What is the meaning of the words 'Site Employee access gates'?
49 The case was opened by both parties on the basis that it was the gates on the perimeter of the Project Site that were the possible Site Employee access gates for the purposes of the Agreement. There was said to be some minor disagreement as to precisely where they were located, but there was no contention advanced to the effect that gates at some other location might be Site Employee access gates. The issues were joined in the following way.
50 Clause 40 of the Agreement provides as follows:
40. SITE SECURITY
(1) (a) Bechtel will determine a system of entry to and exit from the Site. The system will include a method of personal identification for each Company Employee. The system may include computerised personnel access facilities activated by electronic or magnetic cards or by other means.
(b) Information gathered may be used by the Company to verify an Employee's attendance for timekeeping and safety purposes.
(c) An Employee must display or produce on request the form of personal identification issued for the purpose of working on the Project when seeking entry to and exit from the Site, or at any time whilst on the Site.
(d) Any Employee who allows or is involved in the unauthorised use of personal identification shall be subject to dismissal for misconduct.
(2) Any Employee who takes a lighter, matches, mobile telephone, camera or other source of ignition or other prohibited objects onto the Site or who smokes outside of a designated area approved by the Company and the Wheatstone Project Site shall be deemed to be guilty of serious misconduct and may be liable for dismissal.
(3) All Project Employees will be subject to baggage and vehicle searches on entering or leaving any work area or the Site. Employees who refuse to permit baggage or vehicle searches may be subject to disciplinary measures including dismissal.
51 Mr Sheehan relied upon the terms of cl 40, particularly the terms of cl 40(3) for the proposition that the Agreement used the term Site to refer to the Project Site as distinct from the work area where Thiess employees may be undertaking particular work that was covered by the Agreement.
52 In his statement of claim, Mr Sheehan alleged that the main access gate or the AR2 gate were the Site Employee access gates, stating that all employees in the claim group were required to enter the site for the Wheatstone Project via those gates which were operated by Bechtel.
53 In its defence, Thiess said that all employees entering and exiting the Wheatstone Project did so at various entry and exit points on the main site perimeter or from borrow pits adjacent to the main site, and records were kept of the entry and exit. In response to the specific plea that the main access gate and the AR2 gate were the Site Employee access gates for the purposes of cl 16(9), Thiess denied the factual allegation and said that (a) cl 16 does not refer to cl 40 nor vice versa; (b) cl 40 does not refer to gates at all; (c) the term access gates was not defined; and (d) cl 16(9) referred to 'access gates' in relation to the geographical parameters of Project Working Hours. It was also said that Thiess had no control over the location of the gates. The plea put in issue the factual part of the claim that the two identified perimeter gates met the description of Site Employee access gates as used in cl 16(9) and also articulated Thiess's position as to the legal meaning of cl 16(9). No case was advanced that there were some other gates that were the Site Employee access gates.
54 In written opening submissions, Mr Sheehan contended for the proposition that the main access gate, the AR2 gate and the AR4 gate were each Site Employee access gates and relied upon the terms of cl 40 to support that position. Thiess raised no objection to the addition of the claim concerning the AR4 gate (being the gate that provided direct access to the borrow pits on the site, being a place of access that Thiess had referred to in its defence).
55 In its written opening submissions, Thiess dealt with the claim on the basis that the journey between the crib huts and the access gates on the perimeter of the Project Site was not work and cl 16(9) did no more than impose a geographic restriction on employees accruing Project Working Hours. The submissions contained no reference to an argument to the effect that the access gates identified by Mr Sheehan were not the gates for the purposes of cl 16(9). On the contrary, the argument for Thiess was premised on the basis that cl 16(9) referred to gates at the perimeter of the Project Site. Further, there was no claim over to the effect that if Mr Sheehan's claim as to the proper construction was correct then cl 16(9) referred to some gate or gates other than the three gates identified by Mr Sheehan.
56 In oral opening submissions, counsel for Mr Sheehan noted that there was a dispute as to whether the three gates were Site Employee access gates for the purposes of cl 16(9), but there was no claim that there were any other access gates. It was said that, by reason of the pleadings, Mr Sheehan had not come to meet a case to the effect that there was some other gate that was the access gate for the purposes of the Agreement. The submission was properly made, because no affirmative case was advanced by Thiess. However, the denial that the three perimeter gates were in fact the Site Employee access gates remained in place.
57 Counsel for Thiess opened orally on the basis that the answer to the third common question was fairly well resolved between the parties and there were three gates in question and on Thiess's case they were all on the perimeter of the Project Site. Therefore, so it was submitted, the main question for the Court concerned the submission advanced for Thiess that cl 16(9) provides a limitation on working hours by disentitling employees from claiming for payment in relation to time spent outside of the access gates. Indeed, it was submitted that the 'entire matter … hangs on this question'. These submissions if not a concession of the factual position concerning the three perimeter gates, came perilously close to being so. The concession was to be implied from the manner in which Thiess advanced its defence which depended entirely upon the access gates being located on the perimeter of the Project Site, its characterisation of the second common question as being decisive and the statement that the factual issue as to the identification of the gates was fairly well resolved.
58 Part of the affidavit evidence of Mr Sheehan was then ruled inadmissible in part on the basis that it was common ground that the gates were at the perimeter. Also, an objection on the basis of relevance to part of the affidavit evidence of Mr Walford, a witness called by Thiess, concerning the alleged delineation of work areas by erecting some kind of barrier through which there was an entry point and alleged activities in maintaining those barriers at the part of the Project Site where the MOF Contract works were being undertaken was conceded by Thiess and the evidence was not read.
59 After the case for Mr Sheehan was closed, Mr Nel was called to give evidence for Thiess. He was the person responsible for the human resources function for the Wheatstone Project for Thiess at the relevant time. In the course of his cross-examination, Mr Nel gave evidence about his view of the meaning of cl 16(9) at the relevant time. He said that his interpretation was that cl 16(9) referred to a gate that needed to be inside the perimeter of the Project Site and it was the gate where employees entered the area where they were to start work each day. He said that for each of the MOF Contract, the EVT Contract and the Site Prep Contract there was a barricaded area where workers were dropped off and picked up each day. He accepted that there was no boom gate or anything blocking access across the road and it was not a place that was manned for any security check to be undertaken. It was also accepted that it was not an area that was fenced off. He described only a barricaded area. However, he said that there was a hard barricade that workers needed to walk through to get on the bus and that was the access gate.
60 In closing submissions for Thiess, counsel advanced the submission that the evidence of Mr Nel raised the possibility that there were other possible Site Employee access gates in addition to the three gates at the perimeter of the Project Site. The submission was to the effect that the evidence of Mr Nel having been received, when the Court reached its conclusion on the location of the Employee Site access gate in order to answer the third of the common questions, it must do so on the basis of all the evidence including that of Mr Nel.
61 However, it is difficult to see how there remained such a factual issue for determination. Thiess advanced no submission concerning the interpretation to be afforded the words 'Site Employee access gate' other than as part of its argument to the effect that cl 16(9) concerned a geographical limit on what might qualify for work. Inherent in that argument was a claim that the words 'Site Employee access gate' meant the gates at the perimeter of the Project Site. Indeed, in its written opening submissions Thiess alleged that the Project Site was 'bordered by a perimeter fence with various gates allowing entry and exit'. Further, it was said that the effect of cl 16(9) was that Project Working Hours could not continue when an employee was 'outside the site perimeter fence gate and so no longer on site'.
62 In those circumstances, the case was conducted on the basis that there was no legal issue as to what was meant by the Site Employee access gates. The expression referred to the gates at the perimeter of the Project Site by which access and egress from the Project Site was secured. Once the case was conducted on that basis as to the legal issues, the only factual question was whether the three gates referred to by Mr Sheehan were such perimeter gates. As matters unfolded, there was no contest between the parties on that factual question. Therefore, the main access gate, the AR2 gate and the AR4 gate were each Site Employee access gates for the purposes of cl 16(9).
63 If I am wrong in those views and there was an issue as to the meaning to be attributed to the words 'Site Employee access gate' then I would reach the same conclusion for the following reasons.
64 First, the term Site, though capitalised, is not defined. Therefore, it takes its meaning from a consideration of its particular use within the context of the Agreement as a whole.
65 Second, the Agreement is drawn on the basis that it applies to 'on-site construction work for the Wheatstone Project'. It does not seek to circumscribe or delineate any part of the Project Site for the purposes of the application of its terms. It does not refer to the locations or extent of works to be carried out by Thiess under its contracts. The decision of the Commission refers to the MOF Contract, the EVT Contract and the Site Prep Contract but does not suggest that the terms of the Agreement operate in some respect by reference to the ambit of those works. Indeed, on the evidence the works to be carried out under the Site Prep Contract extended over much of the Project Site and in that sense the work site for that contract was the Project Site.
66 Third, cl 40 refers to a system of entry to and exit from the Site determined by Bechtel. Given Bechtel's status as head contractor this is plainly a reference to the Project Site as a whole. Indeed cl 40(1)(c) refers to working on the Project in the context of entry to and exit from the Site, indicating that the term Site refers to the Project Site. Also, as previously noted, cl 40(3) refers to the possibility of searches 'on entering or leaving any work area or the Site' again indicating that Site is not used in cl 40 to refer to some work area that is confined to part of the Project Site. In the context of the terms of cl 40 which described what will occur concerning access, the reference to Site Employee access gates in cl 16(9) should be taken to refer to the gates where access to the Project Site as contemplated by cl 40 was obtained.
67 Fourth, cl 26(4) refers to Thiess being able to 'close the Site or part of the Site or reduce the number of Employees at the Site so that all or most Employees take their annual leave at the same time'. This appears to be the only other reference to the undefined term 'Site'. In context, this should be read as Thiess being able to close access to the Project Site for its employees. The provision is not concerned with an ability on the part of Thiess to cease all activities on the Site, but rather an ability to require employees to take annual leave at the same time. It is not a provision that requires focus upon the distinction between the part of the site where Thiess is undertaking work under its contracts and the Project Site as a whole and therefore is not of real assistance in dealing with what was meant when the term Site Employee access gates is used in cl 16(9).
68 Fifth, the imprecision that would arise as to the entitlement concerning the scheduling of Working Hours if cl 16(9) depended upon a point that was to be established by Thiess anywhere within the Project Area where its workers were undertaking work counts against a different construction. As does the fact that it would render the language effectively otiose if it stated no more than a requirement that the Project Working Hours finish at the place where the construction work finishes.