© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2020] WASCA 201
Court of Appeal (WA)
2020-12-03
Buss P
Original judgment source is linked above.
The Contractor shall claim payment progressively in accordance with Item 33.
An early progress claim shall be deemed to have been made on the date for making that claim.
If the time for any progress claim falls due on a day which is Saturday, Sunday, statutory or public holiday the Contractor shall submit the claim either on the day before or next following that date which itself is not a Saturday, Sunday, statutory or public holiday.
Each progress claim shall be given in writing to the Superintendent and shall include details of the following, calculated in accordance with Annexure Part J:
(i) the value of WUC carried out to the end of the previous month and the amount forecast in accordance with Annexure Part P together with all amounts then otherwise due to the Contractor arising out of or in connection with the Contract;
(ii) the total amount previously certified pursuant to this subclause 37.1;
(iii) the amount being claimed by the Contractor;
(iv) separately identify work attracting GST and work which does not attract GST; and
(v) a written report on the progress made in carrying out the Works during the preceding period since the last progress report in a form approved by the Principal and containing as much detail as the Principal reasonably requires.
The Superintendent shall, within 10 business days after receiving such a progress claim, issue to the Principal and the Contractor, assessed in accordance with Annexure Part J:
(a) a progress certificate identifying the progress claim to which it relates and evidencing the Superintendent's opinion of the moneys due from the Principal to the Contractor pursuant to the progress claim and reasons for any difference ('progress certificate'); and
(b) a certificate identifying the progress claim to which it relates and evidencing the Superintendent's assessment of retention moneys and moneys due from the Contractor to the Principal pursuant to the Contract.
If the Contractor does not make a progress claim in accordance with subclause 37.1, the Superintendent may issue the progress certificate with details of the calculations and shall issue the certificate in paragraph (b) of this subclause 37.2.
If the Superintendent does not issue the progress certificate within 10 business days of receiving a progress claim in accordance with subclause 37.1, that progress claim shall be deemed to be the relevant progress certificate.
The Principal shall on the first day of the following month after the Superintendent receives the progress claim, pay to the Contractor the balance of the progress certificate after setting off such of the certificate in paragraph (b) of this subclause 37.2 as the Principal elects to set-off. If that setting off produces a negative balance, the Contractor shall pay that balance to the Principal within 7 days of receiving written notice thereof.
Neither a progress certificate nor a payment of moneys shall be evidence that the subject WUC has been carried out satisfactorily. Payment other than final payment shall be payment on account only.
At any time and from time to time, the Superintendent may by a further certificate correct any error which has been discovered in any previous certificate, other than a certificate of practical completion or final certificate.
Within 28 days after the expiry of the last defects liability period, the Contractor shall give the Superintendent a written final payment claim endorsed 'Final Payment Claim' being a progress claim together with all other claims whatsoever in connection with the subject matter of the Contract including all claims which the Contractor considers exist under or arising out of any alleged breach of the Contract whether or not such claims have been made at any time previously.
Within 42 days 10 business days of after the expiry of the last defects liability period the Contractor's final payment claim, or where the Contractor fails to provide such claim, the expiration of the period for lodging the final payment claim, the Superintendent shall issue to both the Contractor and the Principal a final certificate evidencing the moneys finally due and payable between the Contractor and the Principal on any account whatsoever in connection with the subject matter of the Contract.
Those moneys certified as due and payable shall be paid by the Principal or the Contractor, as the case may be, within 14 7 days after the debtor receives the final certificate. (original emphasis)
38.2 Withholding payment
Subject to the next paragraph, the Principal may withhold moneys certified due and payable in respect of the progress claim until the Contractor complies with subclause 38.1.
The Principal shall not withhold payment of such moneys in excess of the moneys evidenced pursuant to subclause 38.1 as due and payable to workers, Consultants and subcontractors. (original emphasis)
If the Contractor fails to show reasonable cause by the stated date and time, the Principal may by written notice to the Contractor:
(a) take out of the Contractor's hands the whole or part of the work remaining to be completed and suspend payment unless or until it becomes due and payable pursuant to subclause 39.6; or
(b) terminate the Contract.
When work taken out of the Contractor's hands has been completed, the Superintendent shall assess the cost thereby incurred and shall certify as moneys due and payable accordingly the difference between that cost (showing the calculations therefor) and the amount which would otherwise have been paid to the Contractor if the work had been completed by the Contractor.
If the Contractor is indebted to the Principal, the Principal may retain construction plant or other things taken under subclause 39.5 until the debt is satisfied. If after reasonable notice, the Contractor fails to pay the debt, the Principal may sell the construction plant or other things and apply the proceeds to the satisfaction of the debt and the costs of sale. Any excess shall be paid to the Contractor.
If the Contract is terminated pursuant to subclause 39.4(b) or 39.9, the parties' remedies, rights and liabilities shall be the same as they would have been under the law governing the Contract had the defaulting party repudiated the Contract and the other party elected to treat the Contract as at an end and recover damages.
If the Contract is wrongfully terminated by the Principal or rightfully terminated by the Contractor under clause 39.9, the Contractor shall then be entitled to a claim for:
(i) WUC which will include all direct costs, indirect costs, EPCM costs and Fixed Margin incurred up to and including the date for termination minus any payments that have already been made;
(ii) demobilisation costs, cancellation fees and other reasonable expenses and[/]or costs applicable in complying with or as a consequence of the termination; and
(iii) pro‑rata of the Performance Margin being 4.5% of all direct costs, indirect costs and EPCM costs incurred up to and including the date for termination.
If the Principal rightfully terminates the contract pursuant to clause 39.4 prior to the date of Practical Completion, then the Principal shall not be required to pay the Performance Margin and the Contractor shall reimburse to the Principal amounts paid by the Principal for WUC that has not yet been performed but the Contractor shall be entitled to claim for:
(i) WUC which will include all directs costs, indirect costs, EPCM costs and Fixed Margin incurred up to and including the date for termination minus any payments that have already been made;
(ii) demobilisation costs, cancellation fees and other reasonable expenses and or costs applicable in complying with or as a consequence of the termination.
A party may deduct from moneys due to the other party, any money due or which may become due from that other party under the Contract or otherwise.
If a difference or dispute (together called a 'dispute') between the parties arises in connection with the subject matter of the Contract, including a dispute concerning:
(a) a Superintendent's direction; or
(b) a claim:
(iii) for restitution based or unjust enrichment or other quantum meruit; or
or like claim available under the law governing the Contract,
then either party shall, by hand or by registered post, give the other and the Superintendent a written notice of dispute adequately identifying and providing details of the dispute.
Notwithstanding the existence of a dispute, the parties shall, subject to clauses 39 and 40 and subclause 42.4, continue to perform the Contract.
Within 14 days after receiving a notice of dispute, the parties shall confer at least once to resolve the dispute or to agree on methods of doing so. At every such conference each party shall be represented by a person having authority to agree to such resolution or methods. All aspects of every such conference except the fact of occurrence shall be privileged.
If the dispute has not been resolved within 28 days of service of the notice of dispute, that dispute shall be and is hereby referred to arbitration.
If within a further 14 days the parties have not agreed upon an arbitrator, the arbitrator shall be nominated by the person in Item 37(a). The arbitration shall be conducted in accordance with the rules in Item 37(b).
Nothing herein shall prejudice the right of a party to institute proceedings to enforce payment due under the Contract or to seek injunctive or urgent declaratory relief.
The commencement of proceedings, dispute notices and the appointment of an arbitrator
In resolving that issue I am mindful there are two decisions of this court which support [Tianqi's] view against the submissions made by [MSP]. All of the relevant decisions are first instance decisions. I take as the starting point that I should only follow the [sic] [Lysaght Building Solutions], if I am clearly of the view that [Eriez Magnetics] and GR Engineering are wrongly decided.
[Clause 37] mandates a procedure for the certification of amounts payable. Once those amounts are payable then contractually they are not in dispute. A principal is given an opportunity to raise off setting claims for consideration by the superintendent. But if that is not done and an amount is certified then it must be paid. That is the point of Rolfe J's decision in Algons Engineering [Pty Ltd v Abigroup Contractors Pty Ltd (1998) 14 BCL 215] and it is a point which has been emphasised again and again in any number of cases.
But even if an arbitrator was able to make an interim award which required payment of the certified amount, it is a clumsy process. It offers no real benefit to any of the parties. There is no warrant for issuing a stay on that basis.
[MSP] in this case has applied for summary judgment. Such applications are determined on affidavit evidence. Both counsels [sic] seemed to accept [Tianqi] would not be able to raise, in answer to the summary judgment application, a claim of equitable set-off. By referring matters to arbitration [Tianqi] has foreclosed that possibility [so MSP contended]. That may or may not be correct - this is the hearing of a stay application and not a hearing on the summary judgment application. In any event, it seems unlikely any of [Tianqi's] witnesses who might file affidavit evidence on the summary judgment application would need to appear in person to give evidence. In other words, I am not satisfied that duplication of proceedings - insofar as there is any duplication - would favour the exercise of discretion and warrant the grant of a stay. (emphasis added)
Nothing herein shall prejudice the right of a party to institute proceedings to enforce payment due under the contract not in dispute or to seek injunctive or urgent declaratory relief.
The parties have chosen to refer the dispute to arbitration. That's the forum which has to deal with that matter and the court cannot simultaneously make a determination of that question.
...
We say the dispute is just a dispute as to whether or not payment is due and the question of whether or not there [is] a reasonably arguable defence is one, we say, that falls for determination for the arbitrator not for a court in determining the operation of s 8 and [cl 42.4].
...
[T]he appropriate course is not to engage in the merits of the defence but rather to permit that all disputes are referred to arbitration. [It is accepted] that a party must show there is a dispute so, to that extent, without ... getting into the merits of it, the court must be able to see that there's a dispute.
[C]lause 42 of the contracts survives any contention by [Tianqi] that the whole of the contracts are void. If clause 42.4 survives so as to enable [Tianqi] to bring the arbitration proceedings, clause 42.4 must also survive. It is in clause 42. [Tianqi] does not, and cannot on any principled basis, contend that clause 42.4 is void if clause 42 is not. Second, whatever parts of the contracts [Tianqi] eventually seeks to identify as being void (and those others that survive), the process of clause 42.4 enabling resort to municipal courts to enforce certified payments (in terms of clause 37.2) that are due will survive. There is no suggestion that [Tianqi], or their legal advisers who advised on and drafted the agreements, did not understand the operation of clauses 37 and 42. Furthermore, the essential design of the agreements is that clause 37 creates a pay now argue later regime. This regime will never be avoided as a result of the contentions advanced as to misleading and deceptive conduct.
The Arbitration Act The Arbitration Act provisions
An arbitration agreement is an agreement by the parties to submit to arbitration all or certain disputes which have arisen or which may arise between them in respect of a defined legal relationship, whether contractual or not.
(1) A court before which an action is brought in a matter which is the subject of an arbitration agreement must, if a party so requests not later than when submitting the party's first statement on the substance of the dispute, refer the parties to arbitration unless it finds that the agreement is null and void, inoperative or incapable of being performed.
(2) Where an action referred to in subsection (1) has been brought, arbitral proceedings may nevertheless be commenced or continued, and an award may be made, while the issue is pending before the court.
- Arbitration agreement and interim measures by court (cf. Model Law Art 9)
It is not incompatible with an arbitration agreement for a party to request, before or during arbitral proceedings, from a court an interim measure of protection and for a court to grant the measure.
(a) maintain or restore the status quo pending determination of the dispute (ie, broadly speaking, an interlocutory injunction);
(b) take action that would prevent, or refrain from taking action that is likely to cause, current or imminent harm or prejudice to the arbitral process itself (ie, broadly speaking, an order for the preservation of the integrity of the arbitral process);
(c) provide a means for preserving assets, out of which a subsequent award may be satisfied (ie, broadly speaking, a Mareva injunction); and
(d) preserve evidence that may be relevant and material to the resolution of the dispute (ie, broadly speaking, an Anton Piller order).
The emphasis in the Act is upon the voluntary submission by parties of their disputes to arbitration. By its terms, s 8 provides that when its preconditions are satisfied, the court must refer the parties to arbitration (subject to exceptions which are presently immaterial). Section 8 of the Act confers power on the court, together with a duty to exercise the power in a case where the power arises. If the statutory conditions are satisfied, the court 'must' make an order referring the parties to arbitration. Where, despite agreement by the parties to submit identified disputes to arbitration, one of those parties commences an action in a court in relation to such a dispute, s 8 provides the mechanism for making effectual the parties' agreement as to how their commercial disputes are to be resolved. The mandatory nature of s 8 ensures that the parties to an arbitration agreement are held to their bargain to resolve their disputes by arbitration rather than curial determination. (citations omitted)
(a) whether the applicant for the stay must establish on the balance of probabilities that the matter in which the court proceedings are brought is the subject of an arbitration agreement; or
(b) whether it is sufficient for the applicant to show what appears to be a valid arbitration agreement which prima facie covers the matters in dispute, without having to establish the matters in s 8 on the balance of probabilities.
We think that any rigid taxonomy of approach is unhelpful, as are the labels 'prima facie' and 'merits' approach. How a judge deals with an application under s 8 of the CA Act will depend significantly upon the issues and the context. Broadly speaking, however, and with some qualification, aspects of the prima facie approach have much to commend them as an approach that gives support to the jurisdiction of the arbitrator and his or her competence, as recognised by the common law and by s 16 of the CA Act, whilst preserving the role of the Court as the ultimate arbiter on questions of jurisdiction conferred by ss 16(9) and (10), 34(2)(a)(iii) and 36(1)(a)(iii) of the CA Act. Broadly, the approach is consonant with the structure of the CA Act and the Model Law. However, it is difficult to see how the Court can exercise its power under s 8 without forming a view as to the meaning of the arbitration agreement. Further, it may be that if there is a question of law otherwise affecting the answer to the question of jurisdiction, especially one that is confined, which might be dispositive, it might be less than useful for the Court not to deal with it.
...
To understand whether a body of disputes being the 'matter', assessed and characterised (at the necessarily early stage of the proceeding), is the subject of an arbitration agreement, will generally require the Court to form a view as to the legal meaning of the arbitration agreement. Section 8 is an important power the purpose of which is to protect the practical legitimacy and authority of the arbitration process as reflected in the words of s 1C of the CA Act. It involves the referral to arbitration, by a stay of court proceedings. However, it will often not be possible fully to delineate the metes and bounds of a dispute without fully hearing the dispute. To do so, that is to hear the facts to decide the width of the dispute, would undermine the practical and effective operation of s 8. The application must be brought early (not later than when submitting the party's first statement on the substance of the dispute). The boundaries of the dispute may be unclear, but it will have to be characterised on the material available to be assessed as to whether it can be seen to be the 'subject of' the arbitration agreement. That latter assessment will require some stability or clarity as to the meaning of the arbitration agreement. The Court is then required to construe the clause, at least to the point of being satisfied that the disputes forming the matter are the subject of the agreement, or not, as the case may be. That said, and it is relevant to the arguments here, not every legal question need be, or should be, decided by the Court about the rights and obligations of the parties. That too would tend to undermine the practice and effective operation of s 8.
Need for a sustainable argument for there to be a matter
In my view, the approach in Robotunits is consistent with the approach articulated in Berezovsky, which I respectfully consider to be correct for the reasons given by Aitkens LJ. Thus, in my view, the correct approach is to decide on the balance of probabilities whether, on the proper interpretation of the relevant arbitration agreement, a matter arising in the proceeding falls within the scope of the agreement. This will generally involve a characterisation of the matter, without an assessment of the merits of the disputes arising from the matter. However, in some cases, it may be necessary to consider the merits of a claim or defence said to be the subject of an arbitration agreement in order to be satisfied that there is a relevant 'matter'. For example, if the application of the release is a matter which falls within the scope of an arbitration agreement, the mere fact that the release's application is asserted will not justify a finding as to the existence of a matter the subject of the arbitration agreement if there is no sustainable argument that the release potentially operates to bar or preclude the claims the subject of the dispute.
There is a further difficulty in the approach of the primary judge insofar as it proceeded beyond a characterisation of the nature of the matter and whether it fell within the arbitration agreement. The requirement of an assessment as to whether there was a 'sustainable argument' that the matter falls within the arbitration agreement has its dangers. Of course, if there is no sustainable argument that a matter or dispute can be characterised as falling within the agreement, it should not be referred to arbitration. But difficulties arise if this enquiry becomes one directed to the strength of the case raised by the issue or matter. The importance of this will become more evident in due course ... It is sufficient to say at this point that it would generally be wrong for the Court to examine an argument in a form of summary disposal application, and, if it were thought that an asserted case, in terms otherwise falling within the scope of the agreement, was sufficiently weak not to be 'sustainable', not to refer the matter to arbitration. That would be to usurp the role of the arbitrator. The Court's role in s 8 is not to act as a court of summary disposal filtering the matters that are suitable for arbitration.
The proper construction of the contracts Constructional choices
(a) A party may institute proceedings to enforce payment due under cl 37.2 only so long as the obligation to make the payment is undisputed, irrespective of the merits (or lack thereof) on which the obligation to make the payment is disputed. On this construction, proceedings may not be instituted where the defendant disputes the obligation to make the payment, even if the defendant does not raise an objectively triable issue by way of defence. This is essentially the construction advanced by Tianqi at [46] ‑ [49] above.
(b) A party may institute proceedings to enforce payment due under cl 37.2 irrespective of whether the obligation to make the payment is disputed or the grounds on which the existence of the payment obligation is disputed. On this construction, proceedings may be instituted even where the defendant does raise an objectively triable issue by way of defence.
(c) The reference to 'proceedings to enforce payment due' under the contract is to proceedings which are capable of summary determination: ie, proceedings in which there is no objectively triable issue which would form a proper basis for defending a summary judgment application.
Before the learned master and on this appeal the appellant advanced a number of matters which it was submitted should have persuaded the master in any event not to order summary judgment. These may be summarised as:
(a) the claims were for progress not final payments,
(b) there was dispute whether the moneys were properly finally due to [the subcontractor],
(c) the capacity of [the subcontractor] to repay in the event of an ultimate finding against it was in doubt,
(d) there had been a reference to arbitration,
(e) there were a number of set off claims[.]
...
In my view, however, it is apparent from the nature of what is raised that [the main contractor] is in truth seeking to introduce issues as to its ultimate rights and liabilities under the subcontract into a claim based on a contractual obligation to make provisional payments. None of the matters agitated provides an answer in law to the obligation of the main contractor to have paid to the subcontractor the amounts which comprise the judgment sum. In this respect, I notice cl 47.5 of AS2545 1993 which includes a provision that 'Nothing herein shall prejudice the right of a party to institute proceedings to enforce payments due under clause 42'. (emphasis added)
If the Dispute has not been resolved within 28 days of service of the notice of Dispute or such longer period as the parties may agree in writing, that Dispute shall, subject to the Dispute being a Pass Through Claim and the operation of the Pass Through Provisions, be and is hereby referred to arbitration.
...
Nothing herein shall prejudice the right of a party to institute proceedings to enforce payment due under the subcontract or to seek injunctive or urgent declaratory relief.
Turning to Eriez's alternative submission premised on cl 42.5, it does seem to me that the breadth of the disputes referable to arbitration is relevant to the proper construction of this clause. As I mentioned earlier, the breadth of disputes the subject of the dispute resolution clause is very wide, as it concerns any dispute arising in connection with, amongst other things, a claim. As I noted earlier, the expression 'claim' is defined to include any claim for payment of money under the subcontract. Consequently, any claim for payment of money under the subcontract is a dispute.
In that context, it seems to me to be clear that when cl 42.5 preserves the right of a party to institute proceedings to enforce payment due under the subcontract, it cannot be referring to the payment of amounts which are disputed. Rather, the provision is directed to the enforcement by the court of payment of moneys due and owing and no longer disputed under the subcontract.
That approach is consistent with, and supported by the other provisions of cl 42.5 which exempt from the operation of cl 42 proceedings seeking injunctive or urgent declaratory relief. A common characteristic, of course, of injunctive or urgent declaratory relief is that it is relief of a kind not easily or readily given by an arbitrator. Similarly, arbitrators are incapable of making orders enforcing payment of awards made by an arbitrator. So, cl 42.5 is directed to preserving the rights of parties to invoke the jurisdiction of the courts in circumstances in which an arbitrator could either not provide the relief sought, in terms of enforcement, or would have difficulty providing the relief sought, as is the case with urgent or injunctive declaratory relief. The clause has no application where there is a dispute, because otherwise its operation would entirely undermine all the provisions of cl 42 which precede it. As Eriez's claims for payment are disputed, it seems to me that cl 42.5 does not apply, and it cannot be seriously contended that the relief sought by Eriez in these proceedings is either injunctive or declaratory relief which is urgent.
Clause 47.4 carves out claims for payments due under the Contract, in the following terms:
'Nothing herein shall prejudice the right of a party to institute proceedings to enforce payment due under the Contract or to seek injunctive or urgent declaratory relief in respect of a dispute under clause 47 of any matter arising under the Contract.' (original emphasis)
Accordingly, [the contractor's] action in respect of its three [certified] payment claims and [the principal's] action in respect of the payment claimed to be due [to it] under the [alleged payment certificate in its favour] are not subject to arbitration under the Contract.
[I]n my opinion, the payment claimed by [the principal] under the [alleged payment certificate in its favour] is covered by the 'carve out' provided by cl 47.4 which provides that nothing in the Contract shall prejudice the right of a party to institute proceedings to enforce payment due under the Contract. As such, even though the parties did invoke the provisions of cl 47.2 in an attempt to resolve the issue as to whether any and what sum is payable pursuant to the [certificate], the parties specifically addressed the issue as to the forum to determine the dispute, in the event that it remained outstanding. They agreed not to preclude a party to the dispute to institute proceedings before a court to enforce the payment claimed to be due under the Contract. This is precisely what para 56A of the defence and para 67 of the counterclaim seek to do.
For this reason, no stay or other order ought to be made in relation to para 56A of the defence and para 67 of the counterclaim [concerning payment to the principal under the alleged payment certificate].
In relation to para 68 of the counterclaim which alleges various waivers and estoppels alleged in the defence, insofar as they relate to cl 42 of the Contract, and the payment claims made under that clause which are the subject of the present proceedings before the court, the allegations ought to remain for determination by the court. They constitute an issue for the decision of the court in the course of the determination of the payment claims which are excluded from the arbitration agreement by cl 47.4.
Characterisation of the matter in which the primary proceedings were brought
Certification of amount payable under cl 37.2 and availability of set-off
Tianqi's contentions concerning avoidance of the contracts ab initio
(a) would have entered into 'a fixed price lump sum EPCM contract which it was familiar with';
(b) alternatively, would have ensured that costs were capped under the contract; and
(c) further or alternatively, would not have awarded the contract to MSP.
(a) entered into the alleged LHPP2 contract; and/or
(b) engaged in further negotiations in raising the CAPEX for LHPP2.
I have read the Notices of Dispute which were prepared by the defendant with the assistance of its external lawyers in a short timeframe so as to respond to the Statutory Demand. Notwithstanding the timeframe, to the best of my knowledge and belief, each material assertion of fact in the Notices of Dispute is true.
Tianqi did not establish that MSP's claim was not capable of summary determination
I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.
[1] MSP Engineering Pty Ltd v Tianqi Lithium Kwinana Pty Ltd [2020] WASC 251.
[3] The contract which (according to the parties) is relevant for present purposes is annexed to the affidavit of R F van Erp sworn 30 March 2020, annexure RFVE‑1, GB 70 ‑ 273. A distinction was not drawn by the parties for present purposes between LHPP1 and LHPP2.
[5] Affidavit of R F van Erp sworn 30 March 2020, annexure RFVE‑15, GB 312 ‑ 328.
[6] Affidavit of R F van Erp sworn 30 March 2020, annexure RFVE‑16, GB 329 ‑ 331. The reference to 'equitable set-off' is at GB 331. Despite the express reference to 'equitable set-off', Tianqi in its written submissions referred to this as 'legal set-off': appellant's written submissions, par 29; WB 19.
[7] See cl 2 of each deed of variation, affidavit of R F van Erp sworn 30 March 2020, annexure RVE‑6, RVE‑7; GB 283, 297.
[8] Affidavit of A Rowe sworn 1 May 2020, GB 367.
[9] Affidavit of A Rowe sworn 1 May 2020, pars 31 - 34, 47 - 52; GB 341, 344 - 352; affidavit of J Dunbar dated 1 May 2020, pars 7 - 14; GB 412 - 413.
[10] Affidavit of A Rowe sworn 1 May 2020, par 51; GB 345.
[15] Eriez Magnetics Pty Ltd v Duro Felguera Australia Pty Ltd [2017] WASC 304.
[16] GR Engineering Services Ltd v Eastern Goldfields Ltd [2018] WASC 19.
[19] Lysaght Building Solutions Pty Ltd v Blanalko Pty Ltd [No 3] [2013] VSC 435.
[31] Reference was made to Francis Travel Marketing Pty Ltd v Virgin Atlantic Airways Ltd (1996) 39 NSWLR 160, 165; Rinehart v Welker [2012] NSWCA 95; (2012) 95 NSWLR 221 [118]; Comandate Marine Corporation v Pan Australia Shipping Pty Ltd [2006] FCAFC 192; (2006) 157 FCR 45 [164]; see also Rinehart v Hancock Prospecting Pty Ltd [2019] HCA 13; (2019) 366 ALR 635 [83] (Rinehart v Hancock).
[33] Appeal ts 52 - 54, with reference to cl 15.1 - cl 15.2, cl 19.5(a) and (b), cl 27(e), cl 29.3, cl 30.7, cl 34.9, cl 35, cl 37.4, cl 37.6.
[36] Appeal ts 64; reference was made to Bulkbuild Pty Ltd v Fortuna Well Pty Ltd [2019] QSC 173 [18].
[37] Appellant's written submissions, par 25(c); WB 18. Tianqi's written submissions made no reference to where, in the materials before the master, Tianqi had raised before the master claims to set aside the contracts under the Australian Consumer Law, being sch 2 to the Competition and Consumer Act 2010 (Cth).
[38] Appellant's written submissions, par 27; WB 18.
[39] Appellant's written submissions, pars 34 - 37; WB 21.
[40] Appellant's written submissions, par 39; WB 21 - 22, with reference to Straits Exploration (Australia) Pty Ltd v Murchison United NL [2005] WASCA 241; (2005) 31 WAR 187 [15], [30].
[41] Appellant's written submissions, par 41; WB 22.
[43] Respondent's written submissions, par 38; WB 37, with reference to Glenview Home Inc v Digital Telecommunications Systems Pty Ltd [2003] TASSC 62 [7]; Viridian Noosa Pty Ltd v Neumann Contractors Pty Ltd [2009] QSC 398 [9]; Bayside Civil & Drainage Pty Ltd v Marinestar Holdings Pty Ltd [2000] WASC 17 [10]; Main Roads Construction Pty Ltd v Samary Enterprises Pty Ltd [2005] VSC 388 [19] ‑ [20]; Vantage Holdings Pty Ltd v JHC Developments Group Pty Ltd [2011] QSC 155 [43] ‑ [45].
[46] Appellant's reply to notice of contention, par 16; WB 54.
[47] Appellant's reply to notice of contention, par 17(b); WB 55.
[51] Devaugh Pty Ltd v Lamac Developments Pty Ltd [1999] WASCA 280; (2000) 16 BCL 378.
[52] CPD Contractors Pty Ltd v Celsus Pty Ltd (fka SA Health Partnership Nominees Pty Ltd) [2017] FCA 1620; (2017) 353 ALR 84 [90] ‑ [91], [108] ‑ [109]; Gilgandra Marketing Co-Operative Ltd v Australian Commodities & Marketing Pty Ltd [2010] NSWSC 1209 [52]; The Property People v Housing New Zealand Ltd (1999) (HC) 14 PRNZ 66 [24]; Nearmap Ltd v Spookfish Pty Ltd [2014] NSWSC 1790 [50] ‑ [51].
[53] Tanning Research Laboratories Inc v O'Brien [1990] HCA 8; (1990) 169 CLR 322, 350 - 351; Rinehart v Hancock [67].
[54] See Recyclers of Australia Pty Ltd v Hettinga Equipment Inc [2000] FCA 547; (2000) 100 FCR 420 [18]; Tanning Research (343 - 344), (351 - 354); Flint Ink NZ Ltd v Huhtamaki Australia Pty Ltd [2014] VSCA 166; (2014) 44 VR 64 [31] ‑ [34], [88]; Hancock Prospecting Pty Ltd v DFD Rhodes Pty Ltd [2020] WASCA 77 [125] - [135].
[55] Tanning Research (348), (351); Four Colour Graphics Australia Pty Ltd v Gravitas Communications Pty Ltd [2017] FCA 224 [18]; Casaceli v Natuzzi SpA [2012] FCA 691; (2012) 292 ALR 143 [48]; Amcor Packaging (Aust) Pty Ltd v Baulderstone Pty Ltd [2013] FCA 253 [44].
[57] Rinehart v Rinehart (No 3) [2016] FCA 539; (2016) 257 FCR 310 [103] ‑ [115]; Fitzpatrick v Emerald Grain Pty Ltd [2017] WASC 206 [56]; Samsung C&T Corporation v Duro Felguera Australia Pty Ltd [2016] WASC 193 [40] ‑ [44]; Joint Stock Co 'Aeroflot Russian Airlines' v Berezovsky [2013] EWCA Civ 784; [2013] 2 Lloyd's Rep 242.
[58] Hancock Prospecting Pty Ltd v Rinehart [2017] FCAFC 170; (2017) 257 FCR 442 (Hancock FFC) [141]; cf Rinehart (No 3) [103] - [115]; Fitzpatrick [56]; Samsung v Duro [40] ‑ [44].
[59] Rinehart (No 3) [103] - [115]; Fitzpatrick [56]; Samsung v Duro [40] ‑ [44].
[60] Hancock FFC [145] ‑ [146]. The CA Act refers to the Commercial Arbitration Act 2010 (NSW). Section 8(1) of the CA Act is in identical terms to s 8(1) of the Arbitration Act.
[61] Robotunits Pty Ltd v Mennel [2015] VSC 268; (2015) 49 VR 323 [20].
[64] Cape Lambert Resources Ltd v MCC Australia Sanjin Mining Pty Ltd [2013] WASCA 66; (2013) 298 ALR 666.
[70] See, eg, Re Concrete Constructions Group Pty Ltd [1996] QCA 086; (1997) 1 Qd R 6, 11 ‑ 14; Algons Engineering Pty Ltd v Abigroup Contractors Pty Ltd (1998) 14 BCL 215; Daysea Pty Ltd v Watpac Australia Pty Ltd [2001] QCA 049; (2001) 17 BCL 434 [18] ‑ [21]; Main Roads Construction [26] ‑ [42]; Devaugh [42] ‑ [44], [132] ‑ [135]; Lysaght Building Solutions [29].
[71] Appeal ts 54. In an earlier stay application to this court Tianqi referred to Aquatec‑Maxcon Pty Ltd v Minson Nacap Pty Ltd [2004] VSCA 18; (2004) 8 VR 16 [53] ‑ [54] and Queensland University of Technology v Project Constructions (Aust) Pty Ltd [2002] QCA 224; [2003] 1 Qd R 259 [19] ‑ [24].
[73] See appeal ts 71. The only relevance of cl 39.10 on Tianqi's case on appeal was that cl 39.10 formed part of the contractual context in which cl 42.4 is to be construed.
[74] As senior counsel for Tianqi accepted: appeal ts 44.
[77] See also in this regard, s 12 and s 13 of the Arbitration Act.
[78] It is unnecessary to consider the availability of arbitral power to grant declarations or injunctions in this case. See, however generally, Seeley International Pty Ltd v Electra Air Conditioning BV [2008] FCA 29; (2008) 246 ALR 589 [26] ‑ [28]; Cufone v Cruse [2000] SASC 17 [50] ‑ [61], and on appeal Cufone v Cruse [2000] SASC 304; (2000) 210 LSJS 238.
[79] The concepts of 'due' and 'due and payable' are discussed in CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd [No 2] [2017] WASCA 123 [122].
[80] See, eg, cl 37.4, cl 37.5, cl 39.7, cl 39.9.
[81] Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd [2015] HCA 37; (2015) 256 CLR 104 [46] ‑ [51], [59]; Victoria v Tatts Group Ltd [2016] HCA 5; (2016) 90 ALJR 392 [51]; Black Box Control Pty Ltd v TerraVision Pty Ltd [2016] WASCA 219 [42].
[83] See Ecosse Property Holdings Pty Ltd Gee Dee Nominees Pty Ltd [2017] HCA 12; (2017) 261 CLR 544 [17]; Electricity Generation Corporation v Woodside Energy Ltd [2014] HCA 7; (2014) 251 CLR 640 [35]; Black Box [42(9)].
[84] Devaugh [3], [23], [34] - [36], [42], [64] - [66], [93] - [98].
[90] Eriez Magnetics [15] - [31], [53].
[100] Lysaght Building Solutions [3], [5].
[101] Lysaght Building Solutions [6] - [7].
[102] Lysaght Building Solutions [113(c)], [148].
[103] Lysaght Building Solutions [113(a)].
[104] Lysaght Building Solutions [8].
[105] Lysaght Building Solutions [34] - [86].
[106] Lysaght Building Solutions [87] - [88].
[107] Lysaght Building Solutions [89] - [90], [122].
[108] Lysaght Building Solutions [91] - [111].
[109] Lysaght Building Solutions [112], [122].
[110] Lysaght Building Solutions [113(c)], [148].
[111] Lysaght Building Solutions[121] - [122].
[112] Lysaght Building Solutions [146] - [148].
[113] Lysaght Building Solutions [113(a)], [149] - [158].
[114] Appellant's submissions filed 9 October 2020, pars 15 - 17.
[115] Respondent's submissions filed 16 October 2020, pars 16 - 18.
[116] Respondent's submissions filed 16 October 2020, pars 20, 22.
[117] Affidavit of R F van Erp sworn 30 March 2020, annexure RFVE‑15, pars 15(a), 16 - 17; GB 313 ‑ 314.
[118] Affidavit of R F van Erp sworn 30 March 2020, annexure RFVE‑15, par 17; GB 314 - 315.
[119] Affidavit of R F van Erp sworn 30 March 2020, annexure RFVE‑15, par 18; GB 315.
[120] Affidavit of R F van Erp sworn 30 March 2020, annexure RFVE‑15, par 21; GB 315 - 316.
[121] Affidavit of R F van Erp sworn 30 March 2020, annexure RFVE‑15, par 23; GB 316.
[122] Affidavit of R F van Erp sworn 30 March 2020, annexure RFVE‑15, par 24; GB 316.
[123] Affidavit of R F van Erp sworn 30 March 2020, annexure RFVE‑16, pars 5 - 12; GB 330.
[124] Mr van Erp did not swear to those matters to the best of his 'information', knowledge and belief, or identify the sources of his knowledge.
[125] Hearing 28/05/20; GB 7, 22 - 23.
[128] See, in particular, primary decision [3], [11], [13], [23] - [24], [27] - [29].
[129] See, for example, Saldanha v City of Belmont [2018] WASCA 7 [123] - [124].
(2004) 8 VR 16
(1996) 39 NSWLR 160
(2012) 95 NSWLR 221
(2006) 157 FCR 45
(2019) 366 ALR 635
(2005) 31 WAR 187
(2017) 353 ALR 84
(1990) 169 CLR 322
(2000) 100 FCR 420
(2014) 44 VR 64
(2012) 292 ALR 143
(2016) 257 FCR 310
(2017) 257 FCR 442
(2015) 49 VR 323
(2013) 298 ALR 666
(1997) 1 Qd R 6
(2008) 246 ALR 589
(2015) 256 CLR 104
(2016) 90 ALJR 392
(2017) 261 CLR 544
(2014) 251 CLR 640