[2025] VCAT 755
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2025-08-26
Original judgment source is linked above.
Domestic building work - first and second respondents found liable for applicant's loss and damage - assessment of damages - whether there is double recovery of applicant's loss and damage - whether damages awarded against first & second respondents should be reduced by settlement amount with other respondents - Cases considered - Boncristiano and Another v Lohmann and Others [1998] VR 82 and others.
Yarra Building Surveyor Group Pty Ltd (ACN 076 930 802)(removed from proceeding on 12 September 2023)
Robert Hartley (removed from proceeding on 12 September 2023)
Sumner v Nobes (Building and Property) [2025] VCAT 755
(a) Are there concurrent claims against the Builder and RBS?
(b) If yes, is there double recovery of loss and damage?
Are there concurrent claims against the Builder and RBS?
(a) preparing and issuing the builder permit;
(b) preparing and issuing the occupancy permit; and
(c) performing mandatory inspections of the building works, which are referred to in the occupancy permit.
(a) The RBS held itself out as possessing the skill to provide the building surveying services;
(b) The RBS assumed responsibility for conducting the building surveying services;
(c) It was reasonably foreseeable that, if the RBS failed to take reasonable care in conducting the building surveying services, the future owner of the land could suffer significant economic loss and damage due to the defective works;
(i) The future owner of the land would rely on the building surveying services having been performed with reasonable care and skill, in entering an agreement to purchase the land and in paying a significant price for the land and the building works; and
(ii) If the RBS failed to take reasonable care in conducting the building surveying services, the future owner of the land could suffer significant economic loss and damage due to defects in the building works.
...where there is a plaintiff with concurrent claims against two persons has actually recovered all or part of his loss from another, that recovery goes in diminution of the damages which will be awarded against the defendant.
A plaintiff can never, merely because his claim may lie against more than one person, recover more than the total sum due.
14. The Builders' work was defective. Consequently, by reason of these defects, the Builders breached the warranties that form part of the domestic building contract... our client is entitled to enforce those warranties against the Builders pursuant to s 9 of the Domestic Building Contracts Act 1995 (Vic).
15. The costs to rectify the Builder's defective work is substantial and presently amounts to approximately $280,028 as quantified in the expert evidence our client has adduced in this proceeding.......
21. Our client further alleges breaches on your clients' part by:
(a) issuing an occupancy permit in respect of the Builder's work, despite the existence of the defects in issue in this proceeding;
(b) failing to direct the Builders to rectify their defective works.....
22. ... had your clients performed their functions properly by bringing these defects to the Builders and former owners' attention, then these defects would have been rectified promptly pursuant to the contractual defect rectification regime.
23. ... in these circumstances, our client's loss and damage is the cost to rectify these defects, which cost our client would not be required to incur had your clients properly performed their building surveying services.
29.5 The primary relief out client claims in this proceeding is the cost to rectify the Builders' defective works.[6]
In short, when a plaintiff sues two defendants and settles with one but continues to judgment against the other, in the calculation of damages payable by the latter the plaintiff is entitled to treat the settlement sum as allocated first to any claim separate and additional to any claim that was common to the defendants, and the costs of that separate claim, and, secondly, any excess of the settlement sum necessarily referable to the common or overlapping claim is to be credited in favour of the second defendant. It will be recalled ... that the terms of settlement did not apportion the settlement sum to claim, interest or costs. Thus, there is nothing in the terms of settlement that could affect the application of these principles.
...The common law principle against double recovery, in contract, has embedded in it a requirement for apportionment in order to do justice between the parties and to ensure that there is not double recovery.
[1] Tribunal Book, pages 5 to 14 inclusive - noting the pleadings against the RBS in the Second Further Amended Points of Claim have been struck out because of the Owner's settlement with the RBS in July 2023.
[2] (1984) 27 BLR 26 at 38.
[3] Boncristiano and Another v Lohmann and Others [1998] VR 82 ('Boncristiano').
[5] Townsend v Stone Tomes & Partners (1984) 27 BLR 26 at 38.
[6] Affidavit of Elizabeth Gatt sworn 5 March 2025, paragraph 6.
[7] Boncristiano and Another v Lohmann and Others [1998] VR 82, 89-90.
[8] TCM Builders Pty Ltd v Olyvia Nikou & Anor [2013] VSC 322, [73].
[10] Townsend v Stone Toms & Partners [1998] 4 VR at 89-90.
[11] Affidavit of Imran Fatah sworn 8 May 2025, paragraph 4(b).
[12] (1984) 27 BLR 26 at 41.
[13] [2015] VSC 315, [78].
[14] [1988] 2 All ER 880, 882 ('Banque Keyser').
[16] [2009] VSC 439 at [9].
Sumner
Nobes