austlii:tas/TASPComm/2026/8
General information, not legal advice.
TASPComm
2026-03-06
Original judgment source is linked above.
State Policies and Schedule 1 Objectives of the Act
It is anticipated that where a whole SPP provision is substituted or an additional provision added, it would have the same format as the SPP provision.
(a) make an application to the planning authority for a permit, which permit could not be issued unless the LPS were amended as requested; and
(b) request the planning authority to consider the request to amend the LPS and the application for a permit at the same time.
Modified amendment 19-2025, Tasmanian Planning Scheme - Northern Midlands
1. Amend clause NOR-Site-specific Qualifications by inserting the following:
Description (modification, substitution or addition)
A substitution to Acceptable Solution A1 for this site is:
Each lot, or a lot proposed in a plan of subdivision, must:
(a) be required for public use by the Crown, a council or a State authority;
(b) be required for the provision of Utilities or irrigation infrastructure;
(c) be for the consolidation of a lot with another lot provided both lots are within the same zone; or
(d) be for the separation of the Agriculture Zone from the Future Urban Zone along the alignment of the Midland Highway which divides the site.
A substitution to Acceptable Solution A1 for this site is:
Each lot, or a lot proposed in a plan of subdivision, must:
(a) be required for public use by the Crown, a council or a State authority;
(b) be required for the provision of Utilities;
(c) be for the consolidation of a lot with another lot provided each lot is within the same zone; or
(d) be for the separation of the Future Urban Zone from the Agriculture Zone along the alignment of the Midland Highway which divides the site.

The development must be in accordance with the endorsed document P1 (Subdivision Proposal Plan, 6ty, Project No. 24.264, Drawing No., Cp01, Rev-, 10.04.25).
Sewer and water services must be provided in accordance with TasWater's Submission to Planning Authority Notice and conditions (reference number TWDA 2025/00579-NMC) - Attached at Appendix A, excluding condition 2 and 3.
The final plan of subdivision must show a 12m wide easement (6m either side of the centreline) over the overhead high voltage (22kV) feeders on the subject site.
*permit conditions modified by the decision of the Tasmanian Planning Commission dated 6 March 2026
[1] See Western Australian Planning Commission v Temwood Holding Pty Ltd [2004] HCA 63 at 57 and 60