[2003] VSCA 105
Court of Appeal (Vic)
2003-08-07
WINNEKE, P., PHILLIPS and BUCHANAN, JJ.A.
Original judgment source is linked above.
[ 2003] VSCA 105
Courts - Practice and procedure - Building contract - Plaintiff's summons for final judgment- Finding of triable issue of fact and law - Consideration also of construction of contract - Expression of opinion final in nature and adverse to plaintiff - Application for final judgment "dismissed" - Whether appeal competent - Leave to appeal rescinded - Supreme Court Act 1986 s.17A(6).
1. Was the contractor entitled to submit a final payment claim on 15 or 17 May 2001 given that a separate defects liability period, which [if established] was established on 13 May 2001, had not expired?
2. Was the final payment claim in form ineffective?
3. Does the default procedure for payment under cl.42.1 apply to a final payment claim?
4. Is the liability of the principal under the default payment procedure affected by the subsequent issue of a final payment certificate?
"This conclusion carries with it the consequence that there is a triable issue that the failure of the superintendent to issue a certificate within time cannot bring into play the provisions of the fourth paragraph of cl.42.1. Accordingly, the contractor's application for summary judgment must fail. Nevertheless, in case this conclusion should not stand, and in deference to the arguments put on behalf of the parties, I shall deal with two remaining issues in this application."
"The consequence of this is that on 14 June 2001 the Principal became obliged to pay to the Contractor the sum of $7,698,951 claimed."
But because the late issue of a final certificate also had effect, his Honour concluded (in paragraph [51]):
"It follows that on 3 August 2001, 14 days after the issue of the Final Certificate, the liability of the Principal to pay $7,698,951 which had arisen on 14 June 2001, 28 days after the receipt of the Final Payment Claim, was replaced by a liability in the Contractor to pay to the Principal the sum of $1,880,570."
"For this reason, too, the Contractor's claim for summary judgment must fail."
As authenticated, the formal order of the Court was that the application of the plaintiff for summary judgment brought by summons filed on 10 July 2001 be dismissed, with costs.
"An appeal does not lie to the Court of Appeal from an order giving unconditional leave to defend the proceeding."
As already stated, in the circumstances of this case his Honour's order that the application for final judgment be dismissed was tantamount to an order giving unconditional leave to defend - or so it was, if reference is made only to the reasons given on 26 October.
had a right of appeal if leave was obtained. But such a grant of leave would plainly be discretionary and once granted such leave can be rescinded or revoked - and Mr Burnside accepted as much. Either way then, this Court has the power to rescind the leave earlier granted. It is, after all, the fact that the parties have been locked in an arbitration for some time now, a decision shortly expected, and that may well resolve finally such matters of payment as are in dispute.
"The plaintiff's application for summary judgment brought by summons ... is dismissed."
We have been informed that following delivery of his Honour's reasons, and no doubt because of the fullness of those reasons in relation to the construction of the contract, there was some discussion between counsel for the parties as to the form which his Honour's order should take lest it should impinge upon the contractor's capacity to apply for leave to appeal to this Court against his Honour's reasons in respect of the "contract construction" points. Accordingly, his Honour reserved to the contractor, "liberty to apply for leave to the Court of Appeal as it may be advised".
judge's orders were interlocutory in nature; indeed it is readily apparent that they did not finally determine the rights of the parties in the litigation notwithstanding the forceful reasons given by his Honour in respect of the contract construction issues raised before him. This Court granted leave on the basis that the judge's order dismissing the application for summary judgment should not be taken as the equivalent, in the circumstances, of a grant of leave unconditionally to defend the action. Upon reflection, and after hearing counsel this morning, I regret to say that I do not believe that view was correct. It seems to me that, for the reasons which have been advanced by Phillips, J.A., we should now rescind the leave to appeal granted by the Court and remit the matter to the Trial Division for further hearing. The regret which I have expressed stems from the fact that the application by the respondent to rescind the leave previously granted, on the basis that the appeal is incompetent, has come so late in the day.
1. Leave to appeal granted by this Court on 22 February 2002 is rescinded.
2. Action remitted to the Trial Division for further hearing.
[1] Under clause 42.8 the superintendent is required to issue a final payment certificate within 14 days after the receipt of the final payment claim.
[2] See Reasons for Judgment, paras.[25] and [26].
[4] [1990] 1 W.L.R. 578 at 583 per Lord Donaldson M.R. In England, however, there has been no statutory prescription like our s.17A(6) since 1981.
[6] As it happens, the evidence in question is now challenged: for it is submitted by the respondent (the principal) that the points of claim were sent to the superintendent, not by the solicitors for the contractor, but by its own solicitors; but that does not matter for present purposes.
[10] Sanofi v. Parke Davis Pty Ltd (No.1) [1982] HCA 9; (1982) 149 C.L.R. 147 at 153; [1995] VICSC 219; [1996] 1 V.R. 457 at 460; Coles Myer Ltd v. Bowman [1995] VICSC 219; [1996] 1 V.R. 457 at 460.
Southern Region Pty Ltd
Minister for Police & Emergency Services for and on behalf of the State of Victoria [2003] VSCA 105