20 The Applicant and Respondent entered into a contract for works on 25 November 2016, Works were completed on 23 December 2017. Works included (but not limited to) renovations to the ensuite, main bathroom, balcony, awning, rear verandah, roof and installation of timber flooring.
21 In 2017/2018 remediation works were undertaken which were unsuccessful in preventing water ingress in various areas identified in the reports prepared by The Property Inspectors dated October 2023 and March 2024 and Awesim dated July 2024 and the joint report of August 2024.
22 In 2019 further remediation works were undertaken which were unsuccessful and damage from water ingress continued.
23 No works or proceedings were able to be commenced between 2020 and early 2021 due to the Covid-19 Pandemic.
24 In 2021, in response to a request by the Applicant that the Respondent attend to determine where the water ingress was coming from, the Respondent advised the Applicant to contact the Applicant's insurer as he was unable to attend to undertake the remediation works.
25 Proceedings were commenced by the Applicant due to the failure of the Respondent to address the issues raised by him in relation to the water ingress.
26 In October 2023, the Respondent was served with the Report of The Property Inspectors, Emilio Calandro.
27 The Respondent did not file any evidence in reply apart from a number of emails without any context between himself and his insurer.
28 The Respondent did not participate in the First Proceedings or appear at the Hearing. The Applicant was successful in those proceedings, including in relation to costs.
29 The Respondent then filed the Set Aside Application contending that it was deprived of the ability to participate in, or defend the First Proceedings. It was successful.
30 A new Hearing date was allocated for 22 August 2024 (these proceedings) more than 15 months after the commencement of the proceedings.
31 As a result of the Set Aside Application, further directions were made giving the Respondent further time to file and serve expert material in reply and a direction that upon filing the expert evidence in reply, the parties were to provide a joint report.
32 The joint report identified seven (7) individual areas to be remediated:
(a) Master Bedroom and Ensuite
(b) Ensuite & Bathroom S bends
(c) First Floor Timber Flooring
(d) Main Bathroom
(e) Roofing
(f) External - Northern Wall
(g) External - Back Veranda
33. By the Hearing of these proceedings the Applicant had already incurred costs of the First Proceedings, the Set Aside Application and these proceedings.
"[T]he respondent's conduct before and after the commencement of these proceedings, was unreasonable and when taken as a whole, engages s 60(3)(b), (f) and (g) or the Tribunal's general discretion in s 60(2)-(3)."
(1) That the respondent "fundamentally refus[ed] to undertake any works to the property", which the applicant submitted was "entirely analogous" to the example given by McHugh J in Lai Qin "where a defendant refuses to exercise power such that the 'plaintiff had no reasonable alternative but to commence a litigation'".
(2) That the respondent unreasonably prolonged the time taken to complete the proceedings - by failing to appear at the first hearing on 19 February 2024. The applicants submitted that, to the extent that the respondent's failure to appear was due to default by its former solicitors, that was not a matter that would make it just that the applicant should bear the costs.
(3) That the respondent unreasonably defended the proceedings. The applicant submitted that the respondent consented to undertake works on the day of the hearing "which it could have agreed to over a year earlier" or "by undertaking the works proposed in the ... Orders [made on 19 February and subsequently set aside]".
1. The original leak was repaired during construction with all parties happy with the outcome.
The 2nd repairs were assessed by the insuring assessor and works were completed to this scope of works and the applicant's approvals.
2. Both parties entered discussions with the respondent stating clearly from the start that they would rectify all the issues after going through the correct processes.
The respondent's insurer made it noticeably clear that the applicant needed to show evidence of the claim. The insurers assessor visited the site and made this clear to Mr Schach.
Months went by with the applicant not doing this.
During our first 2 NCAT meetings, the NCAT member also informed the applicant that he would need to get a report and show evidence of the claim.
After this the applicant finally conducted a report which has cause the extensive delays.
From the first phone from Mr Schach to Dowdy Constructions, Dowdy Constructions has always agreed to do the repairs, without any need for it to go to NCAT.
If Mr Schach had shown evidence of the claim from the very beginning, then the works would be already completed by now and neither party would have incurred any legal costs.
...
9. The initial report proved by Mr Schach was a non-invasive report showing 45 items as defects.
A second report was then conducted which was invasive and showed evidence of the claim which Dowdy Constructions had been waiting for, for months.
The report provided was not in the format of a Scott Schedule that is required by NCAT.
...
Dowdy Constructions engage Awesim consulting as their Expert witness report. Awesim consulting narrowed the 45 defects down to 7 main items which both the applicant and Mr Schach expert witness agreed with.
Dowdy Constructions expert witness had requested the reports a number of times from the applicants' solicitors which delayed resolution, and he also requested that the applicant's expert provide their findings in an actual Scott schedule.
The final result from the applicant's witness was still not in a Scott schedule and was not received by Dowdy Constructions or by Awesim Consulting.
We were handed a copy at the hearing after we asked the applicants solicitor for a copy.
Awesim Consulting then had to go out to read the incorrect laid format report.
10. At the start of the hearing the NCAT member and Dowdy Constructions were made aware that Mr Schach expert witness only had 1 hr before he had to leave to catch a flight.
Dowdy Constructions Expert witness was engaged to allow the entire day as per the NCAT order.
Dowdy Constructions requested that we try to resolve the issues in an outside meeting room as now they had the evidence for the claim and as stated always intended to carry out the works.
7. The hearing dates had been changed a number of times by Mr Schach and when the final date was posted out it was sent to Dowdy Constructions accountant and not directly to Dowdy Constructions. Dowdy Constructions email and phone number are for public display online and know by Mr Schach and his legal team.
Dowdy Constructions also did not receive a phone from the court on the day of the hearing when it was evident he was late.
(a) The Applicant had been seeking assistance and for the works to be undertaken by the Respondent from 2020 until May 2023 when the proceedings were commenced. At all times, the Respondent was evasive, unable to be contacted and failed to attend to the necessary rectification.
(b) This matter was a claim for defective works and as such, there was no requirement for the Applicant to prove to the Respondent's insurer that there were defective works.
(c) It was only after the Directions Hearing on 5 October 2023 and the continued failure of the Respondent to attend to investigate the continual water ingress that the Applicant incurred legal costs including the costs of the report writer.
(a) The experts had met in conclave prior to the hearing in order to prepare the joint report.
(b) The expert for the Respondent had not read the joint report prior to the Hearing notwithstanding that he had been back in Australia (after going overseas before the report had been finalised) for at least 3 days and required additional time in the morning of the Hearing to prepare;
(c) Agreed on most points with minimal matters to be resolved in respect to the proposed Scope of Works;
(d) The Respondent sought to negotiate a settlement with the Applicant;
(e) The evidence required to be adduced from the expert on behalf of the Applicant would have only taken 1 hour due to the contents of the joint report.
21 In this case it is apparent from the Senior Member's reasons that, on the basis of the material before him, he was not satisfied, however, without hearing evidence, that the homeowners would be almost certain to succeed. We agree with the builder that the mere fact consent orders are entered into is insufficient to establish that one party would be almost certain to succeed if the matter went to hearing. While there may be circumstances, as in the Gregory matter, where that outcome may have been inevitable, as McHugh J stated, those cases are rare.
22 The fact that the consent orders contain an agreed scope of works does not, in our view, indicate that the Senior Member was bound to accept that, had the matter proceeded to hearing, matters would not have been contested and a similar outcome would have been reached. It was, of course, not permissible for the Senior Member to try a hypothetical action between the parties.
110 It is not sufficient that the Tribunal is almost certain that a work order of some type would have been made. If that were the applicable test, then any consent order for any work in proceedings where the amount claimed or in dispute exceeded $30,000 would result in an order for costs in favour of the owners, irrespective that, had the proceedings been heard to finality, the owners were likely (or even certain) to have failed on substantial issues which may have resulted in the owners not being awarded costs.
111 Rather, the appropriate enquiry is that "even if both parties have acted reasonably, one party was almost certain to have succeeded if the matter had been fully tried so that the party should obtain the costs of the action" (emphasis added) (Kiama Council v Grant [2006] NSWLEC 96 at [80]).
(1) The respondent pay the applicant's costs thrown away by reason of the setting aside of the orders made on 19 February 2024, including the costs of and incidental to the hearing on that date, and the costs of and incidental to the respondent's application to set aside those orders. Such costs to be as agreed or assessed.
(2) The applicant's application for costs is otherwise dismissed.
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
Schach
Dowdy Constructions Pty Ltd [2025] NSWCATCD 84;
(1) That the claim filed by the applicant was for an amount exceeding $30,000 and therefore rule 38 of the Civil and Administrative Tribunal Rules applied, and the successful party in the proceedings was entitled to an order for costs.
(2) Where proceedings are resolved without a hearing on the merits, there is no successful party, save for three "well established exceptions", citing Re: Minister for Immigration & Ethnic Affairs; ex parte Lai Qin (1997) 186 CLR 622; [1997] HCA 6 (Lai Qin) at 624-625.
(3) One of those exceptions is where "both parties have acted reasonably, but a Court or Tribunal can be confident of the outcome or that a party would 'almost certainly' succeed."
(4) This case falls into that category.
(5) Alternatively, a costs order may be justified pursuant to s 60 of the NCAT Act independently of the Lai Qin principles.
(6) Where s 60 applies, the Lai Qin principles "must give way to s 60 where they conflict with s 60 or where s 60 imports additional considerations or principles", citing Roberts v The Owners - Strata Plan No 4393 [2023] NSWCATAP 119.
(7) A second exception under the Lai Qin principle is where one party has acted unreasonably, in respect of which "the Tribunal may have regard to known circumstances, not in dispute between the parties, without reviewing large swathes of evidence", citing Nichols v NFS Agribusiness Pty Ltd [2018] NSWCA 84.
(1997) 186 CLR 622