[2018] VCAT 1864
Victorian Civil and Administrative Tribunal
2018-11-27
Mr J
Original judgment source is linked above.
The Builder's entitlement to extra for rock removal
"14.1 Builder generally not entitled to extra amounts for excavations or footings
After entering into this Contract the Builder cannot seek from the Owner an amount of money not already provided for in the Original Contract Price if the additional amount could reasonably have been ascertained had the Builder obtained all the Foundations Data required under the Act.
14.2 Builder's entitlement to extra amounts for excavation and footings
The Builder will be entitled to claim an amount of money not already provided for in the Original Contract Price if the need for the additional amount could not reasonably have been ascertained from the Foundations Data.
14.3 Owner to pay additional cost of Builder entitled to extra amount
If the Builder is entitled to any additional amounts which could not reasonably have been ascertained for excavations or footings under this Contract or the Act, the Owner will pay to the Builder, in the Builder's next progress claim, the agreed cost of the additional work or, if the cost is not agreed, the cost incurred by the Builder plus15% for the Builder's margin."
(a) the information concerning the building site that a Builder exercising reasonable care and skill would need to prepare -
(ii) an adequate estimate of the cost of constructing those footings; and
(b) any reports, surveys, test results, plans, specifications, computations or other information required by the regulations for the purposes of this section.
(4) In deciding whether he, she or it has obtained all the information required by subsection (2), a Builder must have regard to -
(a) the relevant standards published by Standards Australia; and
(b) the need for a drainage plan or Engineer's drawings and computations; and
(c) the need for information on the fall of the Land on the site."
This definition is adopted in Clause 1.0 of the Contract.
"All edge beans, internal beams, strip, and pad footings are to be founded at least 100 mm into the natural stiff clay soil with a minimum allowable bearing capacity of 150 kPa as a guide. Based on the geotechnical report, the founding depth will be 1000 mm below the existing ground surface level."
Rain water tanks (x4), including pump and connections $14,000.00
"As discussed I need turn key ready to rent landscape, floor covering, fly screens and door steps included. Builder's range is ok. Crossing and mailboxes by builder. All connection ready as per utility requirements. I have utility connection fees only."
"I have received proposed landscape from Phillip and my response to him is also attached.
I can go back and insist he updates or you can ask Glenn to update
I have no preference for any layout apart from lawn where possible rather than garden beds no tenant looks after garden beds. They do mow the lawn.
Simplest/cheapest the council will accept that you know you preference." (sic.)
"The contract documents, including working drawings, colour selection, specifications of the building contract make up the total works to be performed. The home will be built in accordance with these documents. Any items not specified in the documentation will not be included." (sic.)
"The variation is accepted to the footings subject to itemised bill/costing to be provided to enable their costs to be paid. Please itemise pricing to indicate work done and to be done and cost of each. If agreeable I will pass on to sworn surveyor to confirm."
"I understand that the variation has again been rejected. This is in breach of clause 22.1 of the Contract as a refusal to consent to any reasonable or necessary variation requested by the Builder under clause 13.
This letter constitutes written notice under clause 22.1 of the Builder's intention to terminate the Contract unless you remedy the breach by consenting to that variation within 14 days after receipt of this notice."
"With reference to written notice dated 03 February 2016 sent by registered post, I have failed to receive an acceptance of the variation of contract. As such I hereby terminate the contract to build four double storey domestic buildings at 53 Warranga Crescent Broadmeadows."
AND TAKE FURTHER NOTICE that due to your wrongful termination and repudiation of the Building Contract in its entirety, Mr Sen hereby exercises his right to immediately terminate the Building Contract, and further reserves all his other rights, including his right to initiate proceedings against you in respect of loss and damage suffered as a consequence of your conduct." (sic.)
"Repudiation of a contract is a serious matter and is not to be lightly found or inferred: Ross T. Smyth & Co., Ltd. v. T.D. Bailey, Son & Co. (1940) 3 A11 ER 60, at p 71. In considering it, one must look to all the circumstances of the case to see whether the conduct "amounts to a renunciation, to an absolute refusal to perform the contract_": Mersey Steel and Iron Co. v. Naylor, Benzon & Co._ (1884) 9 App Cas 434, at p 439."
"Repudiation is not ascertained by an inquiry into the subjective state of mind of the party in default; it is to be found in the conduct, whether verbal or other, of the party in default which conveys to the other party the defaulting party's inability to perform the contract or promise or his intention not to perform it or to fulfil it only in a manner substantially inconsistent with his obligations and not in any other way."
"... may fairly and reasonably be considered either [as] arising naturally, that is, according to the usual course of things, from such breach of contract itself or ... may reasonably be supposed to have been in the contemplation of both parties, at the time they made a contract, as the probable result of the breach of it."
(Hadley v. Baxendale (1854) 156 ER 145 (at p. 151) ).
"The "ruling principle"... confirmed in this Court on numerous occasions..., with respect to damages at common law for breach of contract is that stated by Parke B in Robinson v Harman [1848] EngR 135; (1848) 154 ER 363 at 365):
"The rule of the common law is, that where a party sustains a loss by reason of a breach of contract, he is, so far as money can do it, to be placed in the same situation, with respect to damages, as if the contract had been performed."
Shen
Hatfield