[2025] QCAT 519
General information, not legal advice.
Queensland Civil and Administrative Tribunal
2025-12-08
Original judgment source is linked above.
Applicant: F Chen, instructed by Queensland Revenue Office
(a) the Contract did not include kitchen appliances but an oven that can be plugged in has been chosen; and
(b) she engaged the plumber and electrician to connect the Home up to services as this was not part of the Contract.
(a) PUH gave the effluent design to the plumber who they engaged. She did not meet the plumber until he came to her land to install the septic tank;
(b) the intention was PUH would arrange and be on site when the plumber attended. However, due to unforeseen and tragic circumstances, this did not happen, and the Applicant facilitated the plumber's attendance, and the invoice was sent to her "out of kindness and respect for the builder;"[1]
(c) PUH facilitated the electrician's attendance but because Ergon was unable to connect power to the site until a later date, the electrical work wasn't completed at that time;
(d) given the tragic circumstances, the Applicant facilitated the electrician's future site visits, and she was invoiced for the work;
(e) the plumbing and electrical work were arranged as part of the comprehensive building contract. The Applicant contracted with PUH to build a home she could move into;
(f) the Contract did not exclude plumbing and electrical work and therefore forms part of the Contract;
(g) PUH's use of subcontractors is not a disqualifying criterion; and
(h) the time it took for the Respondent to assess the Application has disadvantaged the Applicant and should not be used to redefine the terms or intention of the Contract.
(a) a letter from Hinchinbrook Shire Council addressed to PUH and dated 25 August 2021 indicating the plumbing and drainage plans PUH had lodged for the Home had been approved; and
(b) a letter dated 24 June 2021 from Effluent Disposal Systems indicating investigations and tests had been conducted on the Applicant's land. The letter was addressed to "Whom it May Concern."
...The price of build included all certification - building approvals including plumbing and electrical and was not the responsibility of the owner....
(1) A person who is eligible to apply for a home builder grant under the home builder direction may apply for the grant.
(2) An application for a home builder grant must comply with the home builder direction.
(3) An applicant for a home builder grant is entitled to be paid the grant if -
(a) the applicant or, for a joint application, each of the applicants, complies with the eligibility criteria for the grant under the home builder direction; and
(b) the transaction for which the grant is sought is an eligible home builder transaction; and
(c) the relevant requirement in relation to the eligible home builder transaction has been met.
A comprehensive home building contract made by the freehold owner in Queensland or a person who will, prior to completion of the comprehensive home building contract be the freehold owner of land in Queensland, to have a new home built on the land, if the contract commencement date is between 4 June 2020 and 31 March 2021 (both dates inclusive), and the construction commencement date is on or after the contract commencement date and within 6 months of the contract commencement date.
A comprehensive home building contract means a contract under which a builder undertakes to build a home from the start of the building work to the point where the home is ready for occupation and, if for any reason, the work to be carried out under the contract is not completed, includes any further contract under which the work is to be completed.
...the provision of lighting, heating, ventilation, air conditioning, water supply, sewerage or drainage in connection with a building ...
...the definition of comprehensive home building contract that requires all of the works for the building of the home to completion under one contract. If it was otherwise, the $750,000 cap that is prescribed in the Direction would easily be rendered ineffective by owners simply having various works performed outside of the contract and therefore not considered to be subject to the monetary limit. That clearly is not what was intended.
The learned Tribunal Member has erred, in my respectful view, when he found that the builder being 'responsible' for the work of the other contractor, under the Queensland Building and Construction Commission Act 1991 (Qld) (the QBCC Act) was enough to bring the construction of the home within the one contract it had with the owner such as to satisfy the meaning of "a comprehensive home building contract". The definition uses the words "a contract under which a builder undertakes to build a home form the start of the building work to the point where the home is ready for occupation."[6]
The Appeal Tribunal in Scott-Holland determined that the reasoning in the appeal of Taske was sound and applicable to the decision under review. On appeal Scott-Holland was set aside because the Scott-Holland contract was determined not to be a comprehensive home building contract.
1.2 You agree that this Contract forms the entire Contract under which we will supply and install a complete home through to certification signoff. Please read this Contract carefully and contact us if you have any questions or concerns.
3.3 You agree that, unless we otherwise agree, no Variations will be allowed once the Parties have reached Contract and Design.
3.5 Notwithstanding clause 3.3, if you request a Variation, it must be made in writing, and we may accept or reject the request. If we accept the request, we will inform you in writing of any necessary changes to the Home, the Price and/or this Contract (Proposed Variation).
3.6 You may accept the Proposed Variation by singing and returning it to us (including by email). We will not be required to carry out any works or services related to a Proposed Variation until both Parties have signed the Proposed Variation, at which time it will become a Variation.
3.8 Variations will be priced in accordance with any schedule of rates provided to you by us, or as reasonably determined by us.
19.5 Entire Contract: This Contract contain the entire understanding between the Parties, and supersedes all previous discussions, communications, negotiations, understandings, representations, warranties, commitments and Contracts, in respect of its subject matter.
[1] See page 2 of the Applicant's document titled "OBJECTION NOTES - RUSSO".
[3] The term 'home builder direction' is defined in the Schedule to First Home Owner Grant and Other Home Owner Grants Act 2000 (Qld) and means 'the administrative direction called 'Australian Government HomeBuilder Grant - Queensland' made by the Minister and published on the department's website'.
Revenue v Reynolds [2025] QCATA 58.
[8] Commissioner of State Revenue v Taske [2023] QCATA 121, [24].
Russo
Commissioner of State Revenue [2025] QCAT 519