The Owners Strata Plan 64757 v Sydney Remedial Builders Pty Ltd
[2023] NSWSC 1127
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2023-09-12
Before
Rees J, Mr JJ, McDougall J, As Parker J
Source
Original judgment source is linked above.
Judgment (9 paragraphs)
Solicitors: ITC Law (Plaintiff) McLean & Associates (Defendant) File Number(s): 2019/83317
Judgment
- HER HONOUR: The plaintiff, The Owners - Strata Plan 64757, seeks damages in respect of defective building works under section 48MA of Home Building Act 1989 (NSW). The defendant builder, Sydney Remedial Builders Pty Ltd, was retained to remedy building defects caused by the original builder. The parties have reached agreement as to quantum.
- The only issue is whether these proceedings, commenced on 15 March 2019, are within time. That question was referred to architect Dr Phillip Briggs for separate determination. Dr Briggs concluded that the date of practical completion of the works was 16 March 2012. Thus, the proceedings were commenced within the time required by section 18E of the Home Building Act, being before 16 March 2019.
- The plaintiff now urges the adoption of the referee's report under rule 20.24(a) of the Uniform Civil Procedure Rules 2005 (NSW), while the builder asks the Court to reject the report and determine the question for itself.