Architectural Drawings prepared by Signature Property Developers Pty Ltd Ground & First Floor Plan 29/10/2018 K Demolition Plan 3/09/2018 D Landscaping, Site & Waste Management Plan 2/11/2018 J Site Analysis 3/09/2018 C Typical cross section through East-West portion of laneways 28/09/2018 A Retaining Walls Plan 2/11/2018 A Individual house plans for Community Plan 1 CP 1 - LOT 2 - drawing no. DA-01 3/09/2018 E CP 1 - LOT 2 - drawing no. DA-02 3/09/2018 E CP 1 - LOT 2 - drawing no. DA-03 3/09/2018 E CP 1 - LOT 2 - drawing no. DA-04 3/09/2018 E CP 1 - LOT 3 - drawing no. DA-01 3/09/2018 E CP 1 - LOT 3 - drawing no. DA-02 3/09/2018 E CP 1 - LOT 3 - drawing no. DA-03 3/09/2018 E CP 1 - LOT 3 - drawing no. DA-04 3/09/2018 E CP 1 - LOT 4 - drawing no. DA-01 3/09/2018 E CP 1 - LOT 4- drawing no. DA-02 3/09/2018 E CP 1 - LOT 4 - drawing no. DA-03 3/09/2018 E CP 1 - LOT 4 - drawing no. DA-04 3/09/2018 E CP 1 - LOT 5 - drawing no. DA-01 3/09/2018 E CP 1 - LOT 5- drawing no. DA-02 3/09/2018 E CP 1 - LOT 5 - drawing no. DA-03 3/09/2018 E CP 1 - LOT 5 - drawing no. DA-04 3/09/2018 E CP 1 - LOT 6 - drawing no. DA-01 3/09/2018 E CP 1 - LOT 6 - drawing no. DA-02 3/09/2018 E CP 1 - LOT 6 - drawing no. DA-03 3/09/2018 E CP 1 - LOT 6 - drawing no. DA-04 3/09/2018 E CP 1 - LOT 7 - drawing no. DA-01 3/09/2018 E CP 1 - LOT 7 - drawing no. DA-02 3/09/2018 E CP 1 - LOT 7 - drawing no. DA-03 3/09/2018 E CP 1 - LOT 7 - drawing no. DA-04 3/09/2018 E CP 1 - LOT 8 - drawing no. DA-01 3/09/2018 E CP 1 - LOT 8 - drawing no. DA-02 3/09/2018 E CP 1 - LOT 8 - drawing no. DA-03 3/09/2018 E CP 1 - LOT 8 - drawing no. DA-04 3/09/2018 E CP 1 - LOT 9 - drawing no. DA-01 25/10/2018 F CP 1 - LOT 9 - drawing no. DA-02 3/09/2018 E CP 1 - LOT 9 - drawing no. DA-03 3/09/2018 E CP 1 - LOT 9 - drawing no. DA-04 3/09/2018 E CP 1 - LOT 9 - drawing no. DA-05 3/09/2018 E CP 1 - LOT 9 - drawing no. DA-06 3/09/2018 E CP 1 - LOT 10 - drawing no. DA-01 25/10/2018 F CP 1 - LOT 10 - drawing no. DA-02 3/09/2018 E CP 1 - LOT 10 - drawing no. DA-03 3/09/2018 E CP 1 - LOT 10 - drawing no. DA-04 3/09/2018 E CP 1 - LOT 10 - drawing no. DA-05 3/09/2018 E CP 1 - LOT 10 - drawing no. DA-06 3/09/2018 E CP 1 - LOT 11 - drawing no. DA-01 3/09/2018 E CP 1 - LOT 11 - drawing no. DA-02 3/09/2018 E CP 1 - LOT 11 - drawing no. DA-03 3/09/2018 E CP 1 - LOT 11 - drawing no. DA-04 3/09/2018 E CP 1 - LOT 12 - drawing no. DA-01 3/09/2018 E CP 1 - LOT 12 - drawing no. DA-02 3/09/2018 E CP 1 - LOT 12 - drawing no. DA-03 3/09/2018 E CP 1 - LOT 12 - drawing no. DA-04 3/09/2018 E CP 1 - LOT 13 - drawing no. DA-01 3/09/2018 E CP 1 - LOT 13 - drawing no. DA-02 3/09/2018 E CP 1 - LOT 13 - drawing no. DA-03 3/09/2018 E CP 1 - LOT 13 - drawing no. DA-04 3/09/2018 E CP 1 - LOT 14 - drawing no. DA-01 3/09/2018 E CP 1 - LOT 14 - drawing no. DA-02 3/09/2018 E CP 1 - LOT 14 - drawing no. DA-03 3/09/2018 E CP 1 - LOT 14 - drawing no. DA-04 3/09/2018 E CP 1 - LOT 15 - drawing no. DA-01 3/09/2018 E CP 1 - LOT 15 - drawing no. DA-02 3/09/2018 E CP 1 - LOT 15 - drawing no. DA-03 3/09/2018 E CP 1 - LOT 15 - drawing no. DA-04 3/09/2018 E CP 1 - LOT 16 - drawing no. DA-01 3/09/2018 E CP 1 - LOT 16 - drawing no. DA-02 3/09/2018 E CP 1 - LOT 16 - drawing no. DA-03 3/09/2018 E CP 1 - LOT 16 - drawing no. DA-04 3/09/2018 E CP 1 - LOT 17 - drawing no. DA-01 3/09/2018 E CP 1 - LOT 17 - drawing no. DA-02 3/09/2018 E CP 1 - LOT 17 - drawing no. DA-03 3/09/2018 E CP 1 - LOT 17 - drawing no. DA-04 3/09/2018 E CP 1 - LOT 18 - drawing no. DA-01 29/10/2018 G CP 1 - LOT 18 - drawing no. DA-02 2/11/2018 F CP 1 - LOT 18 - drawing no. DA-03 3/09/2018 E CP 1 - LOT 18 - drawing no. DA-04 3/09/2018 E CP 1 - LOT 18 - drawing no. DA-05 2/11/2018 F CP 1 - LOT 18 - drawing no. DA-06 2/11/2018 F
Individual house plans for Community Plan 2 CP 2 - LOT 2 - drawing no. DA-01 2/11/2018 F CP 2 - LOT 2 - drawing no. DA-02 3/09/2018 E CP 2 - LOT 2 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 2 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 3 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 3 - drawing no. DA-02 3/09/2018 E CP 2 - LOT 3 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 3 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 4 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 4 - drawing no. DA-02 3/09/2018 E CP 2 - LOT 4 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 4 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 5 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 5- drawing no. DA-02 3/09/2018 E CP 2 - LOT 5 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 5 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 6 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 6 - drawing no. DA-02 3/09/2018 E CP 2 - LOT 6 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 6 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 7 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 7 - drawing no. DA-02 3/09/2018 E CP 2 - LOT 7 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 7 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 8 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 8 - drawing no. DA-02 3/09/2018 E CP 2 - LOT 8 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 8 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 9 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 9 - drawing no. DA-02 3/09/2018 E CP 2 - LOT 9 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 9 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 10 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 10 - drawing no. DA-02 3/09/2018 E CP 2 - LOT 10 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 10 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 11 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 11 - drawing no. DA-02 3/09/2018 E CP 2 - LOT 11 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 11 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 12 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 12 - drawing no. DA-02 3/09/2018 E CP 2 - LOT 12 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 12 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 13 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 13 - drawing no. DA-02 3/09/2018 E CP 2 - LOT 13 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 13 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 14 - drawing no. DA-01 25/10/2018 F CP 2 - LOT 14 - drawing no. DA-02 2/11/2018 F CP 2 - LOT 14 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 14 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 14 - drawing no. DA-05 3/09/2018 E CP 2 - LOT 14 - drawing no. DA-06 3/09/2018 E CP 2 - LOT 15 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 15 - drawing no. DA-02 2/11/2018 F CP 2 - LOT 15 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 15 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 16 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 16 - drawing no. DA-02 3/09/2018 E CP 2 - LOT 16 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 16 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 17 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 17 - drawing no. DA-02 3/09/2018 E CP 2 - LOT 17 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 17 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 18 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 18 - drawing no. DA-02 3/09/2018 E CP 2 - LOT 18 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 18 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 19 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 19 - drawing no. DA-02 3/09/2018 E CP 2 - LOT 19 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 19 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 20 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 20 - drawing no. DA-02 3/09/2018 E CP 2 - LOT 20 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 20 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 21 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 21 - drawing no. DA-02 3/09/2018 E CP 2 - LOT 21 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 21 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 22 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 22 - drawing no. DA-02 3/09/2018 E CP 2 - LOT 22 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 22 - drawing no. DA-04 3/09/2018 E CP 2 - LOT 23 - drawing no. DA-01 3/09/2018 E CP 2 - LOT 23 - drawing no. DA-02 3/09/2018 E CP 2 - LOT 23 - drawing no. DA-03 3/09/2018 E CP 2 - LOT 23 - drawing no. DA-04 3/09/2018 E
Individual house plans for Community Plan 3 CP 3 - LOT 2 - drawing no. DA-01 3/09/2018 E CP 3 - LOT 2 - drawing no. DA-02 3/09/2018 E CP 3 - LOT 2 - drawing no. DA-03 3/09/2018 E CP 3 - LOT 2 - drawing no. DA-04 3/09/2018 E CP 3 - LOT 3 - drawing no. DA-01 3/09/2018 E CP 3 - LOT 3 - drawing no. DA-02 3/09/2018 E CP 3 - LOT 3 - drawing no. DA-03 3/09/2018 E CP 3 - LOT 3 - drawing no. DA-04 3/09/2018 E CP 3 - LOT 4 - drawing no. DA-01 3/09/2018 E CP 3 - LOT 4- drawing no. DA-02 3/09/2018 E CP 3 - LOT 4 - drawing no. DA-03 3/09/2018 E CP 3 - LOT 4 - drawing no. DA-04 3/09/2018 E CP 3 - LOT 5 - drawing no. DA-01 3/09/2018 E CP 3 - LOT 5- drawing no. DA-02 3/09/2018 E CP 3 - LOT 5 - drawing no. DA-03 3/09/2018 E CP 3 - LOT 5 - drawing no. DA-04 3/09/2018 E CP 3 - LOT 6 - drawing no. DA-01 3/09/2018 E CP 3 - LOT 6 - drawing no. DA-02 3/09/2018 E CP 3 - LOT 6 - drawing no. DA-03 3/09/2018 E CP 3 - LOT 6 - drawing no. DA-04 3/09/2018 E CP 3 - LOT 7 - drawing no. DA-01 3/09/2018 E CP 3 - LOT 7 - drawing no. DA-02 3/09/2018 E CP 3 - LOT 7 - drawing no. DA-03 3/09/2018 E CP 3 - LOT 7 - drawing no. DA-04 3/09/2018 E CP 3 - LOT 8 - drawing no. DA-01 3/09/2018 E CP 3 - LOT 8 - drawing no. DA-02 3/09/2018 E CP 3 - LOT 8 - drawing no. DA-03 3/09/2018 E CP 3 - LOT 8 - drawing no. DA-04 3/09/2018 E CP 3 - LOT 9 - drawing no. DA-01 3/09/2018 E CP 3 - LOT 9 - drawing no. DA-02 3/09/2018 E CP 3 - LOT 9 - drawing no. DA-03 3/09/2018 E CP 3 - LOT 9 - drawing no. DA-04 3/09/2018 E CP 3 - LOT 10 - drawing no. DA-01 3/09/2018 E CP 3 - LOT 10 - drawing no. DA-02 3/09/2018 E CP 3 - LOT 10 - drawing no. DA-03 3/09/2018 E CP 3 - LOT 10 - drawing no. DA-04 3/09/2018 E CP 3 - LOT 11 - drawing no. DA-01 3/09/2018 E CP 3 - LOT 11 - drawing no. DA-02 3/09/2018 E CP 3 - LOT 11 - drawing no. DA-03 3/09/2018 E CP 3 - LOT 11 - drawing no. DA-04 3/09/2018 E CP 3 - LOT 12 - drawing no. DA-01 3/09/2018 E CP 3 - LOT 12 - drawing no. DA-02 3/09/2018 E CP 3 - LOT 12 - drawing no. DA-03 3/09/2018 E CP 3 - LOT 12 - drawing no. DA-04 3/09/2018 E CP 3 - LOT 13 - drawing no. DA-01 3/09/2018 E CP 3 - LOT 13 - drawing no. DA-02 3/09/2018 E CP 3 - LOT 13 - drawing no. DA-03 3/09/2018 E CP 3 - LOT 13 - drawing no. DA-04 3/09/2018 E CP 3 - LOT 14 - drawing no. DA-01 25/10/2018 G CP 3 - LOT 14 - drawing no. DA-02 2/11/2018 G CP 3 - LOT 14 - drawing no. DA-03 10/09/2018 F CP 3 - LOT 14 - drawing no. DA-04 10/09/2018 F CP 3 - LOT 14 - drawing no. DA-05 2/11/2018 G CP 3 - LOT 14 - drawing no. DA-06 2/11/2018 G CP 3 - LOT 15 - drawing no. DA-01 10/09/2018 F CP 3 - LOT 15 - drawing no. DA-02 10/09/2018 F CP 3 - LOT 15 - drawing no. DA-03 10/09/2018 F CP 3 - LOT 15 - drawing no. DA-04 10/09/2018 F CP 3 - LOT 16 - drawing no. DA-01 10/09/2018 F CP 3 - LOT 16 - drawing no. DA-02 10/09/2018 F CP 3 - LOT 16 - drawing no. DA-03 10/09/2018 F CP 3 - LOT 16 - drawing no. DA-04 10/09/2018 F CP 3 - LOT 17 - drawing no. DA-01 10/09/2018 F CP 3 - LOT 17 - drawing no. DA-02 10/09/2018 F CP 3 - LOT 17 - drawing no. DA-03 10/09/2018 F CP 3 - LOT 17 - drawing no. DA-04 10/09/2018 F CP 3 - LOT 18 - drawing no. DA-01 10/09/2018 F CP 3 - LOT 18 - drawing no. DA-02 10/09/2018 F CP 3 - LOT 18 - drawing no. DA-03 10/09/2018 F CP 3 - LOT 18 - drawing no. DA-04 10/09/2018 F CP 3 - LOT 19 - drawing no. DA-01 10/09/2018 F CP 3 - LOT 19 - drawing no. DA-02 10/09/2018 F CP 3 - LOT 19 - drawing no. DA-03 10/09/2018 F CP 3 - LOT 19 - drawing no. DA-04 10/09/2018 F CP 3 - LOT 20 - drawing no. DA-01 10/09/2018 F CP 3 - LOT 20 - drawing no. DA-02 10/09/2018 F CP 3 - LOT 20 - drawing no. DA-03 10/09/2018 F CP 3 - LOT 20 - drawing no. DA-04 10/09/2018 F CP 3 - LOT 21 - drawing no. DA-01 10/09/2018 F CP 3 - LOT 21 - drawing no. DA-02 10/09/2018 F CP 3 - LOT 21 - drawing no. DA-03 10/09/2018 F CP 3 - LOT 21 - drawing no. DA-04 10/09/2018 F CP 3 - LOT 22 - drawing no. DA-01 10/09/2018 F CP 3 - LOT 22 - drawing no. DA-02 10/09/2018 F CP 3 - LOT 22 - drawing no. DA-03 10/09/2018 F CP 3 - LOT 22 - drawing no. DA-04 10/09/2018 F CP 3 - LOT 23 - drawing no. DA-01 10/09/2018 F CP 3 - LOT 23 - drawing no. DA-02 10/09/2018 F CP 3 - LOT 23 - drawing no. DA-03 10/09/2018 F CP 3 - LOT 23 - drawing no. DA-04 10/09/2018 F
BASIX Certificates LOT NUMBERS BASIX CERTIFICATE NUMBERS CP1-LOT 2 873605S CP1-LOT 3 874013S CP1-LOT 4 864512S CP1-LOT 5 864773S CP1-LOT 6 875481S CP1-LOT 7 875494S CP1-LOT 8 876631S CP1-LOT 9 888239M CP1-LOT 10 888134M CP1-LOT 11 876599S CP1-LOT 12 875542S CP1-LOT 13 875336S CP1-LOT 14 875094S CP1-LOT 15 873548S CP1-LOT 16 873574S CP1-LOT 17 875502S_02 CP1-LOT 18 888286M CP2-LOT 2 875851S CP2-LOT 3 875842S CP2-LOT 4 874645S CP2-LOT 5 874584S CP2-LOT 6 875678S CP2-LOT 7 875699S CP2-LOT 8 874806S CP2-LOT 9 874807S CP2-LOT 10 875859S CP2-LOT 11 876329S CP2-LOT 12 877064S CP2-LOT 13 876941S CP2-LOT 14 877448M CP2-LOT 15 877091S CP2-LOT 16 876312S CP2-LOT 17 875886S CP2-LOT 18 874835S CP2-LOT 19 874851S CP2-LOT 20 875710S CP2-LOT 21 875707S CP2-LOT 22 874865S CP2-LOT 23 874873S CP3-LOT 2 876465S CP3-LOT 3 876289S CP3-LOT 4 876267S CP3-LOT 5 876269S CP3-LOT 6 876259S CP3-LOT 7 876261S CP3-LOT 8 876051S CP3-LOT 9 876246S CP3-LOT 10 876242S CP3-LOT 11 876309S CP3-LOT 12 877129S CP3-LOT 13 876959S CP3-LOT 14 887288M CP3-LOT 15 887967S CP3-LOT 16 876370S CP3-LOT 17 876238S CP3-LOT 18 876214S CP3-LOT 19 876211S CP3-LOT 20 876188S CP3-LOT 21 876180S CP3-LOT 22 876231S CP3-LOT 23 875960S
Engineering Plans prepared by Advent Consulting Engineers Drawing Reference Dated Revision Locality Plan and Drawing Schedule, drawing no C001 01/11/2018 H General Notes, drawing no C002 17/04/2018 C Council Precinct Plan ILP Overlay, drawing no C003 03/09/2018 C Bulk Earthworks Plan, drawing no's C100 - C103 20/09/2018 G Roadworks & Stormwater Drainage Layout, drawing no C200 01/11/2018 K Road Works Typical Details, Sheet 1 of 2, drawing no C201 11/09/2018 F Road Works Typical Details, Sheet 2 of 2, drawing no C202 17/04/2018 C Tallawong Road, Longitudinal Section, drawing no C203 17/04/2018 C Tallawong Road Cross Sections CH 990 to H1065), drawing no C204 17/04/2018 C Road 1 Longitudinal Section, drawing no C205 11/09/2018 G Road 1 Cross Sections (CH 15 to CH 180), drawing no C206 11/09/2018 G Road 1 Cross Sections (CH 195 to CH 300), drawing no C207 11/09/2018 G Road 2 Longitudinal & Cross Sections, drawing no C208 11/09/2018 G Road 3 Longitudinal & Cross Sections, drawing no C209 11/09/2018 G Road 4 Longitudinal & Cross Sections, drawing no C210 11/09/2018 G Access Lane 1 Longitudinal & Cross Sections, drawing no C211 25/09/2018 G Access Lane 2 Longitudinal & Cross Sections, drawing no C212 25/09/2018 G Access Lane 3 Longitudinal & Cross Sections, drawing no C213 25/09/2018 G Roadworks Swept Paths, drawing no C215 10/09/2018 B Roadworks & Stormwater Drainage Layout (Ultimate), drawing no C216 01/11/2018 B Stormwater Catchment Plan & Details, drawing no C300 01/11/2018 H Stormwater Standard Details & Roofwater Outlet Connection Details, drawing no C301 17/04/2018 C Typical Stormwater Pit Details, drawing no C302 17/04/2018 C OSD 1 & 2 Pit Schedule drawing no C303 01/11/2018 E OSD 3 Pit Schedule, drawing no C304 01/11/2018 E Allotment Stormwater Drainage Connection & Driveway Location Plan - Stage 1, drawing no C305 01/11/2018 G Allotment Stormwater Drainage Connection & Driveway Location Plan - Stage 2, drawing no C306 01/11/2018 G Allotment Stormwater Drainage Connection & Driveway Location Plan - Stage 3, drawing no C307 01/11/2018 G OSD Tank 1 Layout Plan & Sections, drawing no C310 11/09/2018 F OSD 1 Longitudinal Section Q100, drawing no C311 01/11/2018 E OSD 1 Longitudinal Section Q5, drawing no C312 01/11/2018 E OSD Longitudinal Section, Q100, drawing no C313 01/11/2018 E OSD Longitudinal Section Q5, drawing no C314 01/11/2018 E OSD 3 Longitudinal Section Q100, drawing no C315 01/11/2018 E OSD 3 Longitudinal Section Q5, drawing no C316 01/11/2018 G OSD Tank 2 Layout Plan & Sections, drawing no C317 11/09/2018 D OSD Tank 3 Layout Plan & Sections, drawing no C318 11/09/2018 D Sub OSD Layout Plan & Section, drawing no C319 11/09/2018 C OSD Tank 3 Sections, drawing no C320 11/09/2018 C Inter-Allotment SWD Longitudinal Sections, drawing no C321 01/11/2018 A Inter-Allotment SWD Pit Schedule, drawing no C322 01/11/2018 A Erosion and Sediment Control Plan, drawing no C400 01/11/2018 G Erosion and Sediment Control Details, drawing no C401 17/04/2018 C Staging Plan, drawing no C410 03/09/2018 E Music Model Area Calculation, drawing no C500 11/09/2018 G
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 07 February 2019
Signature Properties No. 2 Pty. Ltd.
Blacktown City Council