[2003] VSCA 83
Court of Appeal (Vic)
2003-06-25
ORMISTON and BUCHANAN, JJ.A. and WARREN, A.J.A.
Original judgment source is linked above.
[ 2003] VSCA 83
Town and Country Planning - Permit Application - Exemptions from notice - Exemptions from review - Nature of application for permit - Requirements of application for permit - Combination of use and development in single application.
Planning and Environment Act 1987 - and (kd), (1), (4), (5) and (6), (1)(a)(i) and (3), and .
Melbourne Planning Scheme - Capital City Zone - Design and Development Overlays - Clauses 37.04, 43.01 and 43.02.
"Demolition of existing 3 and 4 storey buildings and basement car parking, refurbishment and extension (including 5 levels above the top level) of the existing 9 storey Mayfair Building, and construction of a new 23 storey apartment (and some office) tower building and 2-3 storey loft style apartments above a ground level podium, for retail (including through block arcade), residential and commercial office uses together with dedicated 6 level basement car parking and loading facilities."
"82. Appeals where objectors (1) An objector may apply to the Tribunal for review of a decision of the responsible authority to grant a permit. (2) A planning scheme may set out classes of applications for permits the decisions on which are exempted from sub-section (1). (3) If a planning scheme exempts a decision of an application for a permit from sub-section (1), an application for review cannot be made under that sub-section in respect of that decision."
"Exemption from notice and appeal An application to construct a building or construct or carry out works for a use in S.1 of Clause 37.04-1 is exempt from the notice requirements of S.52(1)(a), (b) and (d), the decision requirements of S.64(1), (2) and (3) and the review rights of S.82(1) of the Act."[7]
"Exemption from notice and appeal An application to construct a building or construct or carry out works is exempt from the notice requirements of S.52(1)(a), (b) and (d), the decision requirements of S.64(1), (2) and (3) and the review rights of S.82(1) of the Act."[9]
[1] See Clause 37.04 - 4 (Capital City Zone), Schedule 1, Clause 2.
[3] Clause 37.04 - 2 (Capital City Zone), Schedule 1, Clause 1, Section 2.
[4] Clause 43.01 - 1 (Heritage Overlay).
[5] Clause 43.02 (Design and Development Overlays), Schedules 1, 2, 3 and 4.
[6] As provided by ss.6(2)(kc) and (kd), 52(4), (5) and (6) and 82(2) of the Planning and Environment Act.
[7] The heading to the exemption adopts the expression "appeal", however, the Planning and Environment Act uses the term "review" as does the wording of the exemption.
[8] See Clause 43.02 Design and Development Overlay, Schedule 2 Height Controls - Capital City Zone, Clause 2.
[9] The heading to the exemption adopts the expression "appeal", however, the Planning and Environment Act uses the term "review" as does the wording of the exemption.
[10] Under Clause 37.04-4 (Capital City Zone), Schedule 1, Clause 2.
[11] Under Clause 43.02 (Design and Development Overlays).
[12] Under Clause 43.01-1 (Heritage Overlay).
[13] Under Clause 37.04-4 (Capital City Zone), Schedule 1, Clause 2.
[14] Under Clause 37.04-2 (Capital City Zone), Schedule 1, Clause 1, Section 2.
[17] See ss.60 and 84B of the Planning and Environment Act and Clause 65 of the Melbourne Planning Scheme. The matters concerning objections are described in paras. [8] and [9] above.
[18] See ss.40(b), 42(1) and 51 of the Victorian Civil and Administrative Tribunal Act 1998; also, s.84B of the Planning and Environment Act.
Sweetvale Pty Ltd & Ors
Victorian Civil and Administrative Tribunal & Ors [2003] VSCA 83