"Internal and external plumbing works to service a 2-bedroom 2-bathroom dwelling serviced by a dual-purpose septic tanks with absorption trenches and outbuilding."
Inground water tank installed without applicable approval. Within 14 days: a design by a suitably qualified person, and Certificate of Certification for the tanks and associated plumbing connection works, demonstrating compliance with the National Construction Code TAS B1D7, can be offered for consideration and amendment to the Plumbing Permit PA-PPW-60/2023.
The National Construction Code (NCC) is an initiative of the Council of Australian Governments developed to incorporate all on-site construction requirements into a single code. The NCC is produced and maintained by the Australian Building Codes Board (ABCB) on behalf of the Australian Government and each State and Territory government. The NCC is a uniform set of technical provisions for the design and construction of building and other structures, and plumbing and drainage systems throughout Australia. It allows for variations in climate and geological or geographic conditions.
in the Tasmanian Planning Scheme under the Land Use Planning and Approvals Act 1993.
(1) Stored rainwater must reduce the likelihood of contamination. > > (2) Stored rainwater must not pose a hazard to public health.
(1) Where a Deemed-to-Satisfy Solution is proposed, Performance Requirements B7P1 and B7P4 are satisfied by complying with B7D2 and B7D3. > > (2) Where a Performance Solution is proposed, the relevant Performance Requirements must be determined in accordance with A2G2(3) and A2G4(3) as applicable.
(1) Rainwater storage must only collect roof water. > > (2) A rainwater storage system for Class 1 and Class 10 buildings satisfies B7D1 if it is installed in accordance with the requirements within the Tasmanian Building Act - Directors Guidelines - Charged Downpipes to Rainwater Tanks of Class 1 and Class 10 buildings for drinking water purposes document.
This guideline provides guidance to plumbing permit authorities and contractors on the installation or charged down pipes on Class 1a & 10 buildings for drinking water purposes.
This Guideline is to confirm that the details in relation to charged downpipes that are installed in accordance with this guide note have been determined to be a "deemed to satisfy solution" in Tasmania and rated as low risk plumbing work in Category 2B.
Statutory construction involves attribution of legal meaning to statutory text, read in context. "Ordinarily, that meaning (the legal meaning) will correspond with the grammatical meaning ... But not always." Context sometimes favours an ungrammatical legal meaning. Ungrammatical legal meaning sometimes involves reading statutory text as containing implicit words. Implicit words are sometimes words of limitation. They are sometimes words of extension. But they are always words of explanation. The constructional task remains throughout to expound the meaning of the statutory text, not to divine unexpressed legislative intention or to remedy perceived legislative inattention. Construction is not speculation, and it is not repair. [Citations omitted]
Answer: No. 2. If the answer to the question above is 'yes', do the Guidelines require above-ground storage, therefore where below-ground storage is proposed such a system cannot satisfy the Guidelines (therefore a Performance Solution is required to satisfy Performance Requirement B7P1 (Contamination control))?
Answer: Does not arise. 2. This disposes of the preliminary issue but not the appeal itself. I direct that the appeal be listed for directions on a date to be fixed.
SJM Property Developments Pty Ltd
Huon Valley Council [2025] TASCAT 114
(2014) 253 CLR 531
(2021) 34 Tas R 341