[2025] WASCA 88
General information, not legal advice.
Court of Appeal (WA)
2025-06-13
Mitchell JA
Original judgment source is linked above.
(1) before entering into the contract for the sale of the land, Threadgold had substantially completed the work (or had completed a material part of the work), including the obtaining of approvals, necessary to enable sand to be lawfully removed from the land on a commercial basis;
(2) Threadgold and APH had entered into the Sand Removal Agreement and its terms and purpose;
(3) by development approval application 20/0437, Threadgold had applied for development approval for removal of sand from part of the land;
(4) Threadgold had also applied for a clearing permit, which had been approved in principle;
(5) Threadgold and Mr Threadgold had agreed that, in consideration of Threadgold acting or causing to be taken all necessary steps to remove and sell sand from the land, Threadgold would be entitled to any proceeds or profits derived from that; and
(6) the commercial purpose of the Revenue Sharing Agreement, in circumstances where:
(a) Mr Threadgold wished to sell, and Staunton wished to buy the land;
(b) Threadgold had undertaken work in respect of the land which added value to the land; and
(c) Threadgold had not been compensated for that work or otherwise rewarded for the adding of value;
was to ensure that Threadgold was compensated for that work, notwithstanding the sale of the land by Mr Threadgold to Staunton.
(1) By cl 1, Staunton 'will share 50% of the income derived from the sand removal ($2.00 per Tonne excluding GST) as contemplated in [the Sand Removal] Agreement, subject to':
(a) Threadgold procuring all required approvals[11] within 13 months from the date of the agreement (so by 19 November 2022);
(b) Threadgold 'pays all costs associated with procuring such approvals'; and
(c) Threadgold assigns to Staunton, 'all rights and obligations under the [Sand Removal] Agreement'.
(2) By cl 2, Staunton 'agrees to use all reasonable endeavours to allow the extraction of all sand within the shortest time possible'.
(3) By cl 3, '[t]he revenue sharing only relates to [development approval application 20/0437] and as covered by the [Sand Removal] Agreement'.
(4) By cl 4, Staunton could enter into a different agreement with APH to maximise tax efficiency, provided that did not adversely or materially affect Threadgold.
(5) By cl 5, the Revenue Sharing Agreement ceases at the earlier of:
(a) the 'completion of the sand removal as contemplated in the [Sand Removal] Agreement'; or
(b) five years from the settlement date of the property (being 26 November 2026).
(6) By cl 6, Threadgold and Staunton 'will act in good faith and use all reasonable endeavours to cooperate throughout the lifetime of this agreement'.
(1) By recital B, Threadgold 'shall obtain a Development Approval by the City of Busselton and Clearing Permit CPS 8863/1 for [APH] to extract sand from the land in accordance with the conditions set out in the Development Approval (hereinafter "the Approval")'.
(2) By recital C, '[w]hen granted, a copy of the Approval is set out in the First Schedule hereto'. (No approval had been granted at the time the Sand Removal Agreement was executed).
(3) By recital D, Threadgold 'has agreed with [APH] to allow [APH] exclusively to remove sand from the area identified on the plan set out in the Second Schedule hereto (hereinafter "the Plan") and otherwise upon the terms and conditions of this Agreement'.
(1) By cl 2, Threadgold 'agrees that [APH] shall have the exclusive right to remove sand from the [l]and in accordance with the [a]pproval and from the area outlined in on the Plan from the date of execution of this Agreement until the expiration of the Approval OR 300,000 Loose Cubic Metres (LCM) of sand have been extracted, OR any extended date as hereinafter described'.
(2) By cl 3, APH shall pay to Threadgold 'an amount of $4.00 per tonne plus GST in respect to the sand removed from the [l]and and otherwise in accordance with the terms of this Agreement'.
(a) their agreement concerned the sand the subject of the Sand removal agreement (that is, the sand located on the part of the land identified in development approval application 20/0437) (specified sand);
>
> (b) the plaintiff would procure development approval, the clearing permit, and any other approvals necessary to permit the lawful removal of the specified sand[;]
>
> (c) the time for the plaintiff to procure the approvals was 13 months from the date of entry into the Revenue sharing agreement;
(f) the defendant would cause the removal of the specified sand from the land;
(k) the Revenue sharing agreement would subsist until the earlier of the date of the completion of the removal of the specified sand and 5 years from the date on which the defendant became the registered proprietor of the land;
(l) the plaintiff and the defendant would each act in good faith in their dealings with each other in respect of or in connection with the Revenue sharing agreement;
(m) the plaintiff and the defendant would cooperate with each other in all respects in relation to or in connection with the operation of the Revenue sharing agreement; and
(n) the defendant would use all reasonable endeavours to ensure that all steps to be taken in the performance of the agreement occurred within the shortest time possible to enable the plaintiff's interest in the land to be extracted in the shortest time reasonably possible.
(1) from about 20 April 2022 to 1 July 2022, repeatedly refused or failed, despite requests by Threadgold, to advise DWER that Staunton was, as was the fact, authorised by Threadgold to procure clearing permit application 8863/1 (statement of claim paragraphs 16 and 17);
(2) caused a third party to apply for a clearing permit (statement of claim paragraph 18);
(3) itself applied for a clearing permit (statement of claim paragraph 19);
(4) acted in a manner that was likely to interfere, hamper, delay and prevent performance of the agreement by Threadgold (statement of claim paragraph 20);
(5) wrongfully asserted that, if Threadgold did not obtain a clearing permit within 13 months from the date of the agreement, Staunton was relieved of its obligations to Threadgold under the agreement (statement of claim paragraph 21(a)); and/or
(6) failed or refused to perform its obligations under the agreement (statement of claim paragraph 21(b)).
Ground 1.2 - was the construction of cl 2 determinative?
(1) In breach of the Revenue Sharing Agreement, Staunton hindered Threadgold's efforts to obtain the clearing permit (and, when the permit was not obtained within the 13-month period stipulated in the Revenue Sharing Agreement, Staunton had then wrongly asserted that it was therefore relieved of its obligations under that agreement).
(2) The acts of hinderance were varied and occurred repeatedly in the period from 20 April 2022 to 11 November 2022.
(3) Threadgold submits that these acts breached Staunton's obligations to act in good faith, cooperate and use reasonable endeavours, as pleaded in the statement of claim paragraphs 9(l), 9(m) and 9(n), read with 9(a), 9(b), 9(c), and 9(k).[43]
(4) But for Staunton's breaches, the clearing permit would have been granted and extraction of the sand could have commenced on or about 1 July 2022.
(5) Threadgold was thereby deprived of the opportunity of sharing in revenue from the sand.
(6) Threadgold was entitled to damages for the lost opportunity.
(a) A failure by the plaintiff to obtain the clearing permit within 13 months from the entry into the agreement does not relieve the defendant from its obligations to the plaintiff under the agreement;
(b) Further or alternatively in circumstances where the defendant did not make time of the essence a failure by the plaintiff to obtain the clearing permit within 13 months from the entry into the agreement does not relieve the defendant from its obligations to the plaintiff under the agreement;
(c) Further or alternatively the obligation upon the defendant to perform under the agreement has not been discharged;
(d) [A]t all times during its subsistence the defendant is honestly obliged to use all reasonable endeavours to remove the specified sand from the land; and
(e) The agreement between the plaintiff and the defendant remains on foot.
Ground 1.3 - was there a real question to be tried as to whether the Revenue Sharing Agreement remained on foot?
It is now accepted that superior courts have inherent power to grant declaratory relief. It is a discretionary power which '[i]t is neither possible nor desirable to fetter ... by laying down rules as to the manner of its exercise.' However, it is confined by the considerations which mark out the boundaries of judicial power. Hence, declaratory relief must be directed to the determination of legal controversies and not to answering abstract or hypothetical questions. The person seeking relief must have 'a real interest' and relief will not be granted if the question 'is purely hypothetical', if relief is 'claimed in relation to circumstances that [have] not occurred and might never happen' or if 'the Court's declaration will produce no foreseeable consequences for the parties'. (citations omitted)
(1) First because, as at the date the writ was issued, there was a dispute to quell as to whether the Revenue Sharing Agreement remained on foot. If it was on foot, Staunton would be obliged to assist Threadgold to obtain the clearing permit.
(2) Second because, if the agreement is still on foot, it is foreseeable that sand will be removed before the agreement expires on 26 November 2026.
If it is found that the Learned Master erred in failing to consider other causes of action arising from the pleaded case of the Appellant, the decision should be upheld because:
(a) the evidence did not disclose an arguable fact to support any alternative cause of action; and
(b) the Appellant did not contend what other causes of action remained open and arguable as pleaded, on the evidence before the Court.
Paragraph (a) - the evidence did not disclose an arguable fact
(1) Threadgold was required to establish that there was a triable issue that APH had elected, prior to the issue of the writ, to exercise its right to remove sand.[60]
(2) Staunton had adduced evidence[61] to show that APH had not made an election to exercise its right to remove sand, as at the date the writ was issued.[62]
(3) This discharged Staunton's onus, and shifted the evidentiary onus to Threadgold to demonstrate that there was a triable issue that APH had indeed elected to remove the sand.[63]
(4) The evidence sought to be adduced by Threadgold of the amendment to the development approval did not assist Threadgold because the proposed evidence did not go to APH's intention prior to the writ being issued.[64]
(1) The Revenue Sharing Agreement provides that it is subject to Threadgold procuring all required approvals within 13 months from the date of the agreement (so by 19 November 2022);
(2) In breach of the Revenue Sharing Agreement, Staunton had prevented Threadgold from obtaining the clearing permit by 19 November 2022 (and had then wrongly asserted that it was therefore relieved of its obligations under that agreement); and
(3) The fact that the clearing permit had not been obtained by 19 November 2022 did not mean that the Revenue Sharing Agreement was no longer on foot because, among other things,
(a) it was Staunton's breaches of the agreement that prevented the clearing permit being obtained within that period; and/or
(b) time was not of the essence.
(1) Staunton discharged its onus by adducing evidence that showed that APH had not made an election to exercise its right to remove sand as at the date the writ was issued. There was then an evidentiary onus to Threadgold to demonstrate that there was 'some indication sufficient to give rise to a triable issue, that [APH] had evinced an intention to [elect to remove sand or to remove sand] in the near future'.[66]
(2) The evidence sought to be adduced by Threadgold of the amendment to the development approval was insufficient to discharge that onus.
(3) Threadgold did not argue, or amend its pleading, to contend that the mere issue of an amended approval by the City of Busselton was evidence of APH's state of mind as to its intentions.
Further submissions and application to adduce evidence
I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.
[1] Ground 1, appellant's submissions [27] ‑ [31] WAB 19 - 20.
[2] See appellant's submissions [24] WAB 18. And see GAB 39 - 46; appeal ts 7 - 8, 21 - 22.
[3] See Threadgold Architecture Pty Ltd v Staunton Developments Pty Ltd [2024] WASC 199 (primary decision) [17(4)]; GAB 119 [10(a)].
[4] See primary decision [17(3)]; GAB 119 [10(b)].
[5] The Sand Removal Agreement can be found at GAB 91 ‑ 99.
[7] The Revenue Sharing Agreement can be found at GAB 89 ‑ 90.
[11] Defined as being all the council and other approvals required to ensure the lawful extraction and removal of sand.
[12] GAB 92. It appears to be common ground that the agreement which was JPT-5 of the affidavit of Jonathan Paul Timms sworn 9 May 2024 was the agreement said to be attached to the Revenue Sharing Agreement (see WAB 15 fn 2).
[13] Agreed Chronology [5] WAB 39; GAB 100 ‑ 105.
[18] Agreed Chronology [9] WAB 39. The action was commenced in the District Court but was remitted to the Supreme Court on 11 April 2023 - see primary decision [69], [71], [73].
[19] Agreed Chronology [9] WAB 39; GAB 129 [6], 141 ‑ 142.
[22] Statement of claim prayer for relief A(e). The full list of declarations sought is set out later under the heading 'Claim for a declaration'.
[23] Statement of claim prayer for relief C.
[24] The affidavit is in GAB 128 ‑ 152.
[25] Plaintiff's outline of submissions in support of application to reopen and to lead new evidence, filed 12 December 2023 [16] ‑ [17].
[26] Primary decision [26]; see Pisano v South Metropolitan Health Service [2023] WASCA 80; (2023) 414 ALR 130 [52].
[35] Primary decision [29], [61] ‑ [62].
[39] The amended grounds of appeal filed 12 August 2024 refer to ground 2 instead of ground 3, but this was a typographical error - see appeal ts 2.
[40] Respondent's submissions [4] WAB 30 - 31.
[42] Respondent's submissions [19]. See also respondent's submissions [31].
[45] Sellars v Adelaide Petroleum NL [1994] HCA 4; (1994) 179 CLR 332, 350.
[48] Ainsworth v Criminal Justice Commission [1992] HCA 10; (1992) 175 CLR 564.
[53] See statement of claim par 9(a) and appeal ts 16 - 17. Staunton did not contend otherwise.
[54] See the respondent's submissions in reply to the appellant's submissions as to notice of contention, filed 7 May 2025 (respondent's supplementary submissions) [11] - [13], [17], [19(a) ‑ (b)]. Further, Staunton does not contend that the original development approval did not satisfy the condition in cl 1(a) of the Revenue Sharing Agreement that all approvals be obtained within 13 months of the agreement - see respondent's supplementary submissions [1] (read with [1.1] of the appellant's submissions as to notice of contention, filed 24 April 2025 (appellant's supplementary submissions)).
[55] Appellant's submissions [46] ‑ [47]; GAB 129, 130 (showing that Warwick Kindt spoke in support of the officer recommendation at a council meeting. Mr Kindt was a representative of APH - see GAB 106 - 116), 137 - 141 (in particular, condition 4.4 at GAB 140), 141 - 151 (setting out the officer recommendation, and see, in particular, GAB 145E).
[57] See the respondent's supplementary submissions [10], [13].
[58] See the respondent's supplementary submissions [9], [12], [13], but cf [19(c)].
[59] Respondent's supplementary submissions [8].
[60] See the respondent's supplementary submissions [10], [13], [19(c)].
[61] Being the 2022 emails, GAB 106 - 116.
[62] Respondent's supplementary submissions [11].
[63] Respondent's supplementary submissions [12].
[64] Respondent's supplementary submissions [19(c)].
[65] In the hearing before the acting master, Staunton submitted that the Revenue Sharing Agreement was no longer on foot by, at the latest, 19 November 2022. See appeal ts 26, 28.
[66] Respondent's supplementary submissions [12].
[67] Plaintiff's outline of submissions in support of application for leave to reopen and to lead new evidence, filed 12 December 2023 [17].
[68] Plaintiff's outline of submissions in support of application for leave to reopen and to lead new evidence, filed 12 December 2023 [11].
[69] Zerjavic v Chevron Australia Pty Ltd [2020] WASCA 40 [65] - [67].
[70] As to which, see Frigger v The State of Western Australia [2025] WASCA 7 [212] - [213].
(2023) 414 ALR 130
(1994) 179 CLR 332
(1992) 175 CLR 564