Taraschi v Jessop Constructions Pty Limited
[2024] NSWCATCD 37
At a glance
Source factsCourt
NCAT Consumer and Commercial
Decision date
2023-10-05
Before
Mr J
Source
Original judgment source is linked above.
Judgment (12 paragraphs)
REASONS FOR DECISION
- In these proceedings the respondent carried out residential building work at a property in Caringbah South. The property was sold to the applicant soon after the final occupation certificate was issued. Despite not being in a contractual relationship with the respondent, the applicant has a cause of action against it pursuant to s18D of the Home Building Act 1989 ('HBA').
- These proceedings arise primarily because of the collapse of a retaining wall at the property. The applicant originally claimed damages of $220,076.86 against the respondent which have been or will be sustained in the rectification of the retaining wall and other allegedly defective work.
- The parties accept that the Tribunal has the jurisdiction under the HBA to hear and determine the applicant's claim.
- In these Reasons I will refer to the applicant as the 'owner' and to the respondent as the 'builder',
- The proceedings were heard on 5 October 2023. At the hearing the evidence was: 1. Exhibit A, Tender Bundle of Documents; and 2. Exhibit B, Joint Memorandum of Conclave.
- The parties commissioned a number of expert reports. Expert evidence was provided on behalf of the owner by Mr A Cordeschi, an engineer in a report dated 25 April 2022, Mr J Ovidi, a building consultant in reports dated 27 May and 17 August 2023 and Mr L. Tram an engineer in reports dated 24 May and 18 August 2023. Mr Holbrook, an engineer provided a report dated 26 July 2023 on behalf of the builder. There was no challenge to the expertise of any of these witnesses. I accept them all as appropriately qualified witnesses able to give opinion evidence in the Tribunal.
- Mr Holbrook was not present at the hearing for cross examination. Mr Tran was present and was cross examined.
- The Joint Memorandum of Conclave ('JMC') which is exhibit B was prepared by Mr Tram for the owner and Mr Holbrook for the builder. It was based on Mr Holbrook's report dated 26 July 2023 and Mr Tram's Supplementary report dated 18 August 2023 which was in response to Mr Holbrook's report. Reference is also made to the builder's director's document of 27 July 2023 which is stated to be titled 'Response to expert report, Lucas Tran'. There is no document that I am aware of that is in evidence and which has that title. That document was filed in the Tribunal by the builder, although it was not included in the trial bundle, exhibit A. Nonetheless, I will have regard to it in accordance with s38(6)(a) of the Civil and Administrative Tribunal Act 2013.