Steven Mace v Christopher John McPherson t/as CMC Building Works
[2017] NSWCATAP 8
At a glance
Source factsCourt
NCAT Appeal Panel
Decision date
2016-11-16
Source
Original judgment source is linked above.
Judgment (11 paragraphs)
Solicitors: GSG Legal (Appellant) Tiernan Lawyers (Respondent) File Number(s): AP 16/39190 Decision under appeal Court or tribunal: Civil and Administrative Tribunal Jurisdiction: Consumer and Commercial Division Date of Decision: 02 August 2016 Before: N Vrabac, Senior Member File Number(s): HB 15/53637
Reasons for decision
- In this matter the Appellant appeals from orders made on 2 August 2016 by which the Tribunal dismissed a claim by the Appellant for $14,229.27 for the rebuilding of a masonry wall which had been constructed on top of an existing masonry retaining wall during the course of the completion of construction works to an incomplete dwelling upon the Appellant's land. The claim had been referred to as Item 2 in the proceedings before the Tribunal and in earlier proceedings.
- The orders made included an order that the Respondent was to pay to the Appellant $18,427.44 on or before 26 August 2016. This amount was for claims which had been the subject of findings in earlier proceedings and which were unrelated to the Appeal concerning Item 2.