The Body Corporate for South Pacific Lodge (respondent)
Body Corporate and Community Management Act 1997 (Qld) (Act), and (3)(a)
Body Corporate and Community Management (Accommodation Module) Regulation 2020 (Accommodation Module)
APPLICATION FOR INTERIM ORDER - where the applicant says the body corporate has reconfigured a boundary fence enclosing an area of common property within the courtyard of Lot 9 - where the applicant argues this was done without the proper authority - whether the interim order sought by the applicant is warranted in the circumstances.
(a) Convene an extraordinary general meeting (EGM) to allow all lot owners to vote on a motion proposing to authorise the enclosure and exclusive use of the approximately 1.92 m² of common property adjacent to Lot 9, in accordance with section 169 of the Accommodation Module (resolution without dissent required), ensuring all owners are properly notified under sections 85-88 of the Accommodation Module; and, should the motion pass without dissent, to:
Lodge a new Community Management Statement (CMS) to register for CTS 16292 under section 173 of the Accommodation Module and section 47B of the Land Title Act 1994 (Qld); and
Have the Body Corporate to recover funds from the lot owner the respondent is the Body Corporate The Owner of Lot 9 to pay the Body Corporate $31,960, comprising:
- $16,652 for future land valuation
- $15,308 for administrative costs associated with updating the CMS, Titles, Body Corporate records, and BUP - See Footnote1: Price calculation
- Body Corporate to update all records, CMS, titles, and BUP to reflect the valuation and payment including:
- the registered CMS for CTS 16292;
- the Building Units Plan (BUP 103922), as boundary realignment is required; and
- the Body Corporate records and minutes to accurately reflect the change.
- The total payable amount shall be recorded in the Body Corporate records in accordance with Sections 180 and 182 of the BCCM Standard Module Regulation 2020.
(b) Remove the new fence and reinstate the boundary fence to its original lawful alignment and setback of 1250 mm, as recorded on Building Units Plan BUP 103922 and the current CMS for CTS 16292.
That the Body Corporate and members be restrained from modifying structures, preparing, resolving, or lodging any CMS amendments until final adjudication.
Consideration of legal issues and likelihood of success
Ordinary Resolution - Proposed by Owner, Anita Nolan, Lot: 7
That the Body Corporate reinstate the boundary fence section on the front border of Lot 9; as it was prior to the fence replacement and in accordance with the current Community Title Scheme CTS 16292. - See Attachment B - Image 5 - Set back 1250mm.
That the Body Corporate ratify the approvals given by the Committee to the Owner of Lot 9 to:
1. Use the area to house potted (moveable) plants
2. Maintain the area in good order and condition, at her own expense
3. Concrete and epoxy the surface of the area at her own expense.
Nature or urgency of circumstances and the balance of harm
[2] For general principles see: Australian Broadcasting Corporation v O'Neill [2006] HCA 46 and SDW2 Pty Ltd v JLF Corporation Pty Ltd & Ors [2017] QSC 1
[4] The committee refers to By-laws 6 and 9.
[5] See City Views [2023] QBCCMCmr 379