[2025] VCAT 44
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2025-01-15
Original judgment source is linked above.
Domestic building contract - builder contracted to design and construct - three categories of alleged defects - largest component of the owners' claim for damages based on allegation that the new home was to accommodate their caravan under the "Caravan Requirement" - that claim pleaded as a contract claim, and not based on s18 of the Australian Consumer Law (Victoria) - finding that it was an express term of the contract that the builder would satisfy the Caravan Requirement, and that the builder had breached that term - finding that the owners' assertion that their measure of damages was the cost of demolishing and rebuilding the home was unsustainable - findings in relation to the other defects claims - concession by the builder that the owners should have the opportunity to lead evidence on the cost of alternative accommodation during rectification - as a further hearing is therefore required, owners also to be given the opportunity to lead evidence on damages assessed by reference to the cost of storing their caravan away from their home
Stanley v EWH Construction West Pty Ltd (Building and Property) [2025] VCAT 44
(a) the cost of rectification of defects ("Scenario Two" in the costings prepared by Tom O'Dowd of Victorian Building Consultants Pty Ltd) including rectification of plumbing defects insofar as those costings have been accepted by the Tribunal, as set out in the Reasons accompanying this Order; plus
(b) the cost of alternative accommodation and storage of chattels during rectification works (raised in paragraph 10 of their Amended Points of Claim); plus
(c) the applicants' cost of storing their caravan away from their home for a reasonable period of time (which is open under paragraph 10 of their Amended Points of Claim given the breadth of paragraph (b) of the Particulars under that paragraph).
The parties acknowledge that the developer imposed design guidelines[3] on purchasers including the Stanleys. These guidelines require a degree of uniformity in the appearance of houses built in the street. One consequence of the guidelines is that each of the houses on the Stanleys' side of the street - except theirs - has its garage and driveway on the south side. The Stanleys chose to have their garage and driveway on the north side, and obtained permission from the developer to put this into effect.
(a) EWH cut the site deeper than it should have, and did not compensate for this during the construction of the house. This has caused the finished floor level ('FFL') of the house and the garage to be about 130 mm lower than they should be, which makes the slope of the driveway greater than it should be;
(b) some general defects which are common in building cases brought in VCAT - matters such as deficient internal painting in some areas, gaps and cracks; and
(c) some plumbing defects, externally relating to the stormwater system, and internally in relation to such matters as the size of the waste outlet in the shower. EWH built the driveway, and the garage and house slabs. It also laid the external drains and stormwater system, and installed a water tank on the south east corner of the house, which would be fed from water draining from the roof. In the contract plans,[4] Sheet 2 contains Drainage Notes which required EWH to install surface drainage works in accordance with the engineer's design. That design[5] contained 23 Notes to the builder, including C11 which stated that all existing surface levels were as per architectural plan and or land survey plan; C12 which said the "builder (was) to take all responsibilities and liabilities for any changes to be done without the approval of the design engineer and/or respective council's inspector"; and C15 which said the "laying of new pipes and construction of pits shall be as per local council's standard details, specifications and as per National Plumbing and Drainage Code AS/NZ 3500.3.2015 and Building Code of Australia "Part 3.1.2 drainage". Sheets C-001 and C-002[6] set out the site drainage plan and drainage details. EWH did not lay the paving around the house. Some of the alleged plumbing defects are within, or encased by, that paving. The Stanleys' position is that EWH is liable for these defects because it installed the drainage and because the levels of the paving their contractor laid was dictated by the FFLs of the house and garage.
"Scenario One" in which the house would be demolished and rebuilt. He costed this at $652,197.20 (including a contingency of 10%, builder's margin of 25% and GST) but said that the cost of up to 8 months' alternative accommodation and storage of furniture would have to be added; and
"Scenario Two", based on rectification of defects without demolition of the house. He costed this at $136,429.00 (including a contingency of 10%, builder's margin of 25% and GST) but said that the cost of up to 10 weeks alternative accommodation would have to be added.
the Building Works will be carried out in a proper and workmanlike manner and in accordance with the plans and specifications set out in this Contract (and)
if this Contract states the particular purpose for which the Building Works are required, or the result of which the Owner wishes the Building Works to achieve, so as to show that the Owner relies on the Builder's skill and judgement, the Building Works and any material used to carry out the Building Works will be reasonably fit for that purpose or will be of such a nature and quality that they might reasonably be expected to achieve that result".
Section 8(f) of the Domestic Building Contracts Act 1995 says that this warranty is "part of" the parties' contract:
if the contract states the particular purpose for which the work is required, or the result which the building owner wishes the work to achieve, so as to show that the building owner relies on the builder's skill and judgement, the builder warrants that the work and any material used in carrying out the work will be reasonably fit for that purpose or will be of such a nature and quality that they might reasonably be expected to achieve that result.
(a) told him that the reason they were looking to move homes and build their own home on their land was due to difficulties they were facing in relation to the storing of their caravan at their current residence;
(b) told him that any new home built on their land would need to be built around their caravan so as to allow the caravan to be easily stored in the backyard of the new home through the new dwelling's garage; and
(c) hand delivered to Mr Cugliari an informal sketch[13] of their desired home and confirmed that they required panel lift garage door openings of 2380 mm height and 3000 mm width at the front of the garage, the latter exceeding the 'standard inclusion' of 2400 mm. The Stanleys allege that Mr Cugliari said that if the height of the openings was to be 2380, the ceiling heights would have to be 2700 mm, and that a 3000 mm wide panel lift door was not possible.
(a) confirmed that the Caravan Requirement had been part of the building works since the date of the initial discussion;
(b) confirmed that it had been represented to them that the Caravan Requirement had been incorporated into the building contract via its incorporation into the relevant plans, designs and specifications of the building contract;
(c) questioned whether EWH ensured that the Caravan Requirement was made part of the building contract via its incorporation into the relevant plans, designs and specifications; and
(d) alleged that the Caravan Requirement was not incorporated into the constructed building works.[15]
(a) admitted that the Stanleys met "a salesperson" - subsequent paragraphs confirming that this was Mr Cugliari - at its display home in November 2017, in which the Stanleys said they wanted the garage door to be constructed at a height to accommodate their caravan, but otherwise denied the allegations in paragraph 4 of the Amended Points of Claim;
(b) admitted having received from the Stanleys their informal sketch of the proposed new home, but did not admit the allegations of Mr Cugliari stating specific garage door heights or widths;
(c) admitted having received the payment of $2,000.00 but denied that the contract documents were to include the Caravan Requirement;
(d) admitted having submitted the preliminary building agreement in February 2018, as a quotation;
(e) In stating that "save to say that the email speaks for itself", admitted the Stanleys' allegations in paragraph 6(b) of the Amended Points of Claim that on 10 March 2018 it told them the quote was still open to be accepted, that the Stanleys reiterated the Caravan Requirement,[17] and that the Stanleys sought confirmation that EWH could make arrangements with the relevant design engineers to address the Caravan Requirement;
(f) denied the Stanleys' allegations in paragraph 6(c)(ii) of the Amended Points of Claim that EWH would provide the Caravan Requirement to the relevant draftsperson to ensure that it was incorporated into the relevant plans and designs;
(g) denied that the building contract was to incorporate the Caravan Requirement;
(h) admitted the building contract was entered into on 3 June 2018, but denied that it could contain compliance with the Caravan Requirement as an implied term.[18] EWH said it relied on the written building contract. I note here that in its submissions EWH said the written contract contained clauses that the contract was complete in itself and overrides any earlier agreement, whether made verbally or in writing. However this still leaves in place EWH's admission of the sixth bullet point of clause 11 of the contract.
(i) admitted that the contract contained the warranties set out in section 8 of the Domestic Building Contracts Act 1995;
(j) in the amended paragraph 9 in the Amended Defence dated 29 November 2023, it pleaded to the Stanleys' alleged warranty that the Building Works and materials "would be reasonably fit for any purpose which the [Stanleys] wished to achieve, or would be of such a nature and quality that they might reasonably be expected to achieve the result that the [Stanleys] wished to achieve", by pleading that "the warranty alleged is only given if the contract states the particular purpose for which the work was required". Then in paragraph 17 it pleaded that the Caravan Requirement was not part of the contract, was not mentioned in the contract, and that the contract did not state the particular purpose for which any building work was required, with the result that there was no breach of warranty in respect of the Caravan Requirement;
(k) admitted having performed the building works between 11 September 2018 and 9 May 2019, but did not admit that the Stanleys tried to manoeuvre the caravan into the garage on 17 May 2019. However, EWH admitted its receipt and the contents of the Stanleys' email of 18 May 2019. EWH admitted that the Stanleys moved into the dwelling on 1 June 2019 before the driveway was completed;
(l) did not admit that on 7 July 2019 the Stanleys concluded that the Caravan Requirement had not been incorporated into the building works; and
(m) denied having, on 9 July 2019, confirmed that the Caravan Requirement was part of the Building Contract via its incorporation in the relevant plans, designs and specifications. EWH relied on the contents of its email to the Stanleys dated 9 July 2019.
(a) it admitted that the Stanleys had suffered loss and damage of $11,612,00, being the extent to which that its expert Mr Edwards agreed - in his report dated 28 October 2021 - with breaches identified by the Stanleys' expert Mr O'Dowd; and
(b) it admitted that the Stanleys had suffered loss and damage of $1,522.00, to the extent that its expert Mr Edwards agreed - in his report dated 17 February 2022 - with breaches identified by the Stanleys' plumbing expert Mr Newell.
The evidence regarding the Caravan Requirement
James Clifford, director of EWH- evidence in chief
Noel Clifford, director of EWH- evidence in chief
Evidence of the Caravan Requirement not being satisfied
(a) the driver takes about 5 minutes to painstakingly reverse the caravan at extremely slow speeds, using the utmost skill and caution. Five minutes is an excruciatingly long period of time in this context. I'd ask the reader to reflect on how many times it has taken them 5 minutes to reverse into the driveway of a suburban house;
(b) the vehicle's wheels have been put on boards, when the vehicle is on the cross over, to raise the vehicle's height and thereby increase the angle where the vehicle's towball meets the caravan's hitch, to reduce the prospect of the underside of the caravan striking the footpath;
(c) even with the wheels of the vehicle having been raised by these boards, when the caravan is going over the footpath, once the caravan's wheels have got onto the driveway the distance between the underside of the caravan and the surface of the footpath is a matter of a few centimetres, around the size of a matchbox;
(d) the caravan's wheels have been put on boards, when they are on the driveway, to increase the distance between the bottom of the caravan and the surface of the driveway;
(e) unintentionally, the person who took the video occasionally points the camera down the driveway of the house next door, showing it to be basically level with that property's garage, in a vivid contradistinction with the slope of the Stanleys' driveway as it approaches the Stanleys' garage;
(f) as the driver slowly and carefully reverses the caravan, he or she is told to "Stop!" on several occasions, as persons outside the caravan move the boards or check that the bottom of the caravan is not scraping on the footpath or (it appears) that the top of the caravan is not striking the garage;
(g) as a testament to the skill of the driver and the great care which was exercised, the caravan does not scrape on any surface of paving in this video. However, I have no hesitation in finding that a driver of average skills with experience in towing a caravan, would not be able to perform this task. It becomes a word game: you cannot say that it is "possible" for a person to swim the English Chanel because elite athletes can do so after a lifetime's training. Even though this video shows the caravan - on this occasion - being reversed towards the garage without being damaged, I am comfortable with saying that it is practically impossible for an average driver to achieve that result, with or without outside assistance of people moving boards and periodically telling the driver to "Stop!".
Mrs Stanley gave evidence that when the Stanleys went looking for a new caravan, they sought a caravan which could cope with the driveway. She said that they asked the supplier to deliver the caravan and reverse it into the driveway, but that the supplier was unable to succeed in doing so. As the supplier attempted to reverse the caravan, the hitch - which is the component which attaches the caravan to the vehicle - could not cope with the change of angles; the caravan would not go down the driveway because it was too steep; and the vehicle's wheels began to spin as if the driver was doing a "burn out". Mrs Stanley considered the exercise to be very dangerous.
the Building Works will be carried out in a proper and workmanlike manner and in accordance with the plans and specifications set out in this Contract; (and)
if this Contract states the particular purpose for which the Building Works are required, or the result of which the Owner wishes the Building Works to achieve, so as to show that the Owner relies on the Builder's skill and judgement, the Building Works and any material used to carry out the Building Works will be reasonably fit for that purpose or will be of such a nature and quality that they might reasonably be expected to achieve that result".
(a) that the particular purpose for which the Building Works were required included enabling the Stanleys' caravan to be reversed down the driveway and through the garage, which entailed EWH building a driveway with a suitably small fall;
(b) that the result which the Stanleys wished the Building Works to achieve, was not only to create a house to live in, but significantly was also to allow the Stanleys' caravan to be reversed down the driveway and through the garage, which entailed EWH building a driveway with a suitably small fall in levels, in a way which showed that the Stanleys relied on EWH's skill and judgment; and
(c) that the Building Works and any material used to carry out the Building Works were to be reasonably fit for those purposes, including the Caravan Requirement, or would be of such a nature and quality that they might reasonably be expected to achieve that result.
DAMAGES IN RELATION TO THE CARAVAN REQUIREMENT AND THE FFLS
(a) by not satisfying the Caravan Requirement, and separately,
(b) by building a house and garage to the wrong FFLs.
"In the present case, the respondent was entitled to have a building erected upon her land in accordance with the contract and the plans and specifications which formed part of it, and her damage is the loss which she has sustained by the failure of the appellant to perform his obligation to her. This loss ... can, prima facie, be measured only by ascertaining the amount required to rectify the defects complained of and so give to her the equivalent of a building of her land which is substantially in accordance with the contract. One or two illustrations are sufficient to show that the prima facie rule for assessing damages for a breach of warranty upon the sale of goods has no application to the present case. Departures from the plans and specifications forming part of a contract for the erection of a building may result in the completion of a building which, whilst differing in some particulars from that contracted for, is no less valuable. For instance, particular rooms in such a building may be finished in one colour instead of quite a different colour as specified. Is the owner in these circumstances without a remedy? In our opinion he is not; he is entitled to the reasonable cost of rectifying the departure or defect so far as that is possible" (emphasis added).[50]
(a) the Stanleys cannot expect to use their caravan "forever". As in personal injury cases in which plaintiffs are compensated for loss of future earning capacity, it is possible to determine a period of time over which a loss will be incurred, and to capitalise it into a lump sum which is discounted to reflect the benefit to the plaintiff of receiving the sum early. Simply as an illustration, it might be said that for 10 years, but no more, the Stanleys could be expected to be using a caravan, so that they will suffer a loss for a maximum of 10 years;
(b) the caravan was not at the Stanleys' house when the view was conducted during the hearing. It must have been stored somewhere. I accept that it cannot simply be parked in the street, because the Stanleys would be penalised by the local Council. The caravan could be stored at a facility, at a cost. I have no doubt that the cost of storing the caravan for even 10 years would not come anywhere near the $650,000.00 asserted cost of demolishing and rebuilding the house. Mitigation of damage would in effect require the Stanleys to be compensated for storage costs, at a reasonable location, rather than for the cost of demolishing and rebuilding the house;
(c) EWH builds display homes, and acquires land for that purpose. Could not EWH lease a block of its land, in a reasonable location, to the Stanleys at a peppercorn rental, so that they could store their caravan there? At the end of the lease, possession would revert to EWH and, if history is a guide, EWH then would enjoy the land's increase in value;
(d) there may be some additional cost incurred by the Stanleys in retrieving their caravan before taking a trip, and returning it to storage afterwards. That could be ascertained;
(e) as the basis of the Stanleys' complaint is that they cannot store their caravan at their home, there does not seem to be any basis for saying that the Stanleys should be compensated for the cost of hiring someone to drive their caravan between the storage facility and their home. If they can drive a vehicle towing a caravan, they can drive the vehicle to and from the storage facility;
(f) the Stanleys may be able to establish an entitlement to damages for loss of amenity, but the parties will be aware that awards of this kind are insubstantial.
THE OTHER ALLEGED BUILDING AND PLUMBING DEFECTS
(a) The Stanleys first obtained an informal report by Mr O'Dowd, which was not relied on in this proceeding. Mr O'Dowd set out two alternatives: demolition and rebuilding, and rectifying specific items.
(b) EWH obtained a report from Mr Edwards in reply,[51] dated 28 October 2021.
(c) The Stanleys then obtained a report by Mr Newell about plumbing issues,[52] dated 31 October 2021. Mr Newell did not provide any costings.
(d) Mr O'Dowd prepared his first formal report[53] dated 29 November 2021, in which he provided costings for his two alternatives.
(e) Mr Edwards then prepared a supplementary report[54] dated 17 February 2022 in which he focussed on items identified by Mr Newell.[55] Mr Edwards opined that EWH was not liable for 8 of the 12 items identified by Mr Newell, and he costed the 4 items for which he considered EWH was liable at $1,522.00.
(f) Mr O'Dowd prepared an updated costing on 21 November 2023.
(g) Mr O'Dowd and Mr Edwards gave evidence in the hearing orally, concurrently.
(h) Speaking generally, both Mr O'Dowd and Mr Edwards would cost an item, and add percentages for contingencies, margin and GST. Mr Edwards does this for each item. However Mr O'Dowd states his costing of the item on one page, and then at the end, globally applies 10% contingencies, 25% margin, and 10% GST to the total of all of the items. For example, in relation to items 2.1, refixing and painting the soffit lining on the entrance portico, on page 15 of Mr O'Dowd's report of 21 November 2023, Mr O'Dowd costs labour and materials at $280.00 + $720.00. (Whilst these two figures equal $1,000.00, Mr O'Dowd does not show that figure; only its components). Then on page 22, he gives the sub-total of his costings of all items, and then adds 10% contingencies to give a sub-total, then adds 25% margin to that sub-total to give a second sub-total, and then adds 10% GST. When the parties then refer to the respective costings of Messrs O'Dowd and Edwards, Mr O'Dowd's figure for item 2.1 is stated at $1,512.50. The calculation (not shown on page 15 but implied from the calculation on page 22) is this: $1,000.00 + $100.00 = $1,100.00; plus 25% of $1,100.00 = $1,375.00; plus 10% of $1,375.00 = $1,512.50. Mr Edwards' report of 28 October 2021[56] showed his calculation for item 2.1 as labour and materials = $395.00 + 10% of $395.00 = $434.00; plus 25% of $434.00 = $542.00; plus 10% of $542.00 = $596.00.
The arithmetic is the same but the inconsistent design of setting the figures out in that way made it time consuming to compare the experts' costings.
(i) Another thing was that Mr Edwards' last written costings preceded Mr O'Dowd's, and to bring his figures up to date Mr Edwards said that 30% should be added to his last written costings to adjust for price rises in the building industry. By using this broad brush approach Mr Edwards effectively adds more than 10% GST, to the advantage of the Stanleys.
(j) Both experts were comfortable with adding margin to a contingency so I will accept that as being appropriate.
(a) Item 1 paint finishes on certain architraves are rough, uneven, and have unfilled nail holes. Mr Edwards only concedes that this defect affects a lesser number of them than asserted by Mr O'Dowd and this explains the difference in the experts' costings. I accept Mr O'Dowd's opinion that the defect is more widespread than conceded by Mr Edwards, and on that basis I accept Mr O'Dowd's costing of $4,356.00 including contingency, margin and GST. I award that sum to the Stanleys.
(b) Item 2, the underside of the door head for the sliding door leading to bedrooms 2 and 3 has not been finished with a topcoat. Mr O'Dowd assesses the cost of rectification at $272.25 including contingency, margin and GST, and Mr Edwards at $127.00. I am satisfied with Mr O'Dowd's costing of $272.25 and I award that sum to the Stanleys.
(c) Item 3 Mr O'Dowd says there are areas of kitchen joinery leading into the laundry which have been over sprayed with paint, causing them to have paint overruns and be rough and unsightly; the paint finish on the south side of the living room is uneven; and that there are paint runs on the east wall of the garage. Mr Edwards agrees with the existence of these defects but the experts disagree on the cost of rectification, Mr O'Dowd's $1,678.88 including contingency, margin and GST cf Mr Edwards' $777.00. I am satisfied with Mr O'Dowd's costing of $1,678.88 and I award that sum to the Stanleys.
(d) Item 4 the tops and bottoms of all internal doors have not been painted. Failing to paint the top and underside of a door is not a trivial matter for the consumer because modern internal doors are not solid timber and the paint is necessary to provide a seal. At the same time, failing to paint these areas is an obvious "rip off", because the defects are concealed, and the contractor has been paid for work which he or she has not performed. Mr O'Dowd costed rectification of all of these doors, by removing them, painting them and reinstalling them, at $1,280.00 (plus contingency, margin and GST) which comes to $1,936.00. Mr Edwards sought to argue that time could be saved by doing this work in hot dry weather, to shorten the time between coats being applied, but there can be no sympathy for EWH in respect of this item. I award $1,936.00 to the Stanleys.
(a) 3.6 item 1 Mr O'Dowd says the window frames are damaged by water ingress on the east side of the living room. Mr Edwards agrees. The dispute is not over the scope of rectification work because the two experts suggest the same method using slightly different words. Mr O'Dowd's costing is more than double Mr Edwards'. I cannot accept Mr O'Dowd's costing and I adopt and award Mr Edwards' costing of $1,163.00.
(b) 3.6 item 2 scratched kitchen tiles. Mr O'Dowd reports that 3 tiles in the kitchen are scratched. They were evident on the view. Mr Edwards does not dispute the existence of the scratches but opines that he has not seen evidence that they were caused by the builder. The scratches are such that they appear to have been created by a building contractor. No other areas of the kitchen, which has been used by the Stanleys now for some years, have similar scratches and I am satisfied that these tiles have not been scratched by normal wear and tear. I am satisfied on a balance of probabilities that the scratches were caused by EWH. Mr Edwards did not provide a costing and so I accept the unchallenged costing of Mr O'Dowd of $840.00 plus contingency, margin and GST which comes to $1,343.10. I award $1,343.10 to the Stanleys.
(c) 3.6 item 3 laundry door is creased and requires replacement. The experts agree on the existence of this defect but disagree on the cost of supplying and fitting a replacement as the means of rectification. Mr O'Dowd says $610.00 plus contingency, margin and GST, amounting to $922.63, and Mr Edwards says $679.00. Mr O'Dowd prices the door at $80.00 with the rest being labour. This convinces me that Mr Edwards' figure is to be preferred and I award $679.00 to the Stanleys.
(d) 3.6 item 4 laminated benchtop in laundry is discoloured and its gloss is inconsistent. The experts agree on the existence of this defect and Mr Edwards notes that it has already been replaced unsuccessfully. Mr Edwards actually assesses the cost of supplying and fitting a replacement as the means of rectification at a slightly higher amount than Mr O'Dowd, and in these circumstances I adopt Mr Edwards' figure and award $1,255.00 which includes contingency, margin and GST to the Stanleys.
(e) 3.6 item 5 Mr O'Dowd says there are gaps between the architraves and the walls, some of which are visible using a mirror device that allows one to look down on the architraves, but is not visible otherwise. Mr O'Dowd says these gaps adversely affect the energy rating of the home. He recommends caulking and touch up of relevant painted areas. Mr Edwards agrees that there is a large gap in one area only, and his suggested cost of rectification is very low as a result. I accept Mr O'Dowd's evidence that there are gaps in multiple areas, and I accept his cost of $1,633.50 which includes contingency, margin and GST. I award $1,633.50 to the Stanleys
(f) 3.6 item 6 Mr O'Dowd says windows are scratched throughout the home, which need to be polished out. Mr Edwards does not deny the existence of the scratches, which were visible at the view of the home, but opines that there is no evidence that it was caused by EWH. I am satisfied on the balance of probabilities that they were caused by EWH. There is nothing to suggest that the Stanleys could have caused them. They are consistent with rough handling during installation and other building works. Mr Edwards did not provide a costing and so I accept the unchallenged costing of Mr O'Dowd of $1,440.00 plus contingency, margin and GST which comes to $2,178.00.
(g) 3.6 item 7 the door frame of the sliding door to the al fresco is scratched. Mr Edwards does not deny the existence of the scratches, which were visible at the view of the home, but opines that there is no evidence that they were caused by EWH. I am satisfied on the balance of probabilities that they were caused by EWH. There is nothing to suggest that the Stanleys could have caused them. The scratches are consistent with rough handling during installation and other building works. Mr Edwards did not provide a costing and so I accept the unchallenged costing of Mr O'Dowd of $720.00 plus contingency, margin and GST which comes to $1,089.00.
(a) 4.0 item 1 Mr O'Dowd says there are gaps in insulation, and that additional insulation must be supplied to form a continuous barrier. Mr Edwards agrees but the experts differ very slightly on the cost of rectification: Mr O'Dowd's $302.50 cf Mr Edwards' $226.00. I accept Mr O'Dowd's assessment and award $302.50
(b) 4.0 item 2 the top of the air riser has been sealed with cardboard, which is not an approved product as it is flammable. It must be replaced with plasterboard. Mr Edwards agrees but the experts differ slightly on the cost of rectification: Mr O'Dowd's $650.38 cf Mr Edwards' $226.00. As Mr Edwards' figure does not allow for the cost of materials I accept Mr O'Dowd's assessment and award $650.38
(c) 4.0 item 3 Mr O'Dowd says the light fitting inside the roof space is not protected against damage and requires a protective shield. Mr Edwards agrees but the experts differ very slightly on the cost of rectification: Mr O'Dowd's $136.13 cf Mr Edwards' $112.00. I accept Mr O'Dowd's assessment and award $136.13.
"Scenario One" in which the house would be demolished and rebuilt. He costed this at $652,197.20 (including a contingency of 10%, builder's margin of 25% and GST) but said that the cost of up to 8 months' alternative accommodation and storage of furniture would have to be added; and
"Scenario Two", based on rectification of defects without demolition of the house. He costed this at $136,429.00 (including a contingency of 10%, builder's margin of 25% and GST) but said that the cost of up to 10 weeks alternative accommodation would have to be added.
This item was not mentioned in Mr Newell's report of 31 October 2021. Its table of contents says the sewer drain is dealt with on pages 16 and 17.[63] Those pages deal with the inspection shaft being covered with astroturf [that is, item 2].
In Mr Newell's updating letter dated 18 November 2023[64] he wrote, "Please find an updated list of the defects identified at [the property]. The additional defects were outlined in the body of my report dated the 31st of October 2021 but were not added to the defect list on page 4 of the report" followed by a short list of additional defects including "Additional defects as outlined in the body of the report *The sewer drain is holding water downstream from the laundry waste under the slab". In fact, this issue was not "outlined in the body of (the) report dated the 31st of October 2021". The updating letter does not contain an explanation of how Mr Newell reached his conclusion or made his observation of this item; the volume of water allegedly being held; or the consequences which presumably would vary depending on that volume. There are no photographs of the item.
In the hearing, when evidence was being given by Mr Newell, Mr O'Dowd and Mr Edwards concurrently, Counsel for EWH objected to Mr Newell giving evidence around this topic and in the course of that objection Mr O'Dowd sought to explain his costing by reference to one of Mr Newell's photographs which Mr O'Dowd then acknowledged concerned a separate issue. It seemed to me then that the Stanleys withdrew this item from their claim.
In any event, I find that the Stanleys have not proven this item.
I find that the Stanleys have not proven this item. Mr Edwards did not cost it, nor did Mr O'Dowd.
[1] Mrs Stanley gave evidence that this was the same width as the applicants' previous block.
[3] General, rather than detailed evidence, was given about these design guidelines. It was accepted by the parties that the guidelines could prevent the Stanleys from raising the garage roof as part of rectifying defects in the house.
[6] Pages 593 and 594 of the Tribunal Book.
[7] In addition, there was evidence about the control which the developer of the housing estate has over the appearances of houses, for example by being able to require certain façades, and to dictate set backs and heights. It is implied by this evidence that the work of modifying the slabs, which would doubtless then require the raising of the roofs of the garage and the house, would have to be approved by the developer. If the work of modifying the slabs was feasible, one could not have confidence that approval would be granted.
[9] Counsel for the parties cooperated in attending to deficiencies in discovery and the tendering of these additional documents was by agreement
[10] [2020] VSC 388, especially at paragraphs 34-40, 44, 46 and 50.
[11] Particulars under paragraph 9 of the Amended Points of Claim. The clause is at page 505 of the Tribunal Book.
[12] Paragraph 6(b)(ii) of the Amended Points of Claim.
[13] Whilst described as an "informal sketch", it was a floor plan, with dimensions prepared by Mr Stanley on a computer.
[14] Paragraphs 4, 5 & 6 of the Amended Points of Claim.
[15] Paragraph 15 of the Amended Points of Claim.
[16] Paragraph 16 of the Amended Points of Claim.
[19] Page 28 of first day's Transcript.
[22] Commencing at page 503 of the transcript.
[23] The description "informal sketch" is a bit misleading. They were drawn by Mr Stanley using a computer program and so appear to be the work of a draftsperson. They have dimensions and indicate the position of the roof. As well as some internal walls being different, the first plan shows the house at 219.2 sq m and the second 224.2 sq m.
[25] Produced during the hearing and added to the Tribunal Book as page 800.
[26] Page 519 of the Tribunal Book; the discussion commences at page 515 of the Transcript.
[31] Pages 417-419 of the Tribunal Book.
[38] Paragraph 16 of EWH's Submissions in Reply dated 1 July 2024.
[40] Page 874 of the Tribunal Book, added during the hearing.
[43] Pages 923-932 of the Tribunal Book.
[45] Pages 933-942 of the Tribunal Book.
[50] Bellgrove v Eldridge [1954] HCA 36 at [5].
[51] Pages 20-149 of the Tribunal Book.
[52] Pages 148-216 of the Tribunal Book.
[53] Pages 217-305 of the Tribunal Book.
[54] Pages 306-377 of the Tribunal Book.
[55] Pages 311-322 of the Tribunal Book, containing pages 5 - 16 of this report.
[56] Page 131 of the Tribunal Book, being page 111 of this report.
[57] Video 20211201-165119 filed in the Tribunal's case management system.
[58] Mr Edwards said he agreed with Mr O'Dowd's costing at $475.00, but in saying that he did not waive his 30% increase for inflation.
[59] Page 844 of the Tribunal Book, tendered during the hearing.
[61] Page 919 of the Tribunal Book showed areas of paving which were constructed by EWH, and the areas the subject of items 1 and 2 were not EWH's responsibility.
[62] Page 316 of the Tribunal Book, paragraphs 7.8 and 7.9 of his Report dated 17 February 2022.
[63] Pages 163 and 164 of the Tribunal Book.
Stanley
EWH Construction West Pty Ltd
(1954) 90 CLR 613
(1977) 180 CLR 266