[2009] VCAT 34
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2009-01-12
Original judgment source is linked above.
Planning and Environment Act 1987 s149A; works for resurfacing school oval and construction of gates/fence; whether works exempt from permit as 'works normally associated with an education centre' (clause 62.02-2, as amended by VPP Amendment VC50); whether works 'generally in accordance with the development plan' for the land (clause 43.04-1)
The Ivanhoe Grammar School v Banyule CC [2009] VCAT 34
28 October 2008 no longer require a planning permit having regard to Clause 62.02 of the Banyule Planning Scheme, as amended by Amendment VC50 on 15 December 2008; * (b) The works relating to the re-surfacing of the School's north ground oval are generally in accordance with the Development Plan D777/0 approved by the Responsible Authority for the land on
1 February 2000 (as amended on 10 March 2006). * (c) The works relating the erection of three sets of gates adjacent to Russell Street and Scotts Parade (Gate 1), Fairy Street (Gate 18) and Elphin Street (Gate 19): * require a planning permit under Clause 43.01 of the Banyule Planning Scheme (Heritage Overlay HO-69) as the gates comprise part of a "fence" that specifically requires a planning permit under that clause. The works are therefore not exempt under Clause 62.02 of the Banyule Planning Scheme; * are generally in accordance with the Development Plan D777/0 approved by the Responsible Authority for the land on
Mr Egils Stokans, Solicitor, of Russell Kennedy Lawyers.
28 October 2008 (the 'north oval works'); and * works relating the erection of three sets of gates adjacent to Russell Street and Scotts Parade (Gate 1), Fairy Street (Gate 18) and Elphin Street (Gate 19) (the 'fence works'). These fence works have already been undertaken, and the school seeks retrospective approval. 2. The school's Ridgeway Campus is in a Residential 1 Zone. An Environment Significance Overlay, Vegetation Protection Overlay, Significant Landscape Overlay, Heritage Overlay, and Development Plan Overlay all apply to the school land. Subject to any exemptions under the Banyule Planning Scheme, it is common ground that: * a planning permit would be required for the north oval works under the Residential 1 Zone, the Significant Landscape Overlay, and the Heritage Overlay; and * a planning permit would be required for the fence works only under the Heritage Overlay. 3. Although the Development Plan Overlay (DPO) does not create a separate planning permit 'trigger', the DPO provides[1] that: * A permit must not be granted until a development plan has been prepared to the satisfaction of the responsible authority; * A permit granted must be generally in accordance with the development plan; and * An application for a planning permit under any provision of the scheme that is generally in accordance with the development plan is exempt from third party notice and review. 4. The responsible authority approved development Plan D777/0 for the school land on 1 February 2000. The plan was amended on 10 March 2006. 5. The responsible authority has however advised that it considers neither works are 'generally in accordance' with the development plan. The responsible authority has also purported to require and amendment to the development plan and/or third party notice of the permit applications. The school has therefore sought declarations under s 149A of the Planning and Environment Act 1987 that the works are generally in accordance with the existing development plan. 6. A prompt final hearing was held to enable a decision on the north oval works to be made quickly, as the school desires to implement these works during the summer recess. 7. Shortly before the prompt final hearing, on 15 December 2008, the Minister approved Amendment VC50 to all planning schemes, including the Banyule Planning Scheme applying to the school land. VC50 amended clause 62.02 to exempt certain works associated with an education centre from the requirement for a planning permit. 8. A preliminary question thus arises as to whether either works now fall within this new exemption and no longer require a planning permit. The responsible authority initially sought to have this issue deferred so that it could consider the implications of Amendment VC50. However, I am obliged to consider and apply the planning scheme as in force at the time of my decision. Given the need to have the planning status of the north oval works resolved quickly, the responsible authority ultimately conceded that the VC50 issue should be resolved within the prompt final hearing process and made submissions accordingly. 9. After hearing from the parties at the prompt final hearing, I expressed a view that the north oval works were now exempt from the requirement for a planning permit. I made an immediate oral declaration to that effect, and indicated reasons would follow. I reserved my decision in relation to the fence works.
Buildings and works normally associated with an education centre including, but not limited to, outdoor furniture, playground equipment, art works, drinking fountains, rubbish bins and landscaping.
Making certain minor buildings and works associated with an Education centre exempt from the requirement for a planning permit in clause 62.02, including: temporary portable classrooms, paving, seating, tables, shelters, rubbish bins, playground equipment, art work, shade sails, drinking fountains and facilities for the disabled.
The notice of approval of Amendment VC50 published in the Victorian Government Gazette on 15 December 2008 contains a similar form of wording to the Explanatory Report. The word 'minor' is not however present in the actual exemption introduced into clause 62.02-2, and the new clause also expressly exempts 'landscaping' whereas the Explanatory Report and Gazette use other examples such as 'paving' and 'shade sails'. The reference to 'temporary portable classrooms' and 'facilities for the disabled' in the Explanatory Report and Gazette are reflected in separate amendments to clause 62.02, and thus have little bearing on a characterisation of the genus or type of works under the new exemption that I must consider.
Are the north oval works 'generally in accordance with' the Development Plan?
Are the fence works 'generally in accordance with' the Development Plan?
The school intends to retain existing opportunities for public pedestrian access through the School, subject to its public liability obligations. There are no proposals in this Development Plan to restrict public pedestrian access to or through the Campus.
The three sets of new gates comprised in the fence works will have the effect of restricting public pedestrian access through the school land - at least for the periods when the gates are closed.
[1] Clauses 43.04-1 and 43.04-2 of the Banyule Planning Scheme
[2] Jocelyn Meadow Pty Ltd v Casey City Council [2004] VCAT 2627 at para [61] per Gibson DP, following Canet v Brimbank City Council [2003] VCAT 13
[3] As indicated earlier, clause 43.04-1 of the planning scheme (the Development Plan Overlay) requires that a permit granted must be generally in accordance with the development plan. A finding that the works are not generally in accordance with the development plan therefore leads to an effective prohibition on the works unless or until the development plan is amended.
The Ivanhoe Grammar School
Banyule CC [2009] VCAT 34