[2020] QCAT 271
General information, not legal advice.
Queensland Civil and Administrative Tribunal
2020-07-21
Ryan J
Original judgment source is linked above.
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
(a) Ian Woolfson entered into a contract with Rabin Sharma, Kiran Sharma and Ashan Sharma for the completion of certain renovation works to a residential property in Brisbane, Queensland.
(b) During completion of the renovation work, a dispute arose between Mr Woolfson and the Sharmas about the building work performed and money paid under the contract. One of the disputed issues concerned progress payment 6 ('PP6') issued by Mr Woolfson and alleged by him to be owing under the contract.
(c) Following attempts made by the parties to resolve the disputed issues, the Sharmas exercised their rights to terminate the contract by issuing to Mr Woolfson a notice of intention to terminate followed by a notice of termination. The Sharmas later complained to the Queensland Building and Construction Commission ('QBCC') about the building work performed by Mr Woolfson. Relevantly, the Sharmas alleged that some items of building work were defective and/or incomplete.
(d) The QBCC inspected the building work and reviewed the correspondence exchanged between Mr Woolfson and the Sharmas. The QBCC determined that the contract had been validly terminated by the Sharmas and referred the matter to its insurance branch for assessment. An independent report was prepared following an inspection of the building work by Sergon Building Consultants ('Sergon').
(e) Following an internal review of the QBCC's decision to accept the Sharmas' claim under the Insurance Scheme, the QBCC confirmed its decision dated 9 May 2018 that the contract has been validly terminated at the default of the licensee.
(f) Mr Woolfson wants to review the QBCC's decision dated 9 May 2018. Mr Woolfson says that the contract has not been properly terminated by the Sharmas. Mr Woolfson says that there was a delay to the commencement of the building work because of a change in the plans by the Sharmas. Mr Woolfson submits that there were many variations to the contract, and he did not get paid for all the work performed by him. Mr Woolfson submits that the Sharmas did not terminate the contract correctly and did not identify the specific items of substantial breach in the Notice of Intention to Terminate. Mr Woolfson says that the Sharmas did not pay PP6 in the full amount as invoiced by him. Further, Mr Woolfson says that the building works were never stopped or suspended by him and that practical completion was reached but the Sharmas refused to meet with him to enable all of the forms to be signed and completed.
(g) Further, Mr Woolfson says that he did everything he could to give the Sharmas a beautiful home referring to extra work performed by him that he says he did not claim for from the Sharmas. Mr Woolfson says that after the Sharmas complained to the QBCC, he requested a site meeting that was refused. Mr Woolfson says that he was always prepared to attend to any alleged defective work, after practical completion was signed by the Sharmas.
What is central to all definitions of a building dispute is that the essence of the contract or agreement entered into by all parties is one for the building construction, construction or associated works in this case with a domestic dwelling.
(b) $12,000 for an extra 52m2 of hardwood flooring which was not in the contract;
(c) $10,000 for the renovation of the original house which was not in the contract;
(d) $14,000 for the additional work, earthworks in concrete foundations;
Damages arising from a breach of the terms of the building contract
Are the items claimed part of the terms of the contract?
The applicants' submissions on loss of rent and mitigation of damages
"prescribe the measure of damages in respect of breach of contract to include not only damage naturally resulting from the breach ("i,e. according to the usual course of things") but also damage which might reasonably be or supposed to have been in the contemplation of both parties, at the time they made the contract, as the probable result of the breach of it".
"Additional or special knowledge know to both parties may widen or contract the scope of liability for breach. These rules have been merged in a single principle."
Respondent: Will you be borrowing money from the bank for the build?
Respondent: Will you be selling (second address)?
Applicant (Kiran): No, upon completion of the renovation work at (first address), we will move into that property and rent out the property at (second address) to produce a rental income.
The respondent's submissions on loss of rent and mitigation of damages
a friendly reminder, leaving windows and doors open so you or any unauthorised person can enter the building, will cancel any insurance and is illegal as you know as I'm the builder and the only person who can authorised entry into the site until handover is completed then it's a good idea to get your own insurance.
I understand you'll be renting out (second address) once you've moved into (first address), so it would appear you have already missed out on many $1000s in rent and many more if we do not agree on completion. Your rental losses will soon be more than the money remaining in the contract.
...The broad principle is that an award of damages for breach of contract is designed to put the innocent party in the position that party would have been in had the defaulting party performed the contract; the party who sustains loss as a result of a breach of contract is, "so far as money can do it, to be placed in the same situation, with respect to damages, as if the contract had been performed." (see Robinson v Harman [1848] EngR 135; (1848) 1 Ex 850 at 855, approved in The Commonwealth v Amann Aviation (1991)174 CLR 64). That principle is qualified by the principles concerning remoteness of damage established in Hadley v Baxendale and developed in later decisions. The relevant law was summarised by Brennan J in The Commonwealth v Amann Aviation Pty Ltd:
Where a contract is rescinded for breach, the innocent party loses the benefit of performance of the contract so far as the contract remains unperformed. And there may be other losses resulting from the breach. The rule in Hadley v Baxendale prescribes the condition on which damages can be awarded in respect of a loss sustained by reason of a breach of contract:
"Where two parties have made a contract which one of them has broken, the damages which the other party ought to receive in respect of such breach of contract should be such as may fairly and reasonably be considered either arising naturally, ie, according to the usual course of things, from such breach of contract itself, or such as may reasonably be supposed to have been in the contemplation of both parties, at the time they made the contract, as the probable result of the breach of it."
Applying the rule in C Czarnikow Ltd v Koufos, Lord Reid said that:
The crucial question is whether, on the information available to the defendant when the contract was made, he should, or the reasonable man in his position would, have realised that such loss was sufficiently likely to result from the breach of contract to make it proper to hold that the loss flowed naturally from the breach or that loss of that kind should have been within his contemplation.
...
The measure of damages prescribed by Robinson v Harman ensures that the parties to the contract are kept to the benefits and the burdens of the contract they have made: the plaintiff recovers no more than the net benefit he would have received under the contract; the defendant acquires no right to profit by his breach. (some citations omitted).
Further discussion of loss of rent and mitigation of damages in the current case
a friendly reminder, leaving windows and doors open so you or any unauthorised person can enter the building, will cancel any insurance and is illegal as you know as I'm the builder and the only person who can authorised entry into the site until handover is completed then it's a good idea to get your own insurance.
Section 77(3)(h) of the QBBC Act provides that in building disputes the Tribunal may award costs, so the usual position as to costs in the Tribunal is displaced. It means that the Tribunal can make a costs order that is justified in the circumstances. It is a broad general discretion which must be exercised judicially, not upon irrelevant or extraneous considerations but upon facts connected with or leading up to the litigation: Lyons v Dreamstarter Pty Ltd [2011] QCATA 142 Judge Kingham.
Under s.77 the question of costs is to be addressed in markedly different terms from s.100 of the QCAT Act. The High Court has said that there is no automatic rule that costs follow the event, but the discretion to award costs starts with the proposition that it is just and reasonable that a party who causes another to incur costs should reimburse the other party for them. Otherwise, the factors affecting the discretion will vary in each case: Lyons v Dreamstarter Pty Ltd [2012] QCATA 71 Justice Alan Wilson.
The discretion to award costs must be exercised judicially and in accordance with established principles. A successful litigant is, generally speaking, entitled to an order of costs, and to deprive a successful party of their costs is an exceptional measure: Rainbow Builders Pty Ltd v The State of Queensland through the Department of Housing and Public Works (No. 2) [2016] QCAT 497 Senior Member Brown.
In building cases, unlike in the QCAT Act, there is no strong contra-indication against a costs order. But it remains necessary to consider whether an award of costs is justified in the circumstances: Bartlett v Contrast Constructions Pty Ltd [2016] QCATA 199 Senior Member O'Callaghan, Member Paratz.
Section 77(3)(h) is a "modifying provision" so that it prevails over both sections 100 and 102 of the QCAT Act: Partington & Anor v Urquhart (No 4) [2019] QCATA 96 Snr Member Howard and Member Traves [11], [13], which concerned costs of the appeal in a building case.
As in Tamawood Ltd v Anor v Paans[8], whether it was necessary for a successful party to reasonably incur the cost of legal representation to achieve a satisfactory outcome is a relevant consideration in exercising the broad discretion under s.77: Mair Renovations v Miller [2016] QCAT 317 Member Browne.
[2] [2020] QCAT 110, [6].
[3] 'Building dispute', 'domestic building dispute' and 'reviewable domestic work' in Schedule 2 to the QBCC Act.
[4] Codelfa Construction Pty Ltd v State Rail Authority of NSW (1982) 149 CLR 337 at 352.
[5] Applicant submissions dated 19 February 2020, paragraphs 1 to 3.
[7] For examples of knowledge being absent, see Victoria Laundry (Windsor) Ltd v Newman Industries Ltd [1949] 2 KB 528; Seven Seas Properties Ltd v Al-Essa (No 2) [1993] 1 WLR 1083 at 1088-1089; Carpenter v McGrath (1996) 40 NSWLR 39 at 61; Castle Constructions Pty Ltd v Fekala Pty Ltd (2006) 65 NSWLR 648; [2006] NSWCA 133 at [34]-[53].
[10] Daniel John Marino v Keith Howe [2019] QCAT 390.
Sharma & Ors
Woolfson [2020] QCAT 271
Augustine & Anor v SJ Builders Pty Ltd & Anor [2018] QCAT 248
Bartlett v Contrast Constructions Pty Ltd [2016] QCATA 199
Castle Constructions Pty Ltd v Fekala Pty Ltd (2006) 65 NSWLR 648; [2006] NSWCA 133
Daniel John Marino v Keith Howe [2019] QCAT 390
Environmental Systems Ply Ltd v Peerless Holdings [2008] VSCA 26; (2008) 19 VR 358
Harrison & Anor v Meehan [2016] QCATA 197
Lyons v Dreamstarter Pty Ltd [2011] QCATA 142
Lyons v Dreamstarter Pty Ltd [2012] QCATA 71
Mair Renovations v Miller [2016] QCAT 317
Partington & Anor v Urquhart (No 4) [2019] QCATA 96
Rainbow Builders Pty Ltd v The State of Queensland through the Department of Housing and Public Works (No 2) [2016] QCAT 497
Rigall & Anor v Thompson [2010] QCA 144
Stewart v Scott trading as Fantasy Pools Brisbane [2020] QCAT 110
Tamawood Ltd v Paans [2005] QCA 111
The Commonwealth v Amann Aviation [1991] HCA 54; (1991) 174 CLR 64
(1991) 174 CLR 64
(1996) 40 NSWLR 39
(2006) 65 NSWLR 648
(2008) 19 VR 358
(1982) 149 CLR 337