9 There is no evidence of the cost of designing the sprinkler system apart from oral evidence of Ms Greaves that the Respondent spent $10,000 several years ago for a design, now out of date. The cost of installing the sprinkler system is estimated at $125,000 by an independent consultant who gave evidence before Roseth C. That may not include all necessary work such as the erection of scaffolding, according to Ms Greaves in submissions from the bar table. She submits the reason the work has not been done is because of lack of money. Ms Greave's affidavit at par 12 states that at the recent AGM of the Respondent in December 2008 it was resolved to double levies from April 2009. This will raise about $50,000 per year. She also advised orally that a special levy is to be imposed in the quarter after April 2009 but the amount has not been fixed. A special levy will impose severe hardship on more than half of owners, many of whom are on fixed incomes. The Respondent is also investigating the sale of common property to raise funds. It is hoped $80,000 will be raised in this way during the year. The timetable proposed by the Respondent in par 13 of her affidavit is that all works will be completed by 1 December 2009 and the Court is asked to order accordingly. To order the work to be done earlier will cause financial hardship to the Respondent.
Council's submissions
10 The Respondent has failed for a considerable period to comply with necessary measures in a fire safety order made by the Court which had to be fully complied with by 10 July 2008. According to the affidavit of Ms Greaves the Respondent does not now dispute that the order should be complied with although the correspondence attached to that affidavit sent during 2008 suggests that the Respondent was reluctant to do the work and has been intransigent. The Respondent has chosen to prioritise doing the shoring up work before complying with the fire safety conditions in the orders. There are sufficient funds to do the work required by the Court's fire safety order and a short time frame to do this should be allowed. 10 March 2009 for stage 1 and 10 May for stage 2 is proposed.