[2025] NSWCATCD 169
General information, not legal advice.
NCAT Consumer and Commercial
2025-10-23
Original judgment source is linked above.
Akratos v Papadopoulos [2016] NSWCATAP 139
Blessed Sydney Constructions Pty Ltd v Vasudevan [2018] NSWCATAP 98
Johnson v Dibbin; Gatsby v Gatsby [2018] NSWCATAP 45
Mania v NSW Land and Housing Corporation [2022] NSWCATAP 376
Precise Builders (NSW) Pty Ltd v Jones & Krel [2018] NSWCATAP 112
Latoudis v Casey [1990] HCA 59; [1990] 170 CLR 534
Oshlack v Richmond River Council [1998] HCA 11
The Builder's Non-Compliance with the Work Order of 13 June 2024
(1) The Respondent must complete the Rectification Works within 6 weeks. The said period for completion of the Rectification Works is to commence 28 days after the date of these Orders.
(2) The Respondent will be entitled to a reasonable extension of time in the event of delays to the Rectification Works where the cause of the delay is beyond the Respondent's reasonable control. The Respondent must take all reasonable steps to minimise any delay to the Rectification Works. Any claims for extensions of time must be notified in writing to the Applicants within 7 days and any dispute as to extensions to be determined by the Inspector.
The Legislative Framework for the Owners' Renewal of the Proceeding
8 Renewal of proceedings in respect of certain Division decisions
(1) If the Tribunal makes an order in exercise of a Division function in proceedings, the Tribunal may, when the order is made or later, give leave to the person in whose favour the order is made to renew the proceedings if the order is not complied with within the period specified by the Tribunal.
(2) If an order has not been complied with within the period specified by the Tribunal, the person in whose favour the order was made may renew the proceedings to which the order relates by lodging a notice with the Tribunal, within 12 months after the end of the period, stating that the order has not been complied with.
(3) The provisions of this Act apply to a notice lodged in accordance with subclause (2) as if the notice were a new application made in accordance with this Act.
(4) When proceedings have been renewed in accordance with this clause, the Tribunal:
(a) may make any other appropriate order under this Act or enabling legislation as it could have made when the matter was originally determined, or
(b) may refuse to make such an order.
(5) This clause does not apply if:
(a) the operation of an order has been suspended, or
(b) the order is or has been the subject of an internal appeal.
(1) (1) the order is "other" than the order originally made,
(2) (2) the order is "appropriate",
(3) (3) the order is one that the Tribunal "may make ... under [the NCAT] Act or enabling legislation",
(4) (4) the order is one "as [the Tribunal] could have made when the matter was originally determined".
(i) The time for completion for completion of the 'Rectification Works' as that phrase is defined in [194(1)] of the Primary Decision, is to commence 28 days after the date of orders made in the Renewal of the proceeding, and
(ii) The requirement that the Builder will maintain a valid contractor's licence in accordance with the requirements of the HB Act for the duration of the Rectification Works (see 'Licensing Requirement' in Annexure A of the Primary Decision), be removed.
(a) The Owners are left with a dwelling where rectification works ought to have been completed by 22 August of last year and with effectively no works being carried out almost a year later,
(b) The Builder's explanation for the delay is inadequate in circumstances where:
(c) The ailment of Ms Ma of the proposed remedial builder which apparently affected her during late July and August 2024 does not provide an adequate explanation for the Builder's failure to comply with the work order in the 10 weeks afforded to it to do so,
(d) The Builder did not ensure that the remedial builder commenced any substantive rectification works in the 10 weeks afforded to it under the work order,
(e) The Builder allowed its own licence to lapse in breach of the express terms of the work order,
(f) The Builder and the remedial builder each failed to carry out even the most basic tasks identified by Mr Xue that one would ordinarily expect a builder to carry out when faced with a work order for remedial/rectification works, e.g., becoming familiar with the site,
(g) The proposed contract with the remedial builder does not comply with the requirements of Part 2 Division 1 of the HB Act,
(h) Notwithstanding that the work order was made 16 months ago, there is no evidence that the Builder has signed a binding contract with the proposed remedial builder, or that the proposed remedial builder has obtained insurance under Part 6 of the HB Act,
(i) There is no clear evidence that the Builder has the capability to pay the proposed remedial builder to the completion of the rectification works,
(j) A further work order is inconsistent with the Tribunal's guiding principle (NCAT Act, s 36(1)) in that it will inevitably lead the parties into further dispute if it is not complied with, such that it is only an order to pay money on the Renewal which will resolve the parties' disputes without the risk of further litigation.
36. Further, in so far as a date change is required, there is adequate provision to address such a need by s 41 of the NCAT Act. This section gives the Tribunal power to extend time. Also, in respect of residential tenancy proceedings, s188 of the RT Act may permit variation of the December orders.
37.Otherwise, enforcement in connection with a work order is usually achieved by making a suitable award for compensation, where such relief is available. Such an award permits the person in whose favour an order has been made to engage and pay for others to perform the required obligation sought to be enforced.
38. In making these observations, we leave for separate consideration whether a different work order could be made, for example, in circumstances where work done under the original order was defective and itself required to be rectified.
39. Otherwise, a party in whose favour an order has been made by the Tribunal must look to other means of enforcement provided in the NCAT Act or the relevant enabling legislation. The fact these other means of enforcement may be more complex is not a basis for interpreting Sch 4 cl 8 in a manner that permits other orders to be made that are not properly seen as a means of enforcing or ensuring compliance with the original orders.
(1) The application of the respondent, Winning Builders Pty Ltd (Builder) for a further work order, is refused.
(2) The application of the applicants, Jian Yu Su and Bao Ling Zhao (Owners) pursuant to Clause 8 of Schedule 4 of the Civil and Administrative Tribunal Act 2013 NSW for an order to pay money in substitution for the work order made on 13 June 2024, is granted.
(3) Order that the Builder is to pay the Owners $284,475.66 within 28 days of the date of these orders.
(4) Order that the Builder is to pay the Owners' costs of and incidental to the Renewal of the proceeding, on the ordinary basis, as agreed or as assessed.
(5) Order 4 is suspended, and the following orders take effect if any party seeks costs orders different to order 4 (an alternative costs order).
(6) The party seeking an alternative costs order (the costs applicant) is to file and serve its costs application and a brief submission (no more than 3 A4 size pages) in support of the application within 14 days of the publication of these orders.
(7) The costs respondent(s) is/are to file and serve any submissions (no more than 3 A4 size pages) in response to the costs' application within 14 days thereafter.
(8) The costs' applicant is to file and serve any submissions in reply (no more than 2 A4 size pages) within seven days thereafter.
(9) The parties' submissions on costs are to address whether the Tribunal should make an order under s 50(2) of the Civil and Administrative Tribunal Act 2013 NSW dispensing with a hearing as to costs, such that the issues in dispute as to costs are to be determined on the basis of the papers lodged with the Tribunal by the parties in accordance with these orders and directions.
(10) If more than one party applies for an alternative costs order, the parties are to file an indexed and paginated costs bundle at the end of the submission period.
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
Su
Winning Builders Pty Ltd