The Star Entertainment Sydney Properties Pty Ltd v Buildcorp Group Pty Ltd
[2023] NSWSC 241
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2023-03-17
Before
Rees J
Source
Original judgment source is linked above.
Judgment (7 paragraphs)
Solicitors: Holding Redlich (applicants) Colin Biggers & Paisley (respondent) File Number(s): 2020/00112369
ex tempore Judgment - Application to amend pleading
- Her Honour: This is an application by the plaintiffs to amend their pleading. The plaintiffs already seek damages from the contractor in respect of a contract entered into in October 2014 and a second contract entered into in May 2015, to effect construction and refurbishment works at Star Casino. The plaintiffs now seek to add a claim for damages for breach of a third contract between the plaintiffs and the defendant contractor.
- The contractor accepts that the claim now sought to be brought is not time-barred. The problem is that a cross-claim by the contractor against its subcontractor is likely time-barred; the amendment is opposed for this reason.