[2019] ACAT 74
General information, not legal advice.
ACT Civil and Administrative Tribunal
2019-08-08
Member Robinson, Member Sutherland, Member Orr
Original judgment source is linked above.
User pays - Who benefits from the new infrastructure?
78. The establishment of the new infrastructure gave the 69 residential unit owners immediate and ongoing relief from subsidising the commercial units' electricity consumption. The commercial unit owners benefitted from the improved functioning of their air-conditioning in summer, although if this was sole purpose could have been achieved a lower cost.[24]
Having now completed the works each commercial owner owns and will be responsible for their own air conditioning and electrical cabling as it is dedicated to their respective units and therefore (is) not common property.[25]
_Common property is all the parts of a parcel identified as common property - _
(a) before a units plan is registered--in the relevant unit title application; or
(b) after the relevant units plan is registered - in the units plan.
90. The roof top is not shown on the plan but I am satisfied that it is, based on reasoning in Castro v The Owners Unit Plan No 246 (Castro): [28]
...that, in the absence of the units plan identifying common property, it is appropriate to conclude that the common property is that which is not marked as part of a unit, or a subsidiary to the unit.
An owners corporation for a units plan may, if authorised by an ordinary resolution - approve the installation of sustainability or utility infrastructure on the common property;
a conduit of any kind for the provision of a utility service, and includes, for example, pipes, wires, cables and ducts for a utility service.[29]
Unit owner responsibilities include maintenance, repair or replacement of air conditioning systems and its conduit and cabling, whether inside or outside of a unit, which serves only that unit. To avoid doubt, the rooftop or external to a unit air conditioning compressor may be situated on common property but this does not result in any obligation for the Owners Corporation to maintain, repair to replace the unit and its conduit and cabling.
Redress past unfairness caused by the original infrastructure
Motion 8 was the most practical way of redressing the unfairness arising from the Original Electricity Infrastructure such that each commercial owner pays for their own consumption and the Remedial Electrical Infrastructure.[31]
It must be the case that the proper basis of evaluation, of reaching the preferable decision, in these cases, is reference to community standards or community values. It is not the decision-maker's idiosyncratic view of what will adequately protect the public which is relevant, but what the decision- maker determines will achieve that result in accordance with community standards or values.
The reference to 'community standards' in the preceding excerpt is not a reference to the views expressed by the parties in a particular matter, it is a reference to 'more permanent values' such as those encapsulated in legislation.[33]
It is apparent from the circumstances of this case that there is significant potential for disagreement and conflict of interest between the owners of residential and commercial units in a mixed-use facility. No doubt such developments are attractive and vibrant places to live. However, the reality is that the interests of those who are running and business and those who are maintaining a home may not always be harmonious, particularly when it comes to the costs of services, such as utilities and rubbish removal, as well as lifestyle issues such as noise abatement and car parking. The current rules in relation to budget arrangements, in particular, appear to be unhelpful and inflexible and a legislative remedy may be necessary. Models in other jurisdictions, with longer histories of mixed-use developments, may present helpful models for reform.
[1] 2018 General Meeting of the Owners Corporation of Units Plan 3908 Aurora dated 29 November 2018, Motion 8
[3] SDNM Pty Limited v The Owners Unit Plan 3908 [2018] ACAT 102
[4] Pursuant to an unopposed resolution of the owners corporation at the 2016 AGM made in accordance with section 78(2)(b). I am unsure what the arrangement was prior to 2016 but the default position under the legislation is that all owners contribute according to their unit entitlements not their consumption.
[5] Pursuant to an unopposed resolution of the owners corporation at the 2016 AGM made pursuant to section 78(4) UTMA; and before that the default provisions in section 78(2)(a)
[6] Report from ESBC dated 17 September 2018, attachment B witness statement of Amnon Holland page 4
[7] Ibid see at 4.3, "Option 2- install sub meters"
[8] Minutes of the General Meeting of the owners corporation held 13 June 2018 at 2(b), attachment C witness statement of Luka Ujdur dated 25 February 2019
[9] SDNM v the Owners of Unit Plan 3908 [2018] ACAT 102 at [16]
[10] Email from Gary Green to Luka Ujdur dated 25 May, attachment B witness statement of Luka Ujdur dated 25 February 2019
[11] Minutes of the General Meeting of the owners corporation held 29 November 2018
[12] Detailed reply to respondent's undated submissions filed by the applicant 12 March 2019 page 4 at paragraph 18
[13] [2017] ACAT 51 at [17] - statement not disturbed on appeal before Presidential Member McCarthy in The Owners - Unit Plan No 396 v Uren & Blundell [2017] ACAT 100 and has been adopted in other cases
[14] [2018] ACAT 82, upheld on appeal [2019] ACAT 63
[15] Minutes of Annual General Meeting 2016 of Owners of Unit Plan 3908 held 4 April 2016 at motion 10, attachment E witness statement of Gary Green dated 14 September 2018
[16] SDNM v the Owners of Unit Plan 3908 [2018] ACAT 102 at [36]- [37]
[17] SDNM v the Owners of Unit Plan 3908 [2018] ACAT 102 at [19]
[18] SDNM v the Owners of Unit Plan 3908 [2018] ACAT 102 at [21]
[19] Transcript of proceedings 5 April 2019 page 17 at lines 6-11
[20] Nash v The Owners - Units Plan 2413 & Ors [2018] ACAT 54 at [59]
[21] Transcript of proceedings 5 April 2019 page 24 at lines 34-44; Report from ESBC dated 17 September 2018
[22] Applicant's undated submissions at paragraph 43
[24] Report from ESBC dated 17 September 2018
[25] Report from ESBC dated 17 September 2018
[27] Except one which one owner established in basement
[29] See analysis of the legislation in Castro in which the Tribunal found the OC not responsible for maintain electricity cables which were for the sole benefit of the applicant.
[31] Applicant's submissions undated at [41]
[32] UP 3908 Outcomes of Electrical Remediation works - Electricity Supply Costs
[35] Uren & Anor v The Owners Unit Plan No.396 [2017] ACAT 51 at [17]
[36] Uren & Anor v The Owners Unit Plan No.396 [2017] ACAT 51 at [17]
[37] SDNM Pty Limited v The Owners- Units Plan 3908 [2018] ACAT 102 at [50]
THE OWNERS - UNITS PLAN NO 3908
SDNM PTY LIMITED
Cases cited: Brudenell & Ors v Owners Corporation Unit Plan No 202 [2016] ACAT 101
Castro v The Owners Unit Plan No 246 [2016] ACAT 111
Clews v The Owners- Unit Plan No 3069 [2018] ACAT 82
Nash v The Owners - Units Plan 2413 & Ors [2018] ACAT 54
SDNM Pty Limited v The Owners - Units Plan 3908 [2018] ACAT 102
Uren & Anor v The Owners Unit Plan No 396 [2017] ACAT 51