traminer. It seems to me that Tilley has acknowledged its indebtedness to Traminer for this item and I find in favour of Traminer.
Item 18 180. This is dealt with by Mr Beecroft over clauses 155 to 173 of his affidavit. The problem is described at clause 157 where he said that when, after commencing work in the plant room, stage 13, he "discovered that the penetrations in the concrete slab made by the builder (the hole through which the ductwork was to pass), were different to those shown in the Stage 13 Construction Drawings. They were different both in the size of the penetrations and their location. This meant that the previously manufactured ductwork did not align with the penetrations, or fit through the penetrations. This meant that the previously ordered ductwork could not be used at all, because it had been made to measure specifically in accordance with Stage 13 Construction Drawings." Mr Beecroft related a conversation at clause 158 with Mr Howes which is not denied by Mr Howes. Additional ductwork was ordered from SydFab, supplied and paid for by Traminer. Mr Beecroft says at clause 162 that Mr Howes asked him for "a square metre calculation showing the cost of the extra ductwork you had to supply and install for the stage 13 plant room" which Mr Beecroft supplied by fax. That appears at tab 20 on p 13. Mr Beecroft was asked to invoice at a reduced rate which produced an amount of $7,733 or $8,506 including GST. The item was referred to in a fax of 5 May 2003 but at another rate. That appears in tab 19 p 1. It then seems to have disappeared from the correspondence. I am not satisfied on the balance of probabilities that this is made out and I find for Tilley regarding item 18.
Items 19 and 20 181. I will deal with these two together and they are dealt with by Mr Beecroft over clauses 175 - 213 of his affidavit. Certain work was done on the project which Traminer claimed as extras. They were contained in faxes sent by Traminer to Tilley dated 19 October 2002 (tab 22 p 1) and 28 November 2002 (tab 23 pp 1 to 2). The relevant items in the 29 October 2002 fax are numbers 3 to 8 and 12.
Item 21 185. This is dealt with by Mr Beecroft at clause 214 - 224. There was a fax dated 10 February 2003 from Traminer to Tilley regarding variations in the sum of $9,468.60 for the period October 2002 to February 2003 (see tab 29 pp 1 to 2). That is well documented by Mr Beecroft over clauses 215 - 216. The work was done as he said in clause 220.
Item 22 187. This is the final variation, which is referred to by Mr Beecroft in exhibit 7 over clauses 225 - 230. There is a fax dated 6 June 2003 from Traminer to Tilley regarding variations regarding the final stages (see clause 225 at tab 32 pp 1 to 2). The claim is for $12,538. It is well documented as clause 228 shows. The work was done. It does not appear in the fax of 5 may 2003. There was the meeting between Mr Beecroft and Mr Howes on 18 June 2003 at which Mr Howes agreed to pay $5,491.00. Mr Beecroft noted it in the fax on p 2. This work was all documented and there is no specific denial. I find in favour of Traminer so far as that claim is concerned.
PLAINTIFF'S MISLEADING AND DECEPTIVE CONDUCT ISSUE 29:WHETHER TILLEY COMMITTED MISLEADING AND DECEPTIVE CONDUCT AS ALLEGED IN PARA 15 TO 18 OF THE AMENDED FIRST CROSS-CLAIM. 188. Both parties developed no submissions in relation to this issue but refer to their submissions regarding issue 20.
TRAMINER'S ENTITLEMENT TO RELIEF ISSUE 30:WHETHER TRAMINER IS ENTITLED TO DAMAGES AS CLAIMED IN PARA 23 OF THE AMENDED FIRST CROSS-CLAIM IN THE AMOUNT OF $317,187.68. 189. Both parties refer to other submissions.
ISSUE 31:WHETHER TILLEY ENGAGED IN UNCONSCIONABLE CONDUCT AS PLEADED IN PARA 24 OF THE AMENDED FIRST CROSS-CLAIM. 190. Mr Bland address this pleading at clause 31.1 but Mr Loewenstein conceded at clause 168 that there is "no room for consideration of the principles of unconscionable conduct" so this issue no longer needs to be determined.
ISSUE 32: WHETHER TILLEY WAS UNJUSTLY ENRICHED AS ASSERTED IN PARA 26 OF THE AMENDED FIRST CROSS-CLAIM. 191. Mr Bland says this issue was dealt with in his submissions in relation to issue 28. Mr Loewenstein concedes at clause 169 of his written submissions that "there remains no scope for a claim based upon unjust enrichment given the existence of a contract between the parties defining the parties' obligations". I agree with that submission and it means that this issue no longer needs to be determined.
ISSUE 33:THE DAMAGES AND RELIEF WHICH TRAMINER IS ENTITLED AS CLAIMED AT PARAS (A)-(H) OF THE AMENDED FIRST CROSS-CLAIM. 192. Mr Loewenstein says that the claims in clauses (a)-(c) have been addressed elsewhere and that claims (e)-(h) should await the outcome of the proceedings.
CREDIBILITY AND WEIGHT ISSUE 34: (A) CREDIBILITY ISSUES GENERALLY (B) THE WEIGHT TO BE PLACED ON THE EVIDENCE OF THE PARTIES AND THE EXPERTS' REPORTS 203. Mr Bland points to various passages extracted from Mr Beecroft's evidence to support the proposition that I should not rely upon him as a credible witness.
PAYMENTS AND CLAIM RECONCILIATION ISSUE 35:THE AMOUNT PAID BY TILLEY AIR CONDITIONING TO TRAMINER INDUSTRIES IN RESPECT TO THE WORKS UNDERTAKEN BY TRAMINER INDUSTRIES, CLAIM RECONCILIATION SUMMARY. 208. I will determine this issue next when I come to enter verdicts and judgment.
CONCLUSIONS AND VERDICTS 209. Traminer was not in breach of the contract because it was not prepared to do more demolition work. Traminer should not be liable for any demolition work undertaken by another contractor. Traminer went into the contract on the basis that it would be compensated for any demolition work it undertook which exceeded $65,000. The extent of the demolition work was always far from clear. Traminer was asking to be paid for demolition work it had undertaken which exceeded $65,000 and payment was not forthcoming. It should not be liable to pay for demolition work which Tilley sent to another contractor.
A good amount of ductwork was deleted from the contract. That amount is agreed at 1,153 square metres. I have found that an appropriate rate is $103.56. I accept that the deleted ductwork amounted to a variation of the contract works and that Traminer should not be paid for that work not undertaken.
Traminer has conceded that it is liable for certain adjusted labour costs at an agreed figure.
The quantum of Tilley's claims were set out in a schedule to the statement of claim. The schedule went through various amendments and the latest is dated 25 January 2010 and entitled "Further Amended Schedule A to Amended Statement of Claim". As a result of the findings I have made, and by reference to that schedule, I would not allow item 1 for temporary ductwork. Nor would I allow item 3 for the cost to complete demolition works by another contractor. I would allow item 4 for deleted ductwork in full in the sum of $131,345.15. I would also allow item 7 for adjusted labour costs in the full amount of $37,393.
Accordingly on the statement of claim I would enter a verdict of for the plaintiff in the sum of $168,738.15.
In its cross-claim, Traminer claims $317,187.68 damages for breach of contract. There are two components to the claim.
The first is an amount of $95,260 which Traminer says it is owed by Tilley for unpaid invoices. There are four invoices which Traminer says remain unpaid and they are referred to in clause 8 of the cross-claim and by Mr Beecroft in clause 280 of his affidavit, exhibit 7. Tilley denies its liability for those alleged unpaid invoices and requires strict proof. In respect of one invoice Tilley says it has paid it in full. I have examined the evidence supporting Traminer's claim regarding the unpaid invoices. Mr Beecroft asserts that invoices 318 and 292 remain unpaid and that assertion is supported by his accounting records behind tab 42 of DJB1. I would regard those two invoices as unpaid on that invoice. Invoice 312 is asserted by Mr Beecroft to be unpaid but I cannot find a reference to it in his accounting records. I would not find that invoice unpaid. Invoice 268 is the one which Tilley says it has paid in full. Mr Beecroft says that it is outstanding to the extent of some $20,260, however, the accounting records show that only $8,000 is outstanding and there is also a reference to another invoice 268 which is paid in full. I am not satisfied that that invoice is unpaid. Of the $95,260.00 Traminer says is outstanding for unpaid invoices, I am satisfied that the amount of $52,800 is outstanding.
The second component of Traminer's claim for damages for breach of contract is an amount of $221,927.68 which it says it has not been paid for variation work. I have found that with one exception, all of the variation work was undertaken by Traminer and should be paid for by Tilley. The one exception is item 18 on Traminer's schedule to the cross-claim in the sum of $8,506.30. Of the $221,927.68 Traminer says is outstanding for unpaid variation work I am therefore satisfied that the amount of $213,421.38 is outstanding. In addition, I would award Traminer damages of the same amount under s 87 of the Trade Practices Act for the breach of s 52 of that Act.
Accordingly, when that amount of damages for breach of contract and damages under the Trade Practices Act is added to the outstanding amount for unpaid invoices, I would award damages in the sum of $266,221.38 and on the cross-claim I would enter a verdict for the defendant in that amount.
JUDGMENT 218. I would set off the amount owed to the defendant by the plaintiff against the plaintiff's claim and enter judgment for the defendant in the proceedings in the sum of $97,483.23.
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Tilley Air Conditioning Pty Limited
Traminer Pty Limited
CITATION: Tilley Air Conditioning Pty Limited v Traminer Pty Limited [2010] NSWDC 331
Akron Securities a Illiffe (1997) 41 NSWLR 353 AMP Services Limited v Manning [2006] FCA 256 Brandi v Mingott (1976) 12 ALR 551 BB Constructions (Aust) Pty Limited v Brian A Cheeseman Pty Limited (1994) 35 NSWLR Codelfa Construction Pty Limited v State Rail Authority (NSW) (1982) 149 CLR 337 Demagogue Pty Limited v Ramensky (1992) 39 FCR 31 Erle v Castlemaine District Coummunity Hospital [1074] VR 722 Franklins Pty Limited v Metcash Trading Limited [2009] NSWCA 407 CASES CITED: Global Sportsman Pty Limited v The Mirror Newspapers Pty Limited (1984) 2 FCR 82 Jones v Dunkel (1959) 101 CLR 298 Kitzbeau Pty Limited v WG and B Pty Limited (1995) 184 CLR 281 Lumbers v W Cook Builders Pty Ltd (in liq) (2008) 232 CLR 635 Manly Council v Byrne [2004] NSWCA 123 Mister Figgins Pty Limited v Centrepoint Freehold Pty Limited (1981) 36 ALR 23 Reg Russell Sons Pty Limited v Buxton Meats Pty Limited (1994) ATPR(digest) 46-127 re Creative Landscape Design Centre Pty Limited and Ors [1989] FCA 370 re Gilda Johnstone and Murray Robert Johnstone v Delata Pty Limited and Ors [1993] CRA 79 Webb Distributors (Aust) Pty Limited v The State of Victoria and Anor (1993) 179 CLR 15
[1989] FCA 370
[1993] FCA 79
(1997) 41 NSWLR 353
(1976) 12 ALR 551
(1982) 149 CLR 337
(1992) 39 FCR 31
(1984) 2 FCR 82
(1959) 101 CLR 298
(1995) 184 CLR 281
(2008) 232 CLR 635
(1981) 36 ALR 23
(1993) 179 CLR 15
(1994) 35 NSWLR 227
(1984) 54 ALR 157