austlii:qld/QBCCMCmr/2025/98
General information, not legal advice.
QBCCMCmr
2025-03-24
Original judgment source is linked above.
The Body Corporate for The Ecovillage at Currumbin (applicant)
Body Corporate and Community Management Act 1997 (Qld) (Act), and (3)(a)
Application for emergency expenditure - whether circumstances constitute an "emergency".
Act, s 20; Standard Module, ss 172(1)(c), 180
Please note costs to run EGMs are not insignificant because the scheme is layered and has multiple body corporate managers. EGMs need to be prepared and schedule at each SBC before the PBC EGM (over 147 lots in total). Each BCM charges for EGMs and their administrative costs alone exceed $7,500. This excludes all the volunteer committee preparation and owner consultation time. As a result, is not in the best interests of owners run 10 EGMs if 5 can be scheduled in a few weeks instead. The PBC will pursue a PBC and SBC EGMs regardless but this emergency expenditure would enable the most urgent plumbing repair to be actioned much more quickly.
The leak could get worse at any time and this adds risk to the body corporate in terms of being able to maintain a viable wastewater collection and recycled water supply service to owners. More importantly, the recycled water is temporarily being supplied by a bore and does not currently contain contaminants that could adversely affect common property or the creek, however, once the Community Wastewater Management System upgrade is ready (imminent) the recycled water will need to contain chlorine (mandated last stage of disinfection) which could impact land or waterways which could add significant EPA legislative (legal) risks to the body corporate and hence significant costs. The body corporate should therefore act urgently to protect the body corporate's rights and obligations, to supply adequate and working essential services including recycled water for toilet flushing and sewage treatment. The Ecovillage is not connected to any Council or government sewer system so has to operate its own system. The urgent $2.4M CWMS upgrade (which owners have previously approved) is only days away from being operational, but it cannot be used until this leak is fixed, holding up the urgent essential service project. The plumbing firms who have quoted are currently available to schedule the works if/when selected, in approximately 2 weeks, if/when they are engaged. The $10,000 contingency has been included to account for unforseeable asset condition or weather events, or if Caretaker (Ecotones) effort/input is required. The PBC has passed a unanimous VOCM already to approve the works subject to it being able to go over its spending limit.
Failure to act immediately may lead to the body corporate incurring substantial additional unexpected costs such as manual removal of all sewerage wastewater (about 50,000L and $6,000 per day) by truck, and legal liability related risks. The plumbing works have been delayed because a) the new upgraded headend of the CWMS is now ready for connection and use, but this was not the case a few weeks ago b) manual trucking of sewage will be needed if the upgraded plant cannot be connected so the plumbing fixes are required to avoid this substantial cost.
[1] Section 20, Act, section 180, Standard Module
[2] Section 172(1)(c), Standard Module
[3] My search of Titles Office records for each subsidiary scheme resulted in a total of 147 layered lots (see para [3]). The resulting difference of $200 in the relevant limit for committee spending is immaterial.
[4] The definition of the relevant limit for major spending (where no amount has been set by a general meeting) is the lesser of $1,100 x the number of layered lots; or $10,000