The Body Corporate for The Edge On Margate Beach (respondent)
Body Corporate and Community Management Act 1997 (Qld) (Act), and (3)(a)
Body Corporate and Community Management (Accommodation Module) Regulation 2020 (Accommodation Module)
That remediation works as detailed in the Scope of Work (Scope of Works - Edge on Margate.pdf) be endorsed to be undertaken to ensure the structural integrity of the building and address current water ingress issues.
That the quotation from Allied Commercial Pty Ltd (QBCC: 152 530 59) (Allied Edge on Margate Tender.pdf) for the completion of the remediation works be accepted
That the quotation from BRS Contracting Pty Ltd (QBCC: 1229384) (BRS Edge on Margate Tender.pdf) for the completion of the remediation works be accepted
Of the qualifying motions, Motion A received the most 'Yes"[sic] votes and is therefore the decision of the body corporate.
Motion 4. Appointment of Remediation Project Manager
That the Body Corporate enter into and execute an agreement appointing Domak Consulting Pty Ltd ACN 155 676 010 as trustee for The Dolbel Family Trust T/A Integrity Paint and Coatings Inspections and Project Management to perform the Duties of Project Manager (Integrity Final Project Management Agreement - Windows.pdf) pursuant to the operation of the remediation works.
That the finance for the cost of the project be arranged through a combination of Strata Loan with Lannock Capital 2 Pty Ltd and Owner lump sum contribution to fund working capital requirements for the remediation works
(a) That the Body Corporate enter into and execute a loan contract with Lannock Capital 2 Pty Limited (ACN 153 391 283) to fund working capital requirements for the remediation works for a maximum amount of credit of $1,250,000.00 or such increased amount as approved by a subsequent General Meeting.
(b) That the Body Corporate issue a one-off Sinking Fund Special Levy to each owner as per the attached sheet (Addendum 2 - Finance Hybrid), to a total combined maximum value of $1,250,000.00 (including GST), or such increased amount as approved by a subsequent General Meeting.
(c) The Body Corporate Committee has the authority to approve the raising of additional levies to ensure the Owners Corporation can perform its obligation in relation to each advance under the Loan Contract.
That the Finance for the entire cost of the project be funded through a Strata Loan with Lannock Capital 2 Pty Ltd
That the finance for entire cost of the project be raised wholly through a single Owner lump sum contribution (Special Levy) to fund working capital requirements for the remediation works
Of the qualifying motions, Motion C received the most 'Yes"[sic] votes and is therefore the decision of the body corporate.
With respect to the applicant's claim that the replacement of water-tight windows constitutes an improvement, the respondent body corporate cites the adjudicator's order in Paloma[14] as follows:
This concept does not require something identical to that originally in place but what would currently be appropriate.
In general terms, I would consider that if a window does not require replacement, but is being replaced primarily for uniformity, then its replacement would be an improvement rather than maintenance. However, if a significant portion of windows have defects or have deteriorated, it would be legitimate "preventative" maintenance to replace all other windows of a similar age or design which have not yet shown problems but are reasonably likely to do in the future.
It also states that the alternative proposal made by the original builder was based on an inspection of one of the applicant's lots, Lot 16, and recommended trialling solutions to that lot, adjusting the scope of works based on the trial and subsequent findings, and implementing the same scheme-wide. The respondent body corporate states that months prior to this alternative proposal being made, it had already decided at its annual general meeting in 2024 that the sample lot would be Lot 3;[16]
[1] The respondent body corporate states that on 28 February 2020 it engaged an engineer to provide a report ('Bells Report') which found that the flashing to the windows was defective and draining towards the window frame; that there did not appear to be any penetration or water ingress through the slab element; and that the window weepholes were unusually small with detached subsill flashings and gaps (See page 63 of the application).
[3] As per the contribution schedule lot entitlement for Lots 16 and 18
[4] The CMS includes the scheme's by-laws
[5] Sections 276)(1)(a) and (b) of the Act
[7] See Brighton on Broadwater Breezes [2018] QBCCMCmr 243 at [8]
[10] For general principles see for e.g., Australian Broadcasting Corporation v O'Neill [2006] HCA 46 and SDW2 Pty Ltd v JLF Corporation Pty Ltd & Ors [2017] QSC 1
[11] Cohen v Peko-Wallsend Ltd [1986] HCA 70 at [6]
[12] Meagher, Gummow and Lehane's Equity: Doctrines & Remedies (J.D. Heydon, M.J. Leeming, P.G. Turner) (Fourth Edition) (Sydney: LexisNexis Butterworths, 2002) at [21-395]; Bingham & Anor v 7-Eleven Stores P/L [2003] QCA 402 at [106]-[108]
[16] The respondent body corporate states that on 17 March 2024, an engineer it engaged (Donnan) prepared a remedial scope of works for the bay windows in the building and outlined a detailed description of trial to be undertaken on a sample lot to more accurately identify the extent of the remedial work required throughout the scheme building. It is also worth noting that the scope of works as set out in the invitation to tender states that the successful contractor will be required to undertake works for one lot to the south eastern elevation 'prior to the delivery of the greater project'. (It also states that the details of the sample lot will be provided at tender.
Subsequently, at the annual general meeting held on 23 May 2024, the respondent body corporate decided that Lot 3 would serve as the sample lot since it is in poor condition, partially deconstructed and would not require any scaffolding.
The respondent body corporate submits that thereafter on 1 December 2024, it held a question-and-answer meeting for all lot owners regarding the works. It adds that at this meeting, the applicant and two other lot owners recommended that the original builder be approached to provide an alternative scope of work. Subsequently, the original builder provided a report of an inspection of Lot 16 conducted on 28 November 2024 along with the developer of the building and the applicant. This report recommended the further deconstruction of one of the applicant's lots, Lot 16 to determine the full extent of the work required. The respondent body corporate states that it contravened its decision at the previous annual general meeting that Lot 3 would serve as the sample lot.
[17] See section 170(2) of the Accommodation Module
[19] It would be lower for Lot 21 which has the smallest contribution schedule lot entitlement