Systems of work in place prior to the incident
- At the time of the incident, no exclusion zones were in place around the crane. Workers and other persons including Mr Graff and Mr Sitauti were not given any information or a SWMS about working safely near the crane. Mr Naesse was not notified that a crane would be working on that day and was not given any information relating to an exclusion zone, risk assessment or other safety information for the Erectus workers working in the vicinity of a crane.
- The defendant advised HLH that Mr Dessens' duties were to be general labouring duties such as keeping the work area clean, moving material and assisting installers where required. Mr Dessens' experience consisted of four months working as a general labourer. Mr Dessens informed HLH that he had no "tickets" or qualifications, other than a white card.
- The defendant supplied a site specific Work Health and Safety Plan to Arise dated 10 October 2017 (WHS Plan). The WHS Plan provided that Mr Georges was the defendant's employee on site with responsibility for the defendant's Scope of Works and for its safety and that the project supervisor was Mr Hamburger. The Scope of Works was noted to include, "supply and take delivery of AFS panels". The Risk Register identified the risk of "falling load" and "striking objects" from the tasks of delivery of panels and cranage of panels onto slab. The control measures identified were the setting up of an exclusion zone for the delivery task, using ticketed and licensed personnel, and use of a spotter with a dogman for the cranage task. The WHS Plan included a reference to AS 2550 relating to mobile plant and equipment.
- The defendant provided SafeWork with a SWMS No HSE-006 for the work at the site (the defendant's SWMS). It was an agreed fact that the SWMS was signed by workers including Mr Dessens and that Mr Dessens denies ever seeing or signing the SWMS.
- The defendant's SWMS contained, at entry number 7, the task of "Taking delivery of the AFS Panels". The potential hazards identified included "objects falling from height" and "possible traffic/pedestrian hazards". The initial risk rating was stated to be "1". This was the highest risk rating representing a serious risk of death, permanent disability or serious injury that was very likely or likely to happen. The hierarchy of control measure implemented was stated to be the 3rd priority, being "isolating the hazard from anyone who could be harmed". The control measures identified were:
1. Set up exclusion zone using traffic controls by the head contractor;
2. Only qualified dogmen to attach and direct load;
3. Pallet Lifter to be used in accordance with crane SWMS and manufacturer's instructions;
4. AFS lifting gear to be visually checked for certification; and
5. AFS SWMS must be read in conjunction with this SWMS.
- The residual risk for the task after the control measures were implemented was assessed as "4", indicating that the task was very unlikely to involve a serious injury. The persons identified with responsibility for implementing the control measures were "Head Contractor, Crane Operator, Dogman, HD employee directing delivery". This was the only task in the defendant's SWMS that identified the use of the Pallet Hook.