[2005] FCA 1808
Federal Court of Australia
2005-12-16
Emmett J
Original judgment source is linked above.
REASONS FOR JUDGMENT INTRODUCTION THE ISSUES WITNESSES THE CONSIGNMENTS IN QUESTION THE ANKERGRACHT CONSIGNMENT THE ARCHANGELGRACHT CONSIGNMENT THE MECHANISM OF THE DAMAGE CONDENSATION TIMING OF CONDENSATION Prior To Loading Immediately After Loading During The Voyage EXTERNAL WETTING SIGNIFICANCE OF THE CAPE DARBY AND the CHANGE OF PAPER RESPONSIBILITY FOR THE DAMAGE TO THE COILS DEFAULT OF THE CARRIERS Seaworthiness Proper And Careful Handling And Care DEFAULT OF THE SHIPPER Inherent Vice Act Of Shipper Insufficiency Of Packaging CONCLUSION AS TO RESPONSIBILITY MEASURE OF DAMAGES CONCLUSION
INTRODUCTION 1 These two proceedings are concerned with responsibility for corrosion damage occasioned to coils of sheet steel in the course of their carriage by sea from Japan to Australia. The second plaintiff, Tsuda Corporation ('Tsuda'), was the shipper of the coils and the first plaintiff, Stemcor Australasia Pty Ltd ('Stemcor'), was the consignee of the coils. There were two voyages in question. The first voyage involved the M.V. Ankergracht 91262 and the second voyage involved the M.V. Archangelgracht 91273. The defendants in the proceedings are C.V. Scheepvaartonderneming Ankergracht ('Ankergracht') and CV Scheepvaartonderming Archangelgracht ('Archangelgracht') (together 'the Carriers'), who were respectively the owners of the two vessels and had responsibility as carriers under bills of lading issued in respect of the coils. 2 There is no dispute that the damage occurred. The essence of the dispute is whether the damage occurred because of insufficiency of packing of the steel coils or because of the failure by the Carriers to exercise due diligence to make their vessels seaworthy and to carry, keep and care for the coils properly and carefully. 3 There is no dispute that Stemcor was the holder in due course of relevant bills of lading and, accordingly, Stemcor is an appropriate plaintiff. There is a dispute as to the measure of damages to which Stemcor is entitled if it succeeds in establishing that the Carriers were in breach of their obligations. While there are two separate voyages involved, very similar factual issues arise in relation to each. 4 The two proceedings were first fixed for hearing in early 2005, together with a third proceeding against another, unrelated, carrier involving similar allegations. By agreement of the parties, evidence in each proceeding was treated as evidence in the other. In the course of the hearing, which commenced on 4 April 2005, Stemcor sought to rely on a claim that the Carriers had failed to exercise due diligence to make their vessels seaworthy by reason of failure to install dehumidifying systems in the holds. The hearing was adjourned on 13 April 2005 to enable Stemcor to adduce final evidence as to that question and to give the Carriers the opportunity to respond to the evidence. 5 The hearing was resumed on 29 June 2005 and completed, with oral argument, on 30 June 2005. In the course of final oral argument, Ankergracht sought leave to amend its defence to allege that the coils were subject to inherent vice. The amendment did not raise any new factual issue beyond those that were raised by the existing pleadings and no further evidence was called for. Reliance upon the allegation involved no more than a different characterisation of the existing factual matters. 6 There had been previous written submissions and oral submissions, both by way of opening and after the evidence completed. The hearings had been further complicated by reason of the fact of the third proceeding. However, after the adjournment, that proceeding was settled, although substantial parts of the evidence adduced in relation to that proceeding was admitted in the present two proceedings. Because of the adjournment and the complexity of the issues, the parties were requested to prepare final written submissions that were intended to do no more than bring together in one place the contentions of the parties. 7 On 22 July 2005, counsel for Stemcor and Tsuda provided full and complete written submissions in accordance with my request. However, the Carriers' response, including Ankergracht's submissions in support of its application to amend its defence, was not received until 16 September 2005. Counsel for Stemcor then answered the Carriers written submissions on 14 October 2005. On 19 October 2005, Stemcor indicated that it did not oppose the amendment to Ankergracht's defence. Accordingly, leave to amend was then granted.
THE ISSUES 8 It is common ground that the steel coils were damaged as a result of corrosion resulting from contact with water before or during the course of the voyages. The steel coils in question were particularly prone to corrosion from contact with water. There is a dispute as to the mechanism whereby water entered the packaging around the coils. The essential question, however, is whether the Carriers were entitled to assume that the packaging of the steel coils was such that water in any form could not penetrate the packaging, or whether Tsuda and Stemcor were entitled to assume that there would not be sufficient water in any form, either as liquid or vapour, in the holds of the vessels for condensation to occur on the coils. That, in turn, raises questions as to whether Tsuda adopted a method of packaging the steel coils that was usual in the industry and as to the usual practice of carriers of steel coils of the nature of the coils in question. 9 There are several juridical bases upon which Stemcor claims damages from the Carriers, namely, contract, bailment and negligence. However, it is common ground that the substantive factual and legal content of each basis is the same. It is common ground that the relationship between the parties was governed by the provisions of the amended Hague Rules, as defined in s 7 of the Carriage of Goods by Sea Act 1991 (Cth) ('the amended Hague Rules'). Stemcor relies on breach by the Carriers of the amended Hague Rules. The Carriers, in turn, rely on exempting provisions of the amended Hague Rules. 10 Article 1 of the amended Hague Rules defines 'carrier' as including the owner who enters into a contract of carriage with a shipper. Article 3 rule 1 relevantly provides that a carrier is bound, before and at the beginning of the voyage, to exercise due diligence to: (a) make the ship seaworthy; (b) properly man, equip and supply the ship; (c) make the holds of the ship in which goods are carried, fit and safe for their reception, carriage and preservation. Article 3 rule 2 provides that, subject to the provisions of Article 4, the carrier must properly and carefully, load, handle, stow, carry, keep, care for and discharge the goods carried. 11 Article 4 rule 2 of the amended Hague Rules relevantly provides that neither the carrier nor the ship shall be responsible for loss or damage arising or resulting from: '(i) act or omission of the shipper or owner of the goods, his agent or representative. … (m) …any … loss or damage arising from inherent defect, quality or vice of the goods. (n) insufficiency of packing. …' 12 Article 4 rule 5(b) of the amended Hague Rules provides that the total amount recoverable is to be calculated by reference to the value of the goods at the place and time at which the goods are discharged from the ship in accordance with the contract. The value of the goods is to be fixed according to the commodity exchange price, or, if there be no such price, according to the current market price, or if there be no commodity exchange price or current market price, by reference to the normal value of goods of the same kind and quality.
WITNESSES 13 There was no dispute as to the primary facts relevant for the resolution of the proceedings. The issues are rather as to inferences to be drawn from those primary facts. The disputed inferences concern the circumstances in which the coils came into contact with water, either in the form of a liquid or a vapour. 14 Professor Robert Jones is Adjunct Professor in the Department of Chemistry Materials and Forensic Science within the Faculty of Science of the University of Technology, Sydney. He has had in excess of thirty years experience in investigating the many facets of metallic corrosion processes. In particular, he has investigated and reported on in excess of sixty examples of corrosion of metal products in marine transit to Australia, including coated steel coil of the type in question in these proceedings. Professor Jones has also had twelve months experience working in a steel mill in Sandvik, which produces steel coils. He has been involved in consulting work for the world's largest manufacturer of specialist packaging paper. Professor Jones has been involved in the investigation of marine insurance claims, including claims of corroded steel coils, and has seen many hundreds of wrapped coils, as well as seeing coils being unwrapped. He has observed the wrapping method of approximately a dozen different suppliers and has carried out many physical and chemical examinations on paper used in the wrapping of steel coils, including determining the existence of inhibiters and moisture. 15 Dr Michael Bellstedt holds a bachelors degree in mechanical engineering, a masters degree in refrigeration and air conditioning and a doctorate in engineering, specialising in heat transfer. He is a member of several professional associations in the general field of engineering and in the specific field of refrigeration. Dr Bellstedt maintains an active strategy of professional development in his field. He has published several papers in Australian and German journals and trade magazines, and has presented papers at conferences, seminars and industry meetings in Australia and overseas. He has also spent over ten years in industrial refrigeration contracting as a design, contracts and projects engineer. He has had academic and practical experience in general mechanical engineering and has expertise in thermal and process engineering, including the disciplines of heat transfer, fluid mechanics, thermodynamics, refrigeration and air conditioning. 16 Captain Iain Frost is a surveyor and has carried out many marine hull and cargo casualty surveys on behalf of underwriters world wide. He has had extensive marine and survey experience over more than forty years. His survey experience extends to all cargoes insured under marine policies including commodities, materials (including steel), produce, machinery and electronic equipment, transported by sea, air, road and rail. 17 Captain David Pyett, a master mariner and marine surveyor, has been engaged in maritime consulting and surveying, including survey of damaged cargo on board vessels for many years and has conducted countless marine surveys including cargo surveys. He specialises in the survey of vessels carrying general cargoes, machinery and steel products including steel coils of all types. 18 I have no doubt that all witnesses gave evidence truthfully and no witness consciously sought to mislead the court. To the extent that there was any conflict, I have endeavoured to resolve the conflict by reference to the cogency of the reasoning of the witnesses.
THE CONSIGNMENTS IN QUESTION 19 The Ankergracht and the Archangelgracht are sister ships. Each is an 'A' type vessel of 7,949 GRT and 129.6 metres LOA. Each vessel has a single hold with a tween deck. The hold is served by three hatches with end folding type hatch covers. The two vessels are part of the fleet operated by BV Spliethoff's Bevrachtingskantoor ('Spliethoff'). Stemcor had begun to use Spliethoff's vessels in 2001 and entered into an affreightment contract for one year. That contract required Stemcor to use Spliethoff's vessels to ship steel unless there was no vessel available at the time. 20 Mr David Mahoney, the shipping manager of Stemcor responsible for the selection of the shipping line used to carry the cargoes in question, was familiar with the vessels. He knew them as vessels that were operated as general cargo ships carrying a wide variety of steel cargo. Mr Mahoney was aware that the vessels were carrying steel cargoes from other shippers for other consignees. He was also aware that the cargoes included plate steel, hot rolled steel, cold rolled steel, machinery and motor vehicles. He was also aware of the nature of the holds of the vessels. 21 The relevant shipments were amongst the first shipments to Australia, of coils of the type in question, during the Northern Hemisphere winter. The coils were produced at Tsuda's Taiyo Steel Mill in Fumabashi, Sakae Canal, Japan. They were imported by Stemcor for the purpose of resale to Australian Colour Coaters Operations Pty Limited ('ACC'). 22 ACC's business includes manufacturing steel coil into pre-painted steel products. ACC produces two basic types of metallic coated painted products. One is zinc coated, which is referred to as galvanised, and the other is zinc aluminium coated, which is referred to as aluzinc coated. Some of the coils in question were galvanised and some were aluzinc coated. ACC required the coils ordered from Stemcor to be unchromated but oiled. A chromate coating, depending upon the coating used and the coating weight, can be detrimental to paint adhesion as some chromate coating becomes insoluble and cannot be cleaned off before painting by conventional treatment methods. Hence ACC's specification for oiling only and no chromate coating. 23 If the surface of freshly galvanised or aluzinc coated steel is allowed to come into contact with water, either as a result of direct wetting or by condensation of vapour, corrosion in the form of white rust will occur. If the water evaporates quickly, the corrosion will generally not be severe. However, if the water remains in contact with the surface at high humidities and under poorly ventilated conditions, sever corrosion may occur. Such corrosion occurs rapidly and can be observed within a few hours of the wetting taking place. 24 Such coils cease to be highly susceptible to corrosion from contact with water when a protective layer of basic zinc carbonate forms on the steel. That layer forms when the zinc coating reacts with the oxygen in dry air to form zinc oxide. The oxide that forms is porous and is formed away from the surface of the steel. The oxide then reacts with moisture and carbon dioxide in the air to form a layer of basic zinc carbonate. Once that layer has formed it acts as a sacrificial coating and the steel is resistant to corrosion. 25 Before that sacrificial coating forms, coils of the type in question may be temporarily protected from corrosion in two ways. One way is to apply a light oil coating. Another way is to apply a chromate coating to the steel. Chromate coating entails immersion of the metal in a solution of potassium dichromate, or some other suitable chemical. That process is known as passivation: passivators are inhibitors of corrosion. Natural passivation is where the oxide film referred to above becomes sufficiently developed to stifle further activity of the electrochemical process associated with corrosion. 26 The coils in question were lightly oiled but had no chromate coating. However, the descriptions of the coils in the bills of lading, mates' receipts and shipping orders do not indicate that they were being shipped unchromated and un-passivated. There was no evidence that the Carriers or Spliethoff were informed of ACC's requirement that the coils be unchromated. The Carriers' knowledge of such matters may be relevant to the question of whether they had exercised due diligence in the performance of their obligations under the contracts of carriage. For example, at the time of booking the consignments for shipping, no request was made for a vessel that had either a dehumidifier or a heater fitted in the hold. 27 The process of galvanising or aluzinc coating takes about one hour. It is the practice at the Taiyo mill to complete the wrapping of such coils within one hour after the coils leave the processing line. Accordingly, each of the coils in question was wrapped on the same day that it was produced. The area where the coils were stored is under cover and approximately 8 metres back from an opening in the wall. The conditions at the Taiyo mill are such that the coils were likely to have been kept dry while stored in that location. 28 The practice is for coils to be transported by barge from the Taiyo mill to the loading wharf. Coils are loaded on the barge as soon as the barge arrives at the Taiyo mill and loading takes approximately four hours. The coils are unloaded from the barge at the wharf by stevedores. The coils are covered during their transfer from the Taiyo mill to the wharf and, accordingly, are well protected from rain at that stage. The barge contractor takes instructions from the stevedores regarding the uncovering of the barges for the purposes of loading. 29 As a general rule, cold rolled steel coils, including coils of the nature of the coils in question, are packaged with an inner soft wrapping, which is usually paper, and an outer metal wrapping, including end caps and corner protectors and is then steel strapped. The steel is coiled around a hollow core. The coil is first wrapped in a single sheet of Kraft paper, lined with an adhering film of plastic, the overlaps of which are not usually sealed. Kraft paper is strong, smooth brown paper made from unbleached soda pulp or wood pulp. After the coil is wrapped in Kraft paper, it is then fitted with an outer metal wrapper composed of waste steel sheets. Thereafter, flat metal strapping bands are applied around the circumference of the coil and transversely through the centre core. 30 In some cases, a metal disk is fitted on the end, with protected rings in the form of angle irons surrounding the inner and outer circumference edges. The purpose of that arrangement is twofold. The first is to offer protection to the edges of the coil. The other is to fit a plain disk on the end, not specifically manufactured to fit one size of coil. Any shortage of diameter in the end of disk is taken care of by the overlap of the protective rings. Alternatively, the end disk is fabricated to fit the end of a specific size of coil and cannot be used for any coil of another diameter. 31 The coils in question were packaged in a manner that is consistent with the standard practice for the packaging of steel of the nature of the coils in question, as described above. The standard method of wrapping is shown in the diagrams set out in Schedule 1 to these reasons, which are taken from A Sparks, Steel Carriage by Sea, LLP Professional Publishing, London, 2003. The packaging of the coils included a standard symbol and note requiring that they be kept dry and that they be handled with care, as shown in Schedule 2 to these reasons. The photographs in Schedule 2 also demonstrate that the packaging of the coils was in accordance with the practice described above.
THE ANKERGRACHT CONSIGNMENT 32 The consignment shipped on the Ankergracht consisted of 153 coils which were produced as follows:
THE ARCHANGELGRACHT CONSIGNMENT 38 The consignment shipped on the Archangelgracht consisted of 124 coils, which were produced as follows:
THE MECHANISM OF THE DAMAGE 45 Stemcor contends that the corrosion on the coils occurred solely as a result of condensation in the course of the voyages. It cannot seriously be disputed that some condensation occurred during the course of the voyages: as will become clear, the conditions for condensation did not exist until after the vessels left Yokohama. It is desirable, first, to say something about the physical mechanism involved in the formation of condensate. Evidence on that question was given, substantially without objection, by Dr Bellstedt.
CONDENSATION 46 Ambient air is a mixture of several gases, predominantly nitrogen (79 per cent), oxygen (18 per cent) and argon (1 per cent), with the remaining proportion made up of a variety of other gases, including water vapour. The exact composition of air can vary significantly and gases such as oxygen, nitrogen and carbon dioxide can be removed from and added to the air by various means. There are no upper or lower limits to the range within which these gas concentrations can be changed at the normal range of ambient temperatures, namely, from minus 50şC to plus 50şC. 47 However, there are limits to the range of concentrations of water vapour in air. Concentration of water in the air is governed by Dalton's law and the relationship between water temperature and vapour pressure. Thus, the moisture content of air varies within the following constraints at all times:
TIMING OF CONDENSATION 54 It is common ground that at least some of the corrosion damage to the coils in question was the result of condensation during the voyage. However, the Carriers contend that there were in fact three sources of wetting that caused damage as follows:
Prior To Loading 56 The coils were processed whilst warm, such that, on completion of processing, the temperature of the steel was high and well above the ambient air temperature. On completion of the processing, the coils were stored in ambient air until they were loaded onto barges and transported to the wharf for loading. During that period, the coils would steadily cool from the high temperature to close to the current ambient temperature. The coil surface temperature would be well above the air dew point temperature and, therefore, no condensation could occur. 57 After several days or longer, the coil temperature will begin to approach the air temperature and at constant ambient temperatures, eventually equilibrate with the air temperature. Under those conditions, the coil surface temperature will remain well above the air dew point temperature. If, after equilibration of the coil temperature, a significant increase in the ambient temperature and humidity should occur, due to a sudden weather change, the surface temperature of the coils could be below the changed air dew point temperature. Condensation could then occur until the coil temperature has equilibrated to the new ambient temperature. 58 Dr Bellstedt concluded that conditions were not conducive to the formation of condensation onto the coils prior to loading on board the vessel and it is more probable than not that any condensation occurred after loading of the coils.
Immediately After Loading 59 During the loading process, the hold conditions would become essentially equivalent to the ambient conditions, such that condensate formation during loading would not be likely. If the hold is sealed, but sources of moisture, such as open water, exist within the hold, the hold air is likely to absorb moisture from the water so that the dew point of the hold air would rise steadily. Under those conditions, the dew point would be likely to rise to a level above the surface temperature of the coils. Condensation could therefore occur within days of closing the hold. 60 If the hold is sealed but there are sources of heat within the hold, the air temperature within the hold will rise, but with no change to moisture levels. There would therefore be no change to the dew point temperature of the air. Accordingly, no condensate would be likely to develop on the coils in those conditions. 61 Dr Bellstedt concluded, therefore, that it was unlikely that condensation on the coils could have taken place immediately after loading before commencement of the sea voyage.
During The Voyage 62 During the subsequent trip from Japan to Australia, the condition of the air within the hold and the temperature of the steel coils would be likely to change. The reason for the change would be, first, ingress of air into the hold from the outside, either through intentional ventilation or leakage. That air could be at different temperatures and contain different levels of moisture from the air in the hold. Secondly, there could be a change by reason of heat transmission into the hold through the ship's structure. Heat could enter the hold from the outside warmer ambient air or sea through the separating hull and hold layers. Such heat flow would depend on the characteristics of the ship's design as well as the temperature outside the hold as compared with the temperature inside the hold. 63 Air entering the hold from outside would mix with the air in the hold and change its temperature and moisture content. As indicated above, air ingress into a sealed hold could potentially occur by way of the natural ventilation system, if it were opened either intentionally or accidentally. Natural ventilation could take place with or without the assistance of a fan. Alternatively, air ingress could occur through leakage of air into the hold by way of defective seals or open manhole covers. 64 Ingress of air with a higher moisture content than the hold air will increase the likelihood of condensation in the hold. Ingress of air with a lower moisture content than the hold air will decrease the likelihood of condensation. Ingress of heat into the hold will decrease the likelihood of condensation. Dr Bellstedt concluded that it is possible for condensation to occur during the voyage if ingress of moist air into the hold took place and insufficient heat entered the hold to increase the steel temperature to match the higher hold air dew point temperature. 65 Data recorded on the Ankergracht included comprehensive ambient dry bulb and seawater temperatures and barometric pressures at four hourly intervals throughout the voyage. In addition, measured and calculated data for ambient conditions and conditions within the lower hold and tween deck of the vessel are available. Dr Bellstedt concluded that the measured hold dew point levels exceeded the coil temperatures for most of the voyage, indicating that condensation on the steel coils would almost certainly have occurred. 66 The data kept in respect of the Archangelgracht included comprehensive ambient dry bulb and seawater temperatures and barometric pressures at four hourly intervals throughout the voyage. The same measured and calculated data for ambient conditions and conditions within the lower deck and tween deck were also available. Dr Bellstedt concluded that, in the case of the Archangelgracht, measured hold dew point levels exceeded the coil temperatures for most of the voyage. In those circumstances, he concluded that condensation would almost certainly have occurred. 67 In the light of Dr Bellstedt's evidence, I consider that it is more likely than not, that condensation occurred during the course of both voyages. That condensation led to corrosion on at least some of the damaged coils on the Ankergracht and all of the damaged coils on the Archangelgracht.
EXTERNAL WETTING 68 The Carriers say, however, that at least some, if not all, of the coils loaded onto the Ankergracht were wet prior to loading on board. They say that the water was able to find its way into the coils through the wrapping. The Carriers point to the difference in the extent of the damage to the two consignments and say that that difference gives rise to an inference that greater damage was caused to the coils on the Ankergracht than on the Archanglegracht because the former coils were loaded wet, whereas there was no evidence that coils on the Archangelgracht were loaded wet. 69 In the mates' receipts/shipping orders for the Ankergracht, coils were recorded as having been 'partly wet by rain in barge'. That endorsement related to each of the three bills of lading. A survey report of Scandinavian Underwriters Far East Agency Co Ltd dated 16 November 2001 ('the Survey Report') recorded the following in relation to each of the three bills of lading: 'Steel bands and core edge protector partly rusty, and partly wet with rain.' In addition, photographs show a barge of coils exposed and wet. While there was evidence that a tarpaulin cover on the barges was designed to prevent wetting by rain, the photographic evidence suggests they may have been wet in the barge. 70 The coils in question were received and loaded on 12 November 2001. Loading operations were halted between 1000 and 1415 hours on that day. Loading continued from 1415 hours to 1730 hours and there was no further rain on 12 November after 1415 hours or on 13 November 2001 while the Ankergracht was at Yokohama. Even if the coils were loaded prior to the stoppage at 1000 hours on 12 November 2001, there is no evidence one way or the other to indicate that loading continued while it was raining. The relevant records indicate that loading operations were stopped due to the rain between 1000 and 1415 hours on that day. That is consistent with the evidence of the master and chief officer of the Ankergracht as to their usual practice not to load during rain. Accordingly, on the balance of probabilities, it is more likely than not that the coils were not wetted in the course of loading. 71 The Carriers contend that, since corrosion could occur very rapidly and within hours of being in contact with water, it is reasonable to conclude that some damage occurred by reason of exposure to water on the barge prior to loading. That conclusion entails that rain water was able to infiltrate the external and inner wrappers in which the coils had been shipped. The Carriers say that water entered the wrapping and was trapped within the inner wrapping of the coil and up against the coil surface. 72 Professor Jones considered that the nature and distribution of the corrosion observable on the steel coils on the Archangelgracht is highly consistent with the corrosion having occurred as a result of condensation of moisture within the coils at some point, subsequent to wrapping of the coils for transit, and not as a result of external wetting. The white rust present in the core of coils and the runoff down the ends of the coils, are typical of condensation damage. It is unlikely that the white rusting was due to wetting from external sources that led to entry of water behind the end caps into the wrapped coil by percolation though the unsealed longitudinal edge of the wrapping paper. Corrosion present on the outer turns of the coils, within the core and down the end faces of the coils, as was observed, is not consistent with water entry along a single longitudinal path. 73 Every exposed surface of the coils, including the inside of the core, was wrapped in paper. Further, the wrapped inside of the coils was also protected by another sheet of galvanised steel. During transit, the coils were loaded on the vessels in a horizontal orientation, in that the axis of the coils was parallel to the deck. Professor Jones considered that that would make water ingress into the coils difficult. If extensive external wetting of a coil occurred, water uptake into the wrapped product could occur only if the unsealed longitudinal edge of the paper was lying directly along the deck. He thought that the chances of that occurring in approximately 57 per cent of the Ankergracht consignment, was remote. 74 If horizontally carried coils were exposed to extensive external wetting, that water could run down the end caps, pass beneath the core edge protectors, pass beneath the outer paper wrap and enter the coil itself. However, that is unlikely, since the core of the coil was also wrapped with waterproof paper and the core edge protectors had a firm fit on the end of the coil. If water had entered in that fashion, one would expect to see a circumferential band of white rust around the inner edge of the end caps. That pattern was present in only one case in the Ankergracht. Because the core of the coil is wrapped and taped, even if some small amount of water managed to percolate behind the core edge protector, the water would not enter the coil itself. 75 I consider that it is more likely than not that, even if the coils were wetted in the barge, no water infiltrated the external and inner wrappers prior to the loading of the coils on to the Ankergracht. While that is a possibility, there is no evidence to suggest that it is more likely than not that liquid water, present from rain while the coils were in the barge, infiltrated the packaging. The nature and distribution of the corrosion observed on the steel coils is consistent with condensation and there are other explanations as to the differences in the extent of damage in the Ankergracht and the extent of damage in the Archangelgracht. For example, the differences in timing and periods of ventilation could explain for differences in the ingress of moisture into the holds during the course of the two voyages.
SIGNIFICANCE OF THE CAPE DARBY AND the CHANGE OF PAPER 76 In December 2002, the M.V. Palmgracht carried 173 steel coils from Yokohama to Sydney. In December 2003 and January 2004, the M.V. Cape Darby carried 82 steel coils from Yokohama to Sydney. The Cape Darby is one of a fleet of vessels operated by the Project Asia Service ('PAS'). Since 2003, PAS vessels have been carrying coils of the nature in question with no incidence of corrosion. 77 The PAS vessels were fitted with humidifiers, although there is no evidence one way or the other as to whether the humidifiers were operated during the voyages. There is also evidence that the Kraft paper used for the internal wrapping of the coils on the voyages of the Ankergracht and the Archangelgracht was different from that used for the coils that were carried on the Cape Darby. Mr Paul Whitehead, the managing director of Stemcor, gave evidence concerning the circumstances of the change in wrapping paper. 78 Until June 2003, steel coils purchased by Stemcor from Tsuda that had been produced at the Taiyo mill were wrapped with a diamond shaped threaded laminated paper. Steel coils produced at the Nippon mill in Japan used a different wrapping paper. In May 2003, Mr Whitehead requested that Tsuda change the paper used at the Taiyo mill and to use the same paper as was being used at the mill operated by Nippon. From June 2003, the Taiyo mill began wrapping the coils in a polyethylene crossed paper. 79 On 30 May 2003, Mr Whitehead prepared a report dealing with the 'Coil corrosion problem'. The report relevantly said: 'We have been experiencing an ongoing problem with corrosion damage to [Tsuda] galvanised and aluzinc coils supplied to ACC Australia. The problem is most common during the peak Japanese winter months, which correspond with the peak Australian summer months. However we also see some corrosion damage to coils during the course of the year. The extent of damage on some shipments exceeds 30% of the cargo and at time [sic] up to 50% of the coils have had to be rejected as unusable by ACC. This is causing significant problems for our marine insurers who have come to believe that in some way the [Tsuda] packing is inadequate… The rusting damage caused to [Tsuda] supplied coils is a significant issue which must be addressed and resolved promptly in order for the business to be able to continue. It is also causing significant damage to [Tsuda's] reputation as quality supplier. In order to report specifically and in detail on this problem we inspected two coils one [Nippon], one [Tsuda] from a recently arrived shipment, MV Parkgracht, which loaded in Japan on 29/3/2003 and arrived in Sydney on 16/4/2003. The results of this inspection are typical of the problems seen with [Tsuda] coils which are not evident on the [Nippon] coils…' The report then sets out photographs of coils from both source and continues: 'It would therefore seem that the problem with [Tsuda] coil does not relate to the outer metal wrapping. From the above photos, it does seem that the inner paper wrapping by [Tsuda] is not effective. The inner paper wrapping used by [Nippon] does appear to be effective and can stop water, or possibly water vapour, from transmitting through to the other side. However we have also shipped a lot of [Tsuda] coils with chromte [sic] protection on board the same vessels with the same inner paper coating without any rust claims. On these occasions the paper does an effective job it would seem. In conclusion there are a number of issues we would need to address in order to try to stop this continuing problem. 1. The coils are getting wet through condensation of moisture during the voyage. This is worse during the Japanese winter season as the vessel sails into the warm tropical region. We are intending to trial another shipping line who we believe will be able to provide greater ventilation of the hold and reduce the amount of condensation. 2. The paper being used as the inner wrapper is not effective at protecting oiled coils in this environment when some moisture can be expected to ingress through the outer metal wrapping. Initial [sic] we request that [Tsuda] investigate the [Nippon] paper and urgently make a change to that paper. Although we cannot be certain that these changes will resolve our problems we are hopeful that in combination they will almost eliminate rusting on [Tsuda] coils. Samples of [Nippon] and [Tsuda] inner paper have been sent to you with this report inclduing [sic] [Nippon] paper with rusting on one side and [Tsuda] paper that has partially stuck to the coil. We look forward to your urgent comments on this issue.' 80 There is no evidence as to the addressee of the report. The report is equivocal, in that it simply draws attention to the fact that the problem of corrosion was believed to be the result of condensation and that one paper may or may not have been more effective to protect the ingress of water vapour. 81 There was no evidence of any testing of either of the papers in question to demonstrate the differences in specification or characteristics attaching to the papers or to determine their capacity to prevent the ingress of water. The fact that there was no corrosion on the coils carried by the Cape Darby is equally explicable as resulting from the use of dehumidifiers. In the circumstances, I am not persuaded that the evidence as to the Cape Darby or the change of paper assists in the resolution of the issues raised in the proceedings.
RESPONSIBILITY FOR THE DAMAGE TO THE COILS 82 Stemcor contends that each of the Carriers was in breach of its obligations under the amended Hague Rules. Stemcor says that the damage to the coils was the result of breach of rule 1 of Article 3 or rule 2 of Article 3. The Carriers, however, rely on paragraphs (i), (m) and (n) of rule 2 of Article 4 of the amended Hague Rules. That is to say, Stemcor claims that the Carriers did not exercise due diligence to make their vessels seaworthy and their holds fit for carriage of the coils or, alternatively, did not carefully and properly care for the coils during the voyages. The Carriers, for their part, say that Tsuda did not pack the coils sufficiently to prevent the ingress of water, whether in liquid or vapour form. 83 Packing capable of preventing even the most minor damage is not practical and is not expected for most commodities. By the same token, the degree of care that would have to be exercised by a carrier in order to avoid all minor damage is also not always practical or expected. There must be a balancing exercise undertaken by the Court in dealing with the question of insufficiency of packaging. Such an exercise involves finding some middle ground or rule of reason between a degree of packaging that will eliminate all possible damage on the one hand and a degree of care on the part of the carrier that will eliminate all possibility of minor damage on the other. The law will involve a compromise of the conflict between the interests of the shipper and the carrier. Neither is required to accept total responsibility.
DEFAULT OF THE CARRIERS 84 In essence, Stemcor's complaint is that the Carriers permitted water to enter the holds of the vessels and failed to have in place adequate means for either removing the water or ensuring that water vapour did not condense on the coils. Stemcor says that the Carriers should have taken steps to ensure that water could not enter the holds during loading, or during the course of the voyages. Stemcor says that water may have entered in the form of rain during loading, or on cargo that was wet prior to loading, or through inadequately sealed hatches and manhole covers, or through ventilating during the course of the voyages. Stemcor also says that, in circumstances where water could not be prevented from entering the holds, it was incumbent upon the Carriers to have installed on the vessels dehumidifying systems for removal of water, or heaters to ensure that condensation on the coils would not occur. 85 The obligation of the Carriers was to exercise due diligence to make their respective ships seaworthy and to make the holds fit and safe for the carriage of the coils. Stemcor contends that the Carriers failed in that obligation by failing to take adequate steps to ensure that condensation would not occur during the course of the voyages. That, it says, involved active measures to remove water from the holds to prevent condensation. 86 Condensation would occur during the voyages unless:
Seaworthiness 88 Article 3 rule 1 imposes an obligation on a carrier to provide a ship fit to carry the particular cargo on the particular voyage to the particular destination (Mitsui & Co Ltd v Novorossiysk Shipping Co [1991] 1 Lloyd's Rep 456 at 472). However, the obligation imposed by Article 3 rule 1 is not an absolute one. The absolute duty at common law to provide a seaworthy ship is displaced by Article 3 rule 1, which requires the carrier to exercise due diligence to provide a seaworthy ship (Papera Traders Co. Ltd. and Others v. Hyundai Merchant Marine Co. Ltd. and Another [2002] 1 Lloyd's Rep 719 at 124 (The Eurasian Dream)). In cases where damage has resulted from unseaworthiness, the burden of proving the exercise of due diligence is on the carrier. 89 Seaworthiness is to be assessed according to the voyage under consideration and there is no single standard of fitness that a vessel must meet. Seaworthiness is to be judged in the light of the conditions the vessel will encounter (Great China Metal Industries Co Ltd v Malaysian International Shipping Corporation Berhad [1998] HCA 65 at 27). Seaworthiness is relative to the nature of the ship, to the particular voyage and even to the particular stage of the voyage at which the ship is engaged. Seaworthiness must be judged by the standards and practices of the industry at the relevant time, at least so long as those standards and practices are reasonable (The Eurasian Dream at 126, 127). The vessel must be in a suitable condition and must be in a fit state, as to equipment and in all other respects, to encounter the ordinary perils of the voyage in question (Ibid at 128). 90 The voyages in question were to commence in Yokohama in winter, when it is regularly cold and rain is expected. Rain occurred during loading operations of both vessels. It took about 20 minutes to close down the hatches when rain commenced. It is reasonably likely, therefore, that some rain entered the holds during loading operations. While it would have been possible for loading operations to be deferred until after the risk of rain had passed, it may have been difficult to do so because rain was expected at the time of the year when loading occurred. Having regard to that expectation and the possibility of cargo being loaded from the wharf where it would be exposed to rain during loading, Stemcor contends that some active means should have been adopted by the Carriers to remove water before sailing, beyond merely wiping cargo where it was accessible. 91 The ambient relative humidity in Yokohama remains high during the winter months. In order to travel to Australia, the vessels had to cross the equator where they would encounter warm moist air. Accordingly, there was a high probability that conditions for condensation would be created in the hold during the course of the voyages if free water was not eliminated or if moist air was introduced into the hold in the course of the voyages. 92 Stemcor says that, in order to be capable of carrying the coils in question on the particular voyages at the particular time of year, the vessels ought to have been equipped with a dehumidification system to remove water from the holds before condensation could occur. Alternatively, it would have been possible to install heaters in the hold to increase the temperature of the cargo, on the assumption that no free water was introduced into the holds during loading operations and humid air did not leak into the holds during the course of the voyages. A vessel for use in the voyages in question at the particular time of year for the particular cargo that did not have either a dehumidification system or heaters installed was unseaworthy with regard to that voyage carrying that cargo.
Hatches 93 There is no evidence that the hatches of either vessel were defective in any way so as to render them unseaworthy or their holds not fit and safe for the reception and carriage of the coils. Nor was there evidence of any leakage of moist air into the hold of either vessel through the hatch covers. Survey reports of both vessels prior to loading recorded that the hatch covers were found to be in good condition. Survey reports at the time of discharge also recorded the hatches to be in good condition. The only basis upon which it was suggested that there was any defect in the hatch covers was the inference drawn from records showing parallel increases in temperature inside the hold and outside. 94 However, I am not persuaded on the material before me that an increase in temperature in the hold is dependent upon the ingress of air from outside. Heat passes by conduction as well as convection. One would expect that, as the vessel moves from a colder temperature to a warmer temperature, heat could pass into the hold by conduction through the structure of the vessel, as well as inevitable breathing through holds that are not defective. As the temperature of the air and water outside the vessel rises, one would ordinarily expect the temperature of the vessel and its holds to follow that rise. I am not persuaded on the balance of probabilities that any of the hatches was defective.
Heaters 95 The evidence does not establish that the use of heaters in vessels is commonplace either generally, in vessels carrying steel cargoes or in vessels carrying coils of the nature in question. There was no evidence adduced by Stemcor of any vessel in which such heaters exist or are used. Nor was there evidence identifying the availability of such heaters in the shipping industry, either temporarily or otherwise. The absence of heaters was not, of itself, a basis for concluding that the vessels were unseaworthy and the holds were unfit or that the Carriers had not used due diligence to make the vessels seaworthy and the holds fit.
Dehumidifiers 96 A carrier must demonstrate that it has exercised all reasonable skill and care to ensure that the vessel is seaworthy at the commencement of the voyage. The test to be applied is an objective one. The carrier must act in accordance with international standards and the standards of a reasonable carrier in the particular circumstances of the problem at hand. The more serious the consequences of unseaworthiness, the greater the effort that should be made to make the vessel seaworthy. 97 Dehumidification systems had been used on vessels carrying moisture sensitive cargoes for many years prior to the voyages in question. Since 2003, vessels operated by PAS have been carrying similar coils with no incidence of corrosion. As I have indicated, the Cape Darby has dehumidifiers installed. Dehumidification units are commonly installed on ships and such units were available for installation on the vessels at Yokohama at the time of the voyages in question. Neither the Ankergracht nor the Archangelgracht had any dehumidification system installed. However, the installation of dehumidification systems on either a temporary basis or a permanent basis was reasonably practicable in the circumstances for each of the Ankergracht and the Archangelgracht. 98 A number of matters would need to be attended to in arranging for the installation of dehumidifiers on the vessels as follows:
Proper And Careful Handling And Care 112 Stemcor also contends that, in breach of Article 3 rule 2, the Carriers did not properly and carefully load, handle, stow, carry, keep, care for and discharge the coils in so far as they:
DEFAULT OF THE SHIPPER 131 In their defences, the Carriers provide the same particulars in respect of their contention that the damage to the coils arose or resulted from act or omission of Tsuda, insufficiency of packaging or inherent defect, quality or vice. The particulars are as follows: 'i. The design of the coil wrapping system was such that moisture (sweat, condensation or wetting) could enter beneath the coil core and outer edge protectors. The coils were found to be wrapped with mesh reinforced, plastic clad paper sheeting. The way this had been applied involved the external wrap overlapping the coil wrap. This arrangement permitted moisture penetration beneath the core edge protectors to pass beneath the outer wrap and enter the coil itself. The coil wrapping system was inadequate in that it failed to keep the said moisture out of the coil interior. ii. The metal end caps of the coils were not large enough in diameter to ensure that moisture on the outside of the metal cap did not get onto the inner wrapper underneath the outer whirl. The design of the bore wrapper and bore collar were such as to permit any moisture in the bore to get underneath the metal bore wrapper and collar and run down inside the end cap. iii. The bore paper wrapper and the wrapper folded over the end faces of the coils was not joined properly allowing moisture accumulating in the bore to get under the metal wrappers and then through the inner paper wrapper at the bore to end face joins. iv. The inner wrapper was unable to withstand moisture if it was folded or worked in any way in that the plastic membrane of the inner wrapper would separate from its brown backing paper allowing moisture to penetrate. v. The coils should have been wrapped so as to provide a water proof vapour barrier. The inner wrapping of the coils failed in its function of excluding moisture.' 132 The last particular is in effect a summary of what goes before. That is to say, the Carriers claimed that the coils should have been wrapped so as to be impervious to the ingress of water vapour. Particulars (i) to (iv) are particulars of that assertion. The essence of the Carriers' case, in so far as it was based on insufficiency of packaging, is that the coils should have been wrapped in a manner that would have completely prevented the ingress of water either in the form of liquid or vapour. 133 In their written submissions, the Carriers say that the packaging of the coils was insufficient in a number of respects as follows:
Inherent Vice 135 Ankergracht says that any loss or damage arose or resulted from inherent defect, quality or vice of the coils in the consignment on the Ankergracht, in that the coils in question had been wetted before they were loaded on board and the water from that external wetting was able to infiltrate the external and inner wrappers and was therefore present on, and possibly within, the coils at the time they were delivered to the Ankergracht. Ankergracht says that the existence of that water within the inner wrapping of the coils was inherent vice, since corrosion would occur very rapidly and within hours of being in contact with that water. I have already concluded, on the balance of probabilities, that there was no internal wetting of the coils. Accordingly, Article 4 rule 2(m) does not afford an answer to Stemcor's claims.
Act Of Shipper 136 Ankergracht also relies on the exposure of the coils to external wetting prior to loading as an act or omission of the shipper under Article 4 rule 2(i). I have already concluded, on the balance of probabilities, that there was no internal wetting of the coils. Accordingly, Article 4 rule 2(i) does not afford an answer to Stemcor's claims.
Insufficiency Of Packaging 137 Insufficiency of package is the inadequate preparation of goods to withstand the foreseeable risks of carriage on the voyage contemplated. Packing will be sufficient if it is normal or customary in the trade. To be sufficient, packing must permit the relevant goods to withstand the normal hazards likely to be encountered on the specific voyage contemplated, and to prevent all but the most minor damage under normal conditions of care and carriage. Ordinarily, where goods have been packed in a manner that is normal or customary in the relevant trade, such that goods so packaged do not ordinarily suffer damage, it can be concluded that any damage to such goods was the fault of the carrier in failing to exercise proper care. 138 The insufficiency of the packing defence is very much a question of fact, highly dependent on the circumstances of each case. The Court must strive to pursue a middle ground between requiring ideal protection of stowage, on the one hand, and tolerating flagrant disregard for the safety of the cargo on the other. Looking at it from the other side, it involves pursuing a middle ground between ideal protection of packaging, on the one hand, and flagrant disregard for the safety of the cargo by the packer, on the other. 139 Captain Pyett described the inadequacy of the packaging of the coils in the following way:
CONCLUSION AS TO RESPONSIBILITY 156 It is true that the packaging of the coils was not such as would prevent the ingress of water in the form of vapour. However, the coils were packaged in a way that is regarded as adequate in the industry, and in a manner consistent with the general practice in the industry. There was no evidence of any industry practice of wrapping coils in a way that ensures there is no possible ingress of water in the form of vapour or otherwise. The evidence does not support a finding that the internal wrapping was defective or inadequate in any way. 157 The coils were being transported from a cold northern hemisphere climate to a hot southern hemisphere climate, through the tropics. While the coils were particularly susceptible to damage from corrosion consequent upon contact with water and the Carriers were not specifically informed of any particular sensitivity of the coils, the sensitivity of steel to corrosion generally was well known in the industry. 158 I consider that it is more likely than not that the holds were closed in Yokohama with water trapped inside in the form of wet dunnage and liquid water on some cargoes that were wet with rain. Further, ventilation occurred during the course of the voyages, at times when the vessels were likely to have been in the tropics. Ventilation probably resulted in the ingress of air containing water vapour rather than the removal of water vapour from the holds. 159 I consider that, on the balance of probabilities, condensation occurred after the loading of the coils on each vessel and during the course of the respective voyages of the vessels. That condensation resulted in corrosion. The corrosion could not have occurred if moisture had not been admitted into the holds or if moisture, once admitted, had been removed by the operation of a dehumidification system installed in the vessels. Alternatively, condensation could have been prevented by the operation of a heating system installed on the vessels to ensure that the surface temperature of the coils did not fall below the dew point temperature of the air in the holds. 160 In the circumstances, I consider that the corrosion was caused by the failure on the part of the Carriers to carry, keep and care for the coils properly and carefully during the voyages in circumstances where the vessels had neither dehumidification systems nor heating systems installed. In the circumstances, having regard to the apparent difficulty in preventing the ingress of water into the holds in the ways that I have described, the vessels were not seaworthy for the carriage of the coils in question from Yokohama to Sydney on voyages commencing in December and February respectively. Since it was practicable to install dehumidifiers in the vessels, the Carriers failed to exercise due diligence to make the ships seaworthy and to make the holds fit and safe for the carriage and preservation of the coils. 161 It follows that the Carriers are responsible for the corrosion damage that was occasioned to the coils and Stemcor is entitled to be compensated for that damage.
MEASURE OF DAMAGES 162 Stemcor and Tsuda contend that the amount recoverable, if they succeed, is the wholesale price charged by Stemcor to ACC for the damaged coils. It is common ground that that amount is as follows:
The parties have agreed that the proportions of the values attributable to the damaged coils were as follows:
Those figures are calculated as set out in Schedule 3 to these reasons. 164 Article 4 rule 5(b) of the amended Hague Rules provides the total amount recoverable is to be calculated by reference to the value of the damaged goods at the place and time at which the goods are discharged from the ship in accordance with the contract. The value of the goods is to be fixed according to the commodity exchange price, or if there be no such price, according to the current market price, or, if there be no commodity exchange price or current market price, by reference to the normal value of goods of the same kind and quality. Stemcor contends that rule 5(b) requires calculation by reference to the sale value of the goods to Stemcor in Sydney on the respective dates of unloading, being 28 November 2001 in the case of the Ankergracht, and 13 February 2002 in the case of the Archangelgracht. 165 Stemcor supplies 60 to 70 per cent of the Australian market for imported steel for continuous paint line applications, such as are used by ACC. There is no commodity exchange price for such steel. Stemcor contends, therefore, that current market price is the appropriate measure. Stemcor says that current market price is to be determined by what a willing buyer will pay and what a not unwilling seller will receive for the subject matter being valued. Such a proposition assumes that an efficient market exists (see Spencer v The Commonwealth (1907) 5 CLR 418). 166 Stemcor is a major supplier of aluzinc and galvanised steel coil in Australia and, specifically, in Sydney. It sells such goods to at least one willing buyer in Sydney, namely, ACC. Stemcor has done nothing to add value to the coils and says that the market price for the coils is the price at which the coils can be sold by Stemcor in Sydney. 167 However, that analysis assumes that current market price refers to the price at which the claimant can sell the goods in question rather than the current market price at which goods can be bought by the claimant. Such an analysis is erroneous. A claimant is entitled to be put in the position in which it would have been had the contract been performed. On the assumption that the Carriers were in breach of their obligations, and the damage to the coils was the result of some act or omission on the part of the Carriers, Stemcor would be entitled to be put in the position of having undamaged coils in Sydney. To put it in that position, it would need to buy more coils from Tsuda or elsewhere. If there were a supplier in Sydney, the measure of Stemcor's loss would be the price it had to pay to that supplier in Sydney to obtain undamaged coils. 168 Stemcor did not suggest that there was a current market for the supply of coils in Sydney. There was no evidence of any manufacture of such coils in Australia, let alone in Sydney. The only basis upon which Stemcor could replace the damaged coils was by further import from Tsuda. It was not suggested that, in order to replace the coils in Sydney, Stemcor would be required to pay more than the CIF price paid to Tsuda for the coils in question. 169 Stemcor concedes that, if there is no current market price for the coils in Australia or Sydney, the amount that it would be entitled to recover is the CIF value of the coils, which reflects the normal value of goods of the same kind and quality as the coils shipped on the Ankergracht and the Archangelgracht. 170 The position might be different if there was evidence that the sale of coils to ACC by Stemcor was lost permanently such that it lost the profit on the proposed sale of coils to ACC. In the absence of any such consequential loss, the appropriate measure of damage, consistent with general principle and the appropriate analysis of rule 5(b), is that Stemcor would be entitled to damages equal to the cost of replacing the damaged coils in Sydney. As I have said, it is common ground that that amount is as indicated above.
CONCLUSION 171 In the light of the conclusions that I have reached, there must be judgment for Stemcor and Tsuda in each of the proceedings. Stemcor is entitled to recover from Ankergracht the sum of $375,979.05, together with interest from the date of arrival of the Ankergracht in Sydney on 28 November 2001 to the date of judgment. There should be judgment against Archangelgracht in the sum of $55,676.88, together with interest from the date of arrival of the Archangelgracht in Sydney on 13 February 2002 to the date of judgment. The Carriers should pay the costs of Stemcor and Tsuda of the two proceedings. The two proceedings have been conducted as one and costs should be determined on that basis.
SCHEDULE 3 Ankergracht Salvage calc Actual Salvage return net of GST 144,185.64 Less Costs incurred in salvage (Auctioneer) 23,364.58 Less Net Line time costs 4,981.98 Less Cartage 4,327.04 Less Storage 9,513.34 Less Handling 401.10 Net Salvage return 101,597.60
Total Loss of damaged goods based on price Less Salvage Net Loss 552,038.00 101,597.60 450,440.40 CIF Value of Damaged goods 477,576.65 101,597.60 375,979.05
Archangelgracht Salvage calc Actual Salvage return net of GST 10,596.64 Less Costs incurred in salvage (Auctioneer) 940.96 Less Net Line time costs 46.22 Less Cartage 339.27 Less Storage 745.91 Less Handling 31.45 Net Salvage return 8,492.83
Total Loss of damaged goods based on price Less Salvage Net Loss 75,451 8,492.83 66,958.17 CIF Value of Damaged goods 64,169.71 8,492.93 55,676.88 I certify that the preceding one hundred and seventy-one (171) numbered paragraphs are a true copy of the Reasons for Judgment herein of the Honourable Justice Emmett J.
Date of Hearing: 4, 5, 6, 7, 8, 11, 12 and 13 April, 29 and 30 June 2005
Stemcor (A/sia) Pty Ltd
C.V. Scheepvaartonderneming Ankergracht
(1907) 5 CLR 418