Annexure A
No. Builder's Claim Subject of/factual overlap with existing arbitration proceedings Subject of existing arbitration agreements under Project Documents Builder comments
1 Disputed Defects • Defects Arbitration (being ACICA Case 2016-99 as between the State and Project Co, and ACICA Case 2017-102 as between Project Co and the Builder) and Defects Compensation Arbitration (being ACICA Case 2017-103 as between the State and Project Co, and ACICA Case 2017-104 as between Project Co and the Builder), before Mr Lindgren • Agree that, broadly, there is a factual overlap (in ACICA Case 2017-110 and 2017-111 at paragraph 16.13)
• State's alleged "unconscionable", "wrongful" and/or "unlawful" conduct in relation to Disputed Defects, see ASOC [32]-[37], [69], [78], [83]; • Paragraph 16.13 does not refer to the State's conduct as being "unconscionable" or "unlawful".
• See Builder's Defects Particulars;1
• See Builder's Economic Harm Particulars, [1(d)];2
• See Builder's Loss and Damage Particulars, [5.4], [7.2], [7.3]3
2 Safety Defects • Builders Notice Arbitration as between State and Project Co (ACICA Case 2017-110), before Mr Lindgren (see [16.13] of State's Notice of Arbitration);4 • Challenge to IC/Project Co determination of EOT claims re notification of safety defects, per CC cl 42.10/42.22, subject to Construction Arbitration Agreement; • Agree that, broadly, there is a factual overlap (in ACICA Case 2017-110 and 2017-111 at paragraphs 16.13 and 16.14).
• State's alleged "wrongful" and/or "unlawful" conduct in notifying existence of safety defects, see ASOC [43], [78], [83]; • ACICA Case 2017-111, as between Project Co and Builder • Challenge to Project Co's entitlement to notify the safety defects under the Construction Contract and/or as to existence of the safety defects5, subject to Construction Arbitration Agreement
• See Builder's Economic Harm Particulars, [1(e)];
• See Builder's Loss and Damage Particulars, [7.3]
3 EPAS (Enterprise Patient Administration System) • Builders Notice Arbitration as between State and Project Co (ACICA Case 2017-110), before Mr Lindgren;7 • General dispute as to what the State was required to provide to Project Co under the Project Agreement/what Project was required to provide the Builder under the Construction Contract in terms of EPAS, subject of both the Project Arbitration Agreement and the Construction Arbitration Agreement; • Agree that, broadly, there is a factual overlap in relation to the first point in the column to the left and (refer to section 16.1 to 16.6 of ACICA Case 2017-110 and ACICA Case 2017-111).
• Allegations concerning alleged 'EPAS Representations' and 'EPAS Delays', see ASOC [29]-[31], [38]-[42], [47]-[48], [55]-[58], [61]- [69], [81(b)]; • ACICA Case 2017-111, as between Project Co and Builder • Although presently unclear, to the extent that Builder: (i) alleges that Project Co failed to procure the State to complete the State Works in respect of EPAS (per CC cl 28); or (ii) challenges the IC's determination (adopted by Project Co) certifying TC8, subject of Construction Arbitration Agreement • ACICA Case 2017-110 and ACICA Case 2017-111 only set out six high level bullet points in relation to EPAS, while specific and numerous references have been made to the EPAS claims in the FCA proceedings.
• See Builder's EPAS Particulars;6 - We note that the EPAS Representations in ACICA Case 2017-110) and ACICA Case 2017-111 are not the same (and is more limited) as those outlined in the Federal Court Proceedings. The EPAS Representations in the arbitrations are simply that the State misrepresented EPAS (section 16.4), whereas the Federal Court EPAS Representations include, the State representing that ([47] of ASOC):
• See Builder's Loss and Damage Particulars, [2], [4], [5] - A fully functional EPAS was available to be installed at the nRAH;
- The State Works (including the EPAS for the nRAH) would be delivered and completed before the proposed amended date of TC, and in any event with sufficient time for the Builder to integrate the EPAS for the nRAH with the rest of the ICT Network and perform all the necessary testing before the proposed amended date for TC; and
- The availability of EPAS at the nRAH (or alternatively, its unavailability) would not render it impossible for the Builder to achieve TC by 4 April 2016.
• Many of the paragraphs of the ASOC referenced are not contained in the arbitrations, however, they are broad factual matters which we would expect to see in a pleading later on.
4 EPAS • Builders Notice Arbitration as between State and Project Co (ACICA Case 2017-110), before Mr Lindgren;9 • Builder's breach of warranties and undertakings under the Construction Contract (CC cll 28, 63.3, 65.5), subject to Construction Arbitration Agreement; • Agree, broadly, there is factual overlap.
• Allegation of reliance upon 'EPAS Representations', see ASOC [56]; • ACICA Case 2017-111, as between Project Co and Builder • Builder's breach of warranties and undertakings under BDD cl 4.4 and CC cl 63.3, subject to Builder Direct Arbitration Agreement • We note, however, that paragraph [56] of the ASOC notes that, the Builder relied on the EPAS Representations when determining to:
• See Builder's EPAS Particulars, [46]-[69]; - enter into the Interim Settlement Agreement;
• See Builder's Loss and Damage Particulars, [2] - in planning the design, construction, commissioning and testing phases of the ICT network of the hospital; and/or
- after 17 September 2015, what Claims it was necessary for the Builder to lodge.
• However, the arbitrations only reference the entry into the Interim Settlement Agreement and decisions in relation to which Claims to make (bullet points 1 and 3 above). It does not include reference to the planning the design, construction, commissioning and testing phases of the ICT network of the hospital
5 EPAS • Builders Notice Arbitration as between State and Project Co (ACICA Case 2017-110), before Mr Lindgren;10 • Challenge to IC/Project Co determination of EOT claims re 'EPAS Delays', per CC cl 42.10/42.22, subject to Construction Arbitration Agreement • Agree, broadly, there is factual overlap (refer to section 16.5 of ACICA Case 2017-110 and ACICA Case 2017-11).
• Allegation that Builder would have been able to make Claims, but for 'EPAS Representations' ASOC [56(c)]; • ACICA Case 2017-111, as between Project Co and Builder • We note that there appears to be an error in the reference to clause 42.10/42.22 of CC (as there is no such clause)
• See Builder's Loss and Damage Particulars, [2]
6 EPAS • Builders Notice Arbitration as between State and Project Co (ACICA Case 2017-110), before Mr Lindgren;11 • Challenge to IC/Project Co determination of EOT claims re 'EPAS Delays', per CC cl 42.10/42.22, subject to Construction Arbitration Agreement; • Agree, that broadly, there is factual overlap (refer to section 16.5 of ACICA Case 2017-110 and ACICA Case 2017-11), however, there is no express reference to the Builder's contention in the particulars being 'the IC wrongfully rejected the Builder's claim without a proper consideration of the Builder's submissions' ([41]) in the arbitrations.
• See Builder's EPAS Particulars, [8], [41]-[45] • ACICA Case 2017-111, as between Project Co and Builder • Builder otherwise precluded from making Claims in respect of 'EPAS Delays' by CC cl 42.19, subject to Construction Arbitration Agreement
7 Procuring Breach • Builders Notice Arbitration as between State and Project Co (ACICA Case 2017-110), before Mr Lindgren;12 • Any allegation that Project Co breached Construction Contract, subject to Construction Arbitration Agreement; • Agree, that broadly, there is factual overlap (refer to section 16.17 of ACICA Case 2017-110 and ACICA Case 2017-11).
• Allegation that State induced or procured Project Co to breach the Construction Contract, see ASOC [21]-[28], [70]-[76]; • ACICA Case 2017-111, as between Project Co and Builder • Although presently unclear, to the extent that the Builder: (i) contends that the Financiers' Revised Cure Plan was ineffective or that it was not a valid Cure Plan for the purposes of the Project Agreement and/or the Financier Direct Deed; (ii) challenges the certification of TC and/or CA13, subject of Construction Arbitration Agreement/Project Arbitration Agreement • We note that the Economic Harm Particulars should refer to [1.1(a)] and [1.1(b)]
• See Builder's Economic Harm Particulars, [1(a)], [1(b)]; • See comment above at Item 2, bullet point 2
• See Builder's Loss and Damage Particulars, [6]
8 Procuring Breach • Builders Notice Arbitration as between State and Project Co (ACICA Case 2017-110), before Mr Lindgren;14 • Requires Builder to establish that the Project Agreement did not Completion Deed/Consents and Acknowledgement Deed and that they were not a legitimate means by which Project Co and the Financiers sought to cure the late-TC Major Default, subject to Construction Arbitration Agreement • Builder's Economic Harm Particulars should refer to [1.1(a)] and [1.1(b)]
• Allegation that State "wrongfully" or "unlawfully" caused Project Co to enter into Completion Deed/Consents and Acknowledgement Deed, see ASOC [78], [83]; • ACICA Case 2017-111, as between Project Co and Builder • See comment above at Item 2, bullet point 2
• See Builder's Economic Harm Particulars, [1(a)], [1(b)]
• See Builder's Loss and Damage Particulars, [6], [7]
• [7]
9 IC Conduct • Builders Notice Arbitration as between State and Project Co (ACICA Case 2017-110), before Mr Lindgren;17 • Agree that broadly there is a factual overlap (refer to section 16.11 and 16.12 of ACICA 2017-110).
• Allegations that the IC breached its obligations under the IC Agreement and/or acted unreasonably/ other than in accordance with good industry practice, which conduct directed or consented to by the State and/or Project Co, see ASOC [40]-[42], [43(b)-(c)], [44]-[45], [49]-[53], [55], [59]-[62], [77], [78(d)], [80]-[81]; • ACICA Case 2017-111, as between Project Co and Builder • These allegations were also included in the NOCE (which was referenced in ACICA Case 2017-110 and ACICA Case 2017-111). The allegations in relation to the IC:
• See Builder's [78(d)] IC Conduct Particulars;15 - breaching its obligations under the IC Agreement;
• See Builder's [80] IC Conduct Particulars;16 - acting unreasonably/other than in accordance with good industry practice,
• See Builder's Economic Harm Particulars, [2]; were set out in section 8 of the NOCE (E.15).
• See Builder's Loss and Damage Particulars, [3], [7.4]-[7.7] • The allegations that the conduct was 'directed or consented to by the State and/or Project Co' is set out in sections 8.10, 8.11 and 8.18 of the NOCE.
10 IC Conduct • Builders Notice Arbitration as between State and Project Co (ACICA Case 2017-110), before Mr Lindgren;18 • Any allegation that Project Co breached Construction Contract, subject to Construction Arbitration Agreement; • Agree that, broadly, there is a factual overlap (see section 16.8 of ACICA Case 2017-111 and ACICA Case 2017-110.).
• Allegation that Project Co breached cll 5.3/5.4 of Construction Contract by failing to ensure that the IC acted in accordance with the requirements of the IC Agreement/Project Agreement, see ASOC [77] (by reference to matters set out at ASOC [40]- [42], [43(b)-(c)], [44]-[45], [49]-[53], [55], [59]- [62], [78(d)] and/or [80]-[81]) • ACICA Case 2017-111, as between Project Co and Builder • Requires Builder to establish that IC's conduct in breach of the Project Agreement/IC Agreement, subject to Project Arbitration Agreement and IC Arbitration Agreement • This allegation is contained within the NOCE at sections 8.1 (generally) and 8.5(f).
11 IC Conduct • Builders Notice Arbitration as between State and Project Co (ACICA Case 2017-110), before Mr Lindgren;19 • Requires Builder to establish that IC and State's conduct in breach of the Project Agreement/IC Agreement, subject to Project Arbitration Agreement and IC Arbitration Agreement • Agree that, broadly, there is a factual overlap (refer to section 16.9 of ACICA Case 2017-111 and ACICA Case 2017-110).
• Allegation that State "wrongfully" or "unlawfully" in directing/consenting to IC's conduct and/or interfering in the IC's performance of contractual functions, see ASOC [78(d)], [83]; • ACICA Case 2017-111, as between Project Co and Builder • The general references in the NOCE are at sections 8.10 and 8.11.
• See Builder's [78(d)] IC Conduct Particulars;
• See Builder's Economic Harm Particulars, [1(c)], [2];
• See Builder's Loss and Damage Particulars, [7.4]- [7.7]
12 IC Conduct • Builders Notice Arbitration as between State and Project Co (ACICA Case 2017-110), before Mr Lindgren;20 • Any challenge to IC/Project Co determination of Builder's EOT claims, to be made per CC cl 42.10/42.22, subject to Construction Arbitration Agreement • Agree that, broadly, there is a factual overlap, save that:
• Allegation that IC failed to administer Builder's EOT Claims and/or permitted State to interfere with discharge of its independent functions, see Builder's [80] IC Conduct Particulars, [6(d)], [7], Schedule 7; • ACICA Case 2017-111, as between Project Co and Builder - ACICA Case 2017-111 and ACICA Case 2017-110 only refers to the IC's determinations rejecting the Builder's EOT claims as being final and binding. There is no reference to the IC failing to administer the EOT claims (see section 16.12); and
• See Builder's Economic Harm Particulars, [1(c)], [2]; - the IC's failure to administer the Builder's EOT Claims was not included in the NOCE.
• See Builder's Loss and Damage Particulars, [7.4]- [7.7] • The allegations contained in the NOCE discuss the IC seeking and/or taking directions from the State on matters pertaining to the Independent Certifier Services (see section 8.5(a)).
• The general references to the State's interference with the IC's independent functions is set out at sections 8.10 and 8.11 of the NOCE.
13 Cross-Claims • Subject to Project Arbitration Agreement and/or IC Arbitration Agreement • Agree.
• Any cross-claims, claims for indemnity or contribution as between any of the State, Project Co or the IC in relation to any of Builder's claims, including in relation to State Indemnity Claim, the IC Indemnity Claim and/or the IC Dispute