[2023] NSWLEC 1523
Land and Environment Court (NSW)
2023-05-31
Original judgment source is linked above.
Judgment
Statutory framework
State significant development
Permissibility of development on the site
Proposal in context
Site and setting
Issues for evaluation and judgement structure in response
Noise issues
Selected glossary
Introduction
Operational noise limits under current licence
Noise receiver areas
Project noise trigger levels
Background noise levels and intrusiveness noise trigger levels
Amenity noise trigger levels
Conclusion on PNTL interpretation
Operational noise limits as presented empirically in consent conditions by the parties
First respondent's position
Applicant's position
Outline findings on operational noise limits and link to other disputed consent conditions
Conceptual approach
Outline findings on empirical noise limits as codified in consent conditions.
First respondent's proposed LAFmax noise limits and related conditions
Current operating conditions
Summary of the positions adopted by the parties in regard to proposed operating hours
Key differences between the parties
Evidence
Consideration
Identification of benchmark receivers and future monitoring via consent conditions
Consideration
Table 2 to Condition C4 - identifying sites for noise performance monitoring
Introduction
Cleaning and maintenance
Initial reporting period
Noise enhancing conditions and very noise enhancing conditions
Deferred commencement conditions (Conditions A1-A3 for both parties)
Post approval oversight by regulators (applicant's proposed conditions B2-B3 - first respondent's proposed conditions B2-B4)
Staging of proposed increased throughput and surrender of existing consent (applicant's proposed Conditions B5-B8 and B12-B14 - first respondent's proposed Conditions B6-B9 and B15-B17)
Operating hours (applicant's proposed Conditions B9-B10 - first respondent's proposed Conditions B10-B13)
Evidence of consultation (applicant's proposed Condition B15 - first respondent's proposed Condition B18)
Servicing of monitoring equipment (applicant's proposed Condition B23 - no equivalent first respondent condition)
Applicability of guidelines (first respondent's proposed Condition B28 - no equivalent applicant condition)
Flooding impacts (applicant's proposed Condition C1-first respondent's proposed Condition C1(a))
Removal of vegetation (applicant's proposed Condition C1 - first respondent's proposed Condition C1(b))
Operational noise limits (applicant's proposed Conditions C3-C6 - first respondent's proposed Conditions C3-C8)
Noise performance monitoring (applicant's proposed Conditions C7-C8 - first respondent's proposed Conditions C9-C12)
Operational noise management (applicant's proposed Conditions C9-C11 - first respondent's proposed Conditions C13-C15)
Air quality monitoring (applicant's proposed Condition C15 - first respondent's proposed Conditions C19-C20)
Dust minimisation (applicant's proposed Conditions C16-C17 - first respondent's proposed Conditions C21-C22)
Air emissions controls (applicant's proposed Condition C18 - first respondent's proposed Condition C23)
Operational air quality management plan (applicant's proposed Condition C19 - first respondent's proposed Condition C24)
Air quality annual report / air quality audit (applicant's proposed Conditions C21-C22 - first respondent's proposed Conditions C26-C27)
Parking (applicant's proposed Condition C24-C25 - first respondent's proposed Condition C29-C30)
Operational traffic management plan (applicant's proposed Condition C27 - first respondent's proposed Condition C30)
Operating Conditions (applicant's proposed Condition C27 - first respondent's proposed Condition C32)
Fire management - (applicant's proposed Condition C31 - first respondent's proposed Condition C35)
Dangerous goods (applicant's proposed Conditions C33-C34 - first respondent's proposed Conditions C38-C41)
Emergency services information package (applicant's proposed Condition C36 - first respondent's proposed Condition C43)
Imported soil (applicant's proposed Condition C37 - first respondent's proposed Condition C44)
Discharge limits (applicant's proposed Condition C40 - first respondent's proposed Condition C47)
Water management system (applicant's proposed Condition C41 - first respondent's proposed Condition C48)
Flood management (applicant's proposed Conditions C42-C44 - first respondent's proposed Conditions C49-C51)
Water management plan (applicant's proposed Conditions C45 - first respondent's proposed Conditions C52)
Waste management plan (applicant's proposed Conditions C47-C48 - first respondent's proposed Conditions C54-C55)
Waste monitoring program (applicant's proposed Condition C49 - first respondent's proposed Condition C56)
Community consultation plan - (proposed Condition C65 - both parties)
Management plan requirements (proposed Condition D1 - both parties)
Operational environmental management plan (proposed Condition D4 - both parties)
Revision of strategies, plans and programs (applicant's proposed Condition D5 - first respondent's proposed Condition D5-D6)
Independent audit (applicant's proposed Conditions D12-D13 - first respondent's proposed Conditions D13-D14)
Access to information (applicant's proposed Condition D15 - first respondent's proposed Condition D16)
Jurisdictional considerations
Transport and Infrastructure SEPP
State Environmental Planning Policy (Resilience and Hazards) 2021
Hazardous and offensive development
Contamination and remediation
Blacktown Local Environmental Plan 2015 (BLEP)
Other provisions of s 4.15(1) of the Environmental Planning and Assessment Act
Conclusion
Directions
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 13 September 2023
Sell & Parker Pty Ltd
Minister for Planning
(2008) 160 LGERA 20