[2025] VCAT 354
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2025-04-24
Revision J
Original judgment source is linked above.
Buildings and works, Commercial 1 Zone, use of land to sell or to consume liquor, subdivision of land, signage.
Sanctuary Lakes Club Limited trading as Sanctuary Lakes Golf Club
Sanctuary Lakes Village Pty Ltd v Wyndham CC [2025] VCAT 354
Business identification signage that exceeds 8 square metres and internally illuminated signage that exceeds 1.5 square metres
J Cicero, of Best Hooper. Expert evidence was provided by:
For Sanctuary Lakes Club Limited trading as Sanctuary Lakes Golf Club
Development of the land for a medical centre and ancillary pharmacy, six (6) food and drink premises, a convenience store, a bottle shop, two (2) retail premises, two (2) office tenancies and landscaping and associated car parking, display of signage, use of the land for the sale and consumption of liquor, and a two (2) lot subdivision.
Application under section 77 of the Planning and Environment Act 1987 (Vic) - to review the refusal to grant a permit.
Clause 34.01-4 - Construct a building or carry out works
Clause 52.05-11 - Business identification signage that exceeds 8 square metres and internally illuminated signage that exceeds 1.5 square metres
The site is located on the corner of Greg Norman Drive and an un-named private road, in the Sanctuary Lakes Estate. Part of the un-named road exists within the lands title and the remainder of the carriageway of this un-named road exists within the abutting Golf Club site. The land is currently vacant.
Unaccompanied prior to and after the conclusion of the hearing
What is the relevant physical and strategic context


Figure 2: Amended plans. Source: Council submission
ARE THE PROPOSED BUILDINGS AND WORKS AN ACCEPTABLE RESPONSE TO THE SITE'S PHYSICAL AND STRATEGIC CONTEXT?
IS THE PROPOSED CAR PARKING, LOADING AND VEHICLE ACCESS ACCEPTABLE?
Figure 3: NearMap satellite image showing the Subject Land in red and the Club's Land in green. Source: Golf Club submission
ARE THERE ANY OTHER UNREASONABLE OFF SITE AMENITY IMPLICATIONS?
IS THE USE OF THE LAND TO SELL OR CONSUME LIQUOR ACCEPTABLE?
Business identification signage that exceeds 8 square metres and internally illuminated signage that exceeds 1.5 square metres
(a) All items to be relocated or removed to be indicated on plans (i.e cameras within local road reserve). The camera in the Car Park Access is to be relocated to a new location to the satisfaction of the Council and at the cost of the developer.
(b) Acoustic fencing in accordance with the recommendations of Mr Leo in his statement of evidence dated 27 February 2025.
(c) Relocation of the concertina doors to the café to the eastern façade and the replacement of the concertina doors with fixed glazing.
(d) Rear access doors to the western façade should be a minimum of 35mm thick solid core with acoustic seals and be self-closing.
(e) A notation to state "Acoustic boundary fencing to be at the full cost of the permit holder".
(f) A notation to state "Any mechanical plant with line-of-sight to the window of a nearby dwelling is to be provided with solid perimeter screening with a minimum surface mass of 9 kg/m2 , the screening should be at least 1 metre higher than of the top of the plant equipment, and the side facing the plant equipment should be lined with 32 kg/m2 acoustic insulation".
(g) Detailed signage and line marking for all car parking spaces and accessways.
(h) Relocation of emergency service vehicle car space inline with other parking spaces.
(i) A table to show allocated car parking schedule.
(j) Amended Elevation plans to show:
- Acoustic boundary fencing including dimensions, colours, and materials.
- All internal elevations
(k) Updated plans are required to align with SMP, BESS and STORM commitments.
- Remove the gas meter shown in the car park as no gas connection is proposed.
- Glazing Visible Light Transmission of 40% or above must be noted on elevations and the Finishes schedule.
- Solar panels must be annotated with inclination angle, per BESS inputs.
- Separate bins for each waste stream must be shown at each tenancy (in accordance with WMP and BESS Waste credits)
(l) All appropriate commitments and initiatives from the Sustainability Management Plan required under Condition 5 of this permit must be indicated/shown within the plans. Where measures cannot be visually shown, include a 'notes table' or 'ESD Schedule' providing details of the requirements.
(m) Any changes as required by condition 56 of the permit.
(a) All trees proposed to be removed;
(b) Clearly drafted at a scale of 1:100 or similar with a north point and legend.
(c) Clear graphics to indicate trees (deciduous or evergreen), shrubs, ground covers, grass etc.
(d) Botanical and common name, pot size, quantity, planting density and size at maturity of all plantings.
(e) Notated planting specification drawings.
(f) Location and depth of all surface treatments with materials and colours notated.
(g) Outline of all built features including buildings, fences, storage, water tanks and utility structures etc.
(h) Construction details of any proposed landscape treatment.
(i) Mark all crossovers.
(j) Any vegetation or structures within the nature strip.
(k) Any necessary removal and subsequent replacement of street trees to the satisfaction of the Responsible Authority.
(l) An increase in planting density to the raingardens, in line with Melbourne Water guidelines.
(m) Provide a typical section detail through the raingarden showing how driveway run-off will discharge into the raingarden.
(n) Any changes as required by condition 1 of the permit.
(o) Any changes as required by condition 5 of the permit.
(a) Amend the Energy section to include solar panel orientation that aligns with BESS inputs and development plans.
(b) Amend the raingarden diagram to reflect the 300mm extended detention depth.
(c) Provide details of the EV charging infrastructure to be installed (as a minimum, install cabling and conduits to the nominated parking spaces with dedicated distribution board(s) to support the future installation of Level 2 32 Amp EV chargers or fast charging).
(d) Specify in the Indoor Environment Quality section that glazing with a VLT of 40% or above will be installed (this is a pre-requisite of the Green Star Hand Calculation daylight assessment)
(a) The number and size of delivery and waste collection vehicles accessing the site;
(b) The propping location of delivery and waste collection vehicles within the site (must be within a dedicated loading bay or chevron line-marked area), to the satisfaction of the Responsible Authority. This does not include small vans and trucks which are able to use standard car parking bays;
(c) Swept path diagrams indicating said vehicle access manoeuvring within the site;
(d) The timing of said vehicle access and egress. All vehicle access must occur outside of peak site operational periods to avoid impacts to the functionality of the accessways;
(e) No loading, collection or otherwise is permitted from the road reserve. All operations must occur on-site;
(f) Loading, unloading and waste collection arrangements must occur in accordance with the Acoustic Report prepared by SLR dated December 22, 2022 (or as amended).
(a) All respective floor areas to be updated within the document along with associated waste generation rates based on the Condition 1 plans;
(b) Timing of collections set outside of peak operating hours of site and limited to Monday to Saturday 7.00am-6.00pm;
(c) Swept path diagrams indicating vehicle manoeuvring and propping within the waste storage location;
(d) All propping locations must be within a dedicated loading bay or dedicated chevron line-marked area, except for collection vehicles from within car parking bays outside of the business hours of 9.00am-5.00pm;
(e) Any collection timing or vehicular controls required to comply with the Loading Management Plan required under Condition 12 of this permit.
(a) Directional signage and other measures to direct access and egress to site;
(b) Parking restrictions and proposed enforcement of restrictions;
(c) Allocation of car spaces in accordance with the allocation schedule shown on the endorsed plans, including the restriction and control of access to staff car parking spaces; and
(d) Management of parking for all uses.
(a) the contact name and phone number(s) of the site manager,
(b) bulk excavation,
(c) management of the construction site,
(d) land disturbance,
(e) hours of construction, including program/duration of works
(f) noise,
(g) control of dust, spoil and debris
(h) public safety,
(i) traffic management plans suite of all stages,
(j) construction vehicle road routes (including full swept path analysis of largest anticipated vehicles to site),
(k) discharge of any polluted water,
(l) security fencing, disposal of site waste and any potentially contaminated materials,
(m) crane locations during construction (if applicable),
(n) location of site offices, and onsite staff parking,
(o) redirection of any above or underground services,
(p) site lighting during any night works.
(q) all vehicle, personnel and equipment access to be from Greg Norman Drive.
Once submitted and approved the requirements contained in the Construction Management Plan must be carried out to the satisfaction of the Responsible Authority during the construction of the permitted development.
Except with the written consent of the Responsible Authority, within the tree protection zone, the following are prohibited:
(a) vehicular or pedestrian access
(b) trenching or soil excavation
(c) storage or dumping of any soils, materials, equipment, vehicles, machinery or waste products
(d) entry and exit pits for underground services
(e) any other actions or activities that may result in adverse impacts to retained tree(s)
Unless approved otherwise by the responsible authority, all commercial/industrial storm water systems must incorporate measures to satisfy the objectives of "Urban Stormwater Management Guidance" (publication 1739.1, EPA 2021) to reduce or retain in total:-
(a) 80% of suspended solids;
(b) 45% phosphorus;
(c) 45% nitrogen; and
(d) 70% litter/gross pollutants larger than 5mm.
Before any drainage works associated with the development commence, detailed construction plans must be submitted to and approved by the Council.
(a) Use of textured or rough services that make it difficult to apply graffiti.
(b) Use of permeable fencing instead of solid walls.
(c) Construct buildings with high-density, low absorbency materials.
(d) Use anti-graffiti coating to protect the surface when building or revitalising the walls (including façade and fencing).
(e) Install sensor lighting and/or enhance surveillance to deter graffitists.
(f) Break up large surfaces to minimise the canvas available for graffitists.
(g) Use measures to make the surface less accessible to the public.
(a) The development is constructed in accordance with all relevant endorsed documents required under this permit; including development plans, streetscape plans, waste management plan, loading management plan, sustainability management plan etc.
(b) The parking area(s) shown on the endorsed plan(s) have been constructed to the requirements and satisfaction of the Responsible Authority.
(c) The streetscape area(s) shown on the endorsed plan(s) have been constructed to the requirements and satisfaction of the Responsible Authority and at no cost to the Responsible Authority.
(a) dazzle or distract drivers due to its colouring;
(b) be able to be mistaken for a traffic signal because it has, for example, red circles, octagons, crosses or triangles; or
(c) be able to be mistaken as an instruction to drivers.
No layout alteration - liquor license (red line plan)
(a) At-grade car spaces outside of Block C within common property;
(b) Dimensions of both lots and their boundaries, and
(c) Common property areas with the development plans.
Certified Plans to be referred under S8 of Subdivision Act
Agreement with relevant authorities for utility services
(a) Construct all the parking areas, access lanes, driveways and associated works shown on the plan such that they are:
- constructed and available for use in accordance with the plan approved by the Responsible Authority; and
- formed to such levels and drained so that they can be used in accordance with the plan; and
- treated with an all-weather seal; and
(b) Complete the landscaping on the site in accordance with the endorsed plans. The landscaped areas shown on the endorsed plans must be planted and maintained to and once completed must not be used for any other purpose.
(c) Construct the site stormwater and drainage system to the satisfaction of the Responsible Authority.
(a) telecommunications network or service provider for the provision of telecommunication services to each lot shown on the endorsed plan in accordance with the provider's requirements and relevant legislation at the time; and
(b) a suitably qualified person for the provision of fibre ready telecommunication facilities to each lot shown on the endorsed plan in accordance with any industry specifications or any standards set by the Australian Communications and Media Authority, unless the applicant can demonstrate that the land is in an area where the National Broadband Network will not be provided by optical fibre.
(a) a telecommunications network or service provider that all lots are connected to or are ready for connection to telecommunications services in accordance with the provider's requirements and relevant legislation at the time; and
(b) a suitably qualified person that fibre ready telecommunication facilities have been provided in accordance with any industry specifications or any standards set by the Australian Communications and Media Authority, unless the applicant can demonstrate that the land is in an area where the National Broadband Network will not be provided by optical fibre.
(a) The development is not commenced within two (2) years of the date of this permit; or
(b) The development is not completed within four (4) years of the date of this permit.
(c) The Plan of Subdivision is not certified within two (2) years of the date of this permit; or
(d) If the subdivision permitted by this permit is not completed within five (5) years from the date of the certification of the Plan of Subdivision
The Responsible Authority may extend the periods referred to if a request is made in writing whereby either of the following instances apply:
[1] The submissions and evidence of the parties, any supporting exhibits provided to the hearing and the statements of grounds filed have all been considered in the determination of the proceeding. In accordance with the practice of the Tribunal, not all of this material will be cited or referred to in these reasons.
[3] Knox City Council v Tulcany Pty Ltd [2004] VSC 375.
Sanctuary Lakes Village Pty Ltd
Wyndham CC [2025] VCAT 354