austlii:qld/QBCCMCmr/2025/393
General information, not legal advice.
QBCCMCmr
2025-11-05
Original judgment source is linked above.
1. That the Body Corporate engage a suitably qualified engineer within 14 days to inspect the full length of the retaining wall and fence behind Lot 21 and immediately implement all necessary safety recommendations. These recommendations should include, but not be limited to, temporary safety fencing, stabilization, and erosion-control works.
2. That the Body Corporate preserve and provide copies of all records relating to the wall, fence, and gardening contracts to both the applicant and the Commissioner within 14 days. This is urgent because months of refusal risk the loss or alteration of evidence before adjudication.
3. A temporary restriction on new commitments or non-urgent payments to the conflicted gardening contractor pending determination, requiring any genuinely urgent safety works to proceed only via an independent contractor.
• Payments to David Henderson have allegedly never been ratified or disclosed.
• The Secretary, Treasurer, and Chairperson are friends and have served together for about seven years.
• EGM paperwork sought to ratify payments to David Henderson for the last four years and included his new tender, but excluded the applicant's previously provided motions.
• The EGM voting papers issued 8 October 2025 seek to ratify payments dating back to 2021 and present David Henderson's quote as the cheapest by excluding the full cost of green-waste disposal, which is included in other tenders.
• Deck (2020): The owner sought retrospective approval for a timber deck, claiming it was self-assessable under Brisbane City Council guidelines. The Committee granted conditional approval, placing full responsibility for all costs, future repairs, maintenance, liability, and compliance on the Lot Owner.
• Gate (2025): In August 2025, the owner installed a gate in the shared dividing fence without prior approval. The Committee issued a formal direction requiring the owner to either remove the gate and reinstate the fence or provide proof of qualified installation, insurance, and accept ongoing responsibility for maintenance and liability, citing non-compliance with by-laws and safety requirements.
1. That the Body Corporate engage an engineer within 14 days to inspect the retaining wall and fence behind Lot 21 and implement safety measures including temporary safety fencing, stabilization, and erosion-control.
2. That the Body Corporate preserve and provide copies of all records relating to the wall, fence, and gardening contracts to both the applicant and the Commissioner within 14 days.
3. A temporary restriction on new commitments or non-urgent payments to the body corporate gardener pending determination, requiring any urgent safety works to proceed only via an independent contractor.
An adjudicator may make an order that is just and equitable in the circumstances (including a declaratory order) to resolve a dispute, in the context of a community titles scheme, about-
(a) a claimed or anticipated contravention of the Act or the community management statement; or
(b) the exercise of rights or powers, or the performance of duties, under the Act or the community management statement; or
(c) a claimed or anticipated contractual matter about-
(i) the engagement of a person as a body corporate manager or service contractor for a community titles scheme; or
(ii) the authorisation of a person as a letting agent for a community titles scheme.
(1) The adjudicator may make an interim order if satisfied, on reasonable grounds, that an interim order is necessary because of the nature or urgency of the circumstances to which the application relates.
Examples
1. The adjudicator may stop the body corporate from carrying out work on common property until a dispute about the irregularity of proceedings has been investigated and resolved.
2. The adjudicator may stop a general meeting deciding or acting on a particular issue until it has been investigated and resolved.
(2) An interim order
(a) has effect for a period (not longer than 1 year) stated in the order; and
(b) may be extended, varied, renewed or cancelled by the adjudicator until a final order is made; (c) may be cancelled by a later order made by the adjudicator; and
(d) if it does not lapse or is not cancelled earlier, lapses when
(i) the application is withdrawn; or
(ii) the commissioner gives the person who made the application a written notice under section 241 rejecting the application; or
(iii) a final order is made by an adjudicator to whom the application is referred. ...
The legal principles governing the disposition of an application for interlocutory injunction were discussed by me in Stacks Managed Investments Ltd v Tolteca Pty Ltd [2015] QSC 234 at 3 to 5 and again in Tribal Health Pty Ltd v Flush Fitness Pty Ltd [2016] QSC 103. In the latter case I summarised relevant principle in these terms (at [23]):
(a) The law in Australia has long regarded it to be necessary to make two main inquiries: (i) whether the applicant has shown that it has a prima facie case; and (ii) whether the applicant has shown that the balance of convenience favours the granting of the relief claimed.
(b) The significance of the requirement that a prima facie case be shown is elaborated upon in Australian Broadcasting Corporation v O'Neill (2006) 227 CLR 572 and Live Earth Resource Management Pty Ltd v Live Earth LLC [2007] FCA 1034 at [11] to [13].
(c) The considerations brought to bear on the balance of convenience requirement were the subject of discussion in Australian Broadcasting Corporation v O'Neill and Bowen Central Coal Pty Ltd v Aquila Coal Pty Ltd [2011] QCA 334, the latter case clarifying that the adequacy of an award of damages and the question of the sufficiency of the usual undertaking were to be considered as part of the totality of the balance of convenience question.
(d) The progression of the two main inquiries is not a mechanical exercise. Whether the relief sought is prohibitory or mandatory, the Court should take whichever course appears to carry the lower risk of injustice if it should turn out to have been "wrong" in the sense of granting an injunction to a party who fails to establish his right at an ultimate trial, or in failing to grant an injunction to a party who succeeds at trial. In making that decision, the Court should weigh in the balance all relevant factors, including matters pertaining to the strength of the case to be tried and the balance of convenience.
3. PTG - $3,333.00 plus the following:[10]
Given the retaining wall is failing this is always a risk of damage / failure occurring to anything within the zone of influence above the wall as a result. As a matter of general advice we usually recommend in these instances that if failure has been identified that access should be limited to the area directly above the retaining wall for a distance at least equal to the height of the wall (i.e for a 1m high wall do not access within 1m horizontal behind the top of the wall) until such time as rectification / replacement of the retaining wall has occurred.
"Pursuant to section 205 of the BCCM Act, I formally require, within 7 days of this notice, copies of all Body Corporate records (including but not limited to committee and general meeting minutes, motions, correspondence, quotes, invoices, contracts, and conflict-of-interest declarations) that:
-relate to the retaining wall and fence, including any engineering, inspection or repair proposals, and
-relate to the gardening contract, including any tenders, approvals, payments, and any actual or perceived conflicts of interest.
In addition, I specifically request all historical records from the date the current gardening contractor was first engaged to the present that concern:
-the initial appointment, tendering or approval of the gardening contract,
-any extensions, renewals or amendments of that contract, and
-all conflict-of-interest declarations, abstentions from voting, or related correspondence at any time since the gardener was first engaged.
For the avoidance of doubt, this is a request for the committee or its manager to identify and provide the relevant records directly to me. It is not a request to merely grant access for me to inspect or search through the entire record set myself."
[1] From provided photographs it would appear that these were part of the original build
[5] Also described as a serious question to be tried.
[6] SDW2 Pty Ltd v JLF Corporation Pty Ltd [2017] QSC 001
Australian Broadcasting Corporation v Lenah Game Meats [2001] HCA 63
[7] From provided photographs it would appear that these were part of the original build
[8] See page 99 of interim submissions from body corporate.
[10] Potentially adding up to $15,741.50.
[11] For example uncompacted filled sites and sites subject to land slippage.
[12] As opposed to a standard "deemed to satisfy" footing design
[13] The Groves No. Four Minyama [2017] QBCCMCmr 371 at [27]
SDW2 Pty Ltd
JLF Corporation Pty Ltd
SDW2 Pty Ltd v JLF Corporation Pty Ltd [2017] QSC 001
Australian Broadcasting Corporation v O'Neill [2006] HCA 46
(2006) 227 CLR 572