[2010] QCAT 212
Queensland Civil and Administrative Tribunal
2010-05-13
Original judgment source is linked above.
Ryan v Cornwall [2010] QCAT 212
Section 43A of the Limitation of Actions Act 1974; section 51 of the Domestic Building Contracts Act 2000; effect of section 61 of the Queensland Civil and Administrative Tribunal Act 2009.
David John Ryan and Rene Marea Ryan represented by Brendan Cuddihy of Jeffery Cuddihy & Joyce, Solicitors.
(a) extend a time limit fixed for the start of a proceeding by this Act or an enabling Act;...
(2) An extension or waiver may be given under subsection (1) even if the time for complying with the relevant requirement has passed.
(3) The tribunal can not extend or shorten a time limit or waive compliance with another procedural requirement if to do so would cause prejudice or detriment, not able to be remedied by an appropriate order for costs or damages, to a party or potential party to a proceeding..."
limitation law means a law (including, but not limited to, this Act) that provides for the limitation or exclusion of any liability or the barring of a right of action for a claim by reference to the time when a proceeding on, or the arbitration of, the claim is started.
(2) A limitation law of the State is to be regarded as part of the substantive law of the State.
(3) This section applies to a cause of action that arose before the commencement of this section but does not apply to a proceeding started before the commencement."
Ryan
Cornwall [2010] QCAT 212